Who delivers on time?

Every project registered with RERA declares a completion date. We read the regulators' own registers and set those promises against what happened: extensions, completions and projects still overdue, for every registration of the developers we work with.

Checked 6 October 2026 · Select a builder for every project and date

New: Bengaluru builders who deliver on time →

Bengaluru · Karnataka RERA

BuilderRegisteredCompletedOn timeMedian delayOverdue now
Sobha Limited1196453% (34/64)0 mo5
Prestige Group845364% (34/53)0 mo8
Brigade Group703962% (24/39)0 mo6
Puravankara Limited541225% (3/12)5.2 mo12
Assetz Property Group441547% (7/15)0.3 mo4
Godrej Properties401283% (10/12)0 mo3
Sattva Group321267% (8/12)0 mo6
Century Real Estate321443% (6/14)4.5 mo7
Total Environment22650% (3/6)3.7 mo3
Casagrand Builder22633% (2/6)1.7 mo5
Embassy Group15540% (2/5)2.2 mo0
Radiance Realty74100% (4/4)0 mo0
TVS Emerald41Too few—0

Gurugram · HARERA Gurugram

BuilderRegisteredCompletedOn timeMedian delayOverdue now
Signature Global713030% (9/30)4 mo0
DLF Limited453294% (30/32)0 mo1
M3M India452576% (19/25)0 mo0
Emaar India422291% (20/22)0 mo1
Godrej Properties26771% (5/7)0 mo0
Experion Developers171173% (8/11)0 mo0
Central Park16450% (2/4)2.8 mo0
Smartworld Developers14475% (3/4)0 mo0
Elan Group13475% (3/4)0 mo0
Whiteland Corporation12475% (3/4)0 mo0
Sobha Limited10425% (1/4)5.7 mo0
Krisumi Corporation71Too few—0

Tamil Nadu · TNRERA

BuilderRegisteredCompletedCompleted without extensionOverdue now
Casagrand Builder1083161% (19/31)22
TVS Emerald3311100% (11/11)4
Radiance Realty221292% (11/12)1
Appaswamy Real Estates171457% (8/14)0
Alliance Group13333% (1/3)4
Akshaya Pvt Ltd112100% (2/2)7
Brigade Group1010% (0/1)4
Sobha Limited8683% (5/6)2
Prestige Group53100% (3/3)0
Puravankara Limited50—1
Godrej Properties42100% (2/2)0
Urbanrise30—1

“On time” counts completed projects with a recorded completion date that finished on or before the date promised at registration. Builders with fewer than 3 such projects in a city are not given a percentage. Builders with fewer than 3 registrations in a city are not shown for that city.

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • Karnataka RERA — Bengaluru Urban and Bengaluru Rural districts
  • HARERA Gurugram — Gurugram
  • TNRERA — Tamil Nadu building projects
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

How do you know if a builder delivers on time?+

Every project in India must declare a completion date when it registers with the state RERA. The registers then record extensions and, in Karnataka and Haryana, the date a project was completed or received its occupancy certificate. Comparing those dates across all of a builder's projects shows how often it finished by the promised date.

Where does this data come from?+

From the public registers of Karnataka RERA, HARERA Gurugram, TNRERA, read on 2026-10-06. We do not estimate or adjust any figure; each builder page lists every registration we counted with its dates.

Why are some delays not the builder's fault?+

Regulators granted blanket COVID-19 extensions in 2020–21, and approvals or court orders can hold up a project. The registers don't record the reason for a delay, so read the figures as a record of what happened, not a verdict on why.