Property Point

Delivery record · from RERA

Is Sattva reliable?

Per the regulators' own registers, in Bengaluru, 8 of 12 completed projects with a recorded completion date finished by the date promised at RERA registration.

32 registrations · checked 6 October 2026

Bengaluru · Karnataka RERA

32

Registered projects

12 completed · 20 ongoing

67%

Finished by the date promised at registration

8 of 12 completed projects

0months

Median delay past the promised date

Across completed projects (on-time = 0)

6

Overdue now

Ongoing projects past their latest RERA date with no completion filed

Completion = the date of the first occupancy (or completion) certificate recorded on the project's K-RERA page; where none is recorded, the date the builder applied for completion on K-RERA.

Every registration

Sattva projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
SATTVA AANGANEBengaluru East · BengaluruSept 2026Oct 2032NoneIn progress
SATTVA EKATRADoddaballapura · BengaluruSept 2026Mar 2029NoneIn progress
SATTVA SONGBIRD PH 2Bengaluru South · BengaluruMar 2026Jun 2031NoneIn progress
SATTVA CITYYelahanka · BengaluruFeb 2026Feb 2032NoneIn progress
SATTVA AARANYABengaluru South · BengaluruDec 2025Jan 2031NoneIn progress
Sattva Vasanta CoveDevanahalli · BengaluruDec 2025Dec 2030NoneIn progress
Sattva Aeropolis Phase 2Devanahalli · BengaluruSept 2025Oct 2028NoneIn progress
Sattva Vasanta SkyeDevanahalli · BengaluruMay 2025May 2031NoneIn progress
Sattva SimpliCityBengaluru South · BengaluruMar 2025Dec 2025NoneCompleted Jan 2026 · <1 mo late
Park Cubix Phase 2Devanahalli · BengaluruFeb 2025Sept 2029NoneIn progress
Sattva Forest RidgeBengaluru South · BengaluruDec 2024Dec 2029NoneIn progress
Sattva BhumiDevanahalli · BengaluruOct 2024Dec 2026NoneIn progress
Sattva SongbirdBengaluru East · BengaluruSept 2024May 2029NoneIn progress
Sattva LuminaYelahanka · BengaluruSept 2024Nov 2029NoneIn progress
SATTVA SPRINGSBengaluru South · BengaluruJul 2024Sept 2027NoneIn progress
Sattva Knowledge PointBengaluru North · BengaluruJul 2024Jun 2025NoneCompleted Apr 2025 · on time
Green GrovesNelamangala · BengaluruMay 2024Sept 2026NoneOverdue
La VitaBengaluru East · BengaluruDec 2023Jul 2026NoneOverdue
Sattva BlissBengaluru East · BengaluruJan 2023Aug 2027NoneCompleted Jun 2025 · on time
Aeropolis, a project of Sattva GroupDevanahalli · BengaluruMay 2022Jul 2026NoneOverdue
Show all 32 registrations
SALARPURIA-SATTVA ANUGRAHABengaluru North · BengaluruSept 2021Dec 2024NoneCompleted Jun 2024 · on time
SALARPURIA-SATTVA SIGNETBengaluru East · BengaluruJan 2021Aug 2024NoneCompleted May 2024 · on time
SALARPURIA-SATTVA EXOTICBengaluru North · BengaluruApr 2019Nov 2023Aug 2024 (1)Completed Apr 2024 · 4 mo late
Salarpuria Sattva Serene LifeDevanahalli · BengaluruDec 2018Jun 2019NoneCompleted Jan 2024 · 55 mo late
SALARPURIA SATTVA MISTY CHARM LAND OWNER SHAREBengaluru South · BengaluruSept 2018Jan 2023Oct 2023 (1)Overdue
SALARPURIA SATTVA MISTY CHARMBengaluru South · BengaluruMay 2018Jan 2023Oct 2024 (2)Completed Jan 2024 · 11 mo late
salarpuria sattva park cubixDevanahalli · BengaluruOct 2017Mar 2022Dec 2023 (2)Overdue
DIVINITY, a project jointly promoted by Salarpuria and Sattva GroupBengaluru South · BengaluruOct 2017Jun 2021Mar 2022 (1)Completed Mar 2020 · on time
SALARPURIA-SATTVA ANUGRAHABengaluru North · BengaluruOct 2017Jun 2021Mar 2022 (1)Completed Apr 2021 · on time
SALARPURIA-SATTVA OPUSBengaluru North · BengaluruSept 2017Jun 2021Sept 2023 (3)Overdue
SALARPURIA-SATTVA EAST CRESTBengaluru East · BengaluruSept 2017Sept 2020Jun 2021 (1)Completed Mar 2019 · on time
SALARPURIA-SATTVA CADENZABengaluru South · BengaluruSept 2017Jun 2019NoneCompleted Dec 2018 · on time
Companies these projects are registered under (15)
  • Darshita Southern India Happy Homes Private Limited · Bengaluru
  • K M Srinivasa Murthy · Bengaluru
  • PLUTO REALTORS PVT. LTD. · Bengaluru
  • S S DEVELOPERS · Bengaluru
  • SALARPURIA HOUSING PRIVATE LIMITED · Bengaluru
  • SALARPURIA PROPERTIES PRIVATE LIMITED · Bengaluru
  • SALARPURIA REAL ESTATES PRIVATE LIMITED · Bengaluru
  • SATTVA CITY PRIVATE LIMITED · Bengaluru
  • SATTVA DEVELOPERS PRIVATE LIMITED · Bengaluru
  • SATTVA INFRASTRUCTURE INDIA PRIVATE LIMITED · Bengaluru
  • SATTVA REAL ESTATE PRIVATE LIMITED · Bengaluru
  • SHIRASA CONSTRUCTION PRIVATE LIMITED · Bengaluru
  • Sattva Resi Private Limited · Bengaluru
  • TRINAYANI REALTOR PRIVATE LIMITED · Bengaluru
  • TRINAYANI REALTORS PRIVATE LIMITED · Bengaluru

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • Karnataka RERA — Bengaluru Urban and Bengaluru Rural districts
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Sattva Group deliver on time?+

Per the regulators' own registers, in Bengaluru, 8 of 12 completed projects with a recorded completion date finished by the date promised at RERA registration. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Sattva Group projects are registered with RERA?+

32 with Karnataka RERA (Bengaluru Urban and Bengaluru Rural districts). 12 of them are completed and 20 are ongoing.

Which Sattva Group projects are running late?+

6 ongoing registrations are past the latest date allowed on RERA without a completion on file, including Green Groves, La Vita, Aeropolis, a project of Sattva Group, SALARPURIA SATTVA MISTY CHARM LAND OWNER SHARE, salarpuria sattva park cubix. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.

How can I check a Sattva project's RERA record myself?+

Search the project's registration number on Karnataka RERA (rera.karnataka.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare Sattva with the other developers we track, or see the Sattva homes listed now.