Delivery record · from RERA
Is Sattva reliable?
Per the regulators' own registers, in Bengaluru, 8 of 12 completed projects with a recorded completion date finished by the date promised at RERA registration.
32 registrations · checked 6 October 2026
Bengaluru · Karnataka RERA
32
Registered projects
12 completed · 20 ongoing
67%
Finished by the date promised at registration
8 of 12 completed projects
0months
Median delay past the promised date
Across completed projects (on-time = 0)
6
Overdue now
Ongoing projects past their latest RERA date with no completion filed
Completion = the date of the first occupancy (or completion) certificate recorded on the project's K-RERA page; where none is recorded, the date the builder applied for completion on K-RERA.
Every registration
Sattva projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| SATTVA AANGANEBengaluru East · Bengaluru | Sept 2026 | Oct 2032 | None | In progress |
| SATTVA EKATRADoddaballapura · Bengaluru | Sept 2026 | Mar 2029 | None | In progress |
| SATTVA SONGBIRD PH 2Bengaluru South · Bengaluru | Mar 2026 | Jun 2031 | None | In progress |
| SATTVA CITYYelahanka · Bengaluru | Feb 2026 | Feb 2032 | None | In progress |
| SATTVA AARANYABengaluru South · Bengaluru | Dec 2025 | Jan 2031 | None | In progress |
| Sattva Vasanta CoveDevanahalli · Bengaluru | Dec 2025 | Dec 2030 | None | In progress |
| Sattva Aeropolis Phase 2Devanahalli · Bengaluru | Sept 2025 | Oct 2028 | None | In progress |
| Sattva Vasanta SkyeDevanahalli · Bengaluru | May 2025 | May 2031 | None | In progress |
| Sattva SimpliCityBengaluru South · Bengaluru | Mar 2025 | Dec 2025 | None | Completed Jan 2026 · <1 mo late |
| Park Cubix Phase 2Devanahalli · Bengaluru | Feb 2025 | Sept 2029 | None | In progress |
| Sattva Forest RidgeBengaluru South · Bengaluru | Dec 2024 | Dec 2029 | None | In progress |
| Sattva BhumiDevanahalli · Bengaluru | Oct 2024 | Dec 2026 | None | In progress |
| Sattva SongbirdBengaluru East · Bengaluru | Sept 2024 | May 2029 | None | In progress |
| Sattva LuminaYelahanka · Bengaluru | Sept 2024 | Nov 2029 | None | In progress |
| SATTVA SPRINGSBengaluru South · Bengaluru | Jul 2024 | Sept 2027 | None | In progress |
| Sattva Knowledge PointBengaluru North · Bengaluru | Jul 2024 | Jun 2025 | None | Completed Apr 2025 · on time |
| Green GrovesNelamangala · Bengaluru | May 2024 | Sept 2026 | None | Overdue |
| La VitaBengaluru East · Bengaluru | Dec 2023 | Jul 2026 | None | Overdue |
| Sattva BlissBengaluru East · Bengaluru | Jan 2023 | Aug 2027 | None | Completed Jun 2025 · on time |
| Aeropolis, a project of Sattva GroupDevanahalli · Bengaluru | May 2022 | Jul 2026 | None | Overdue |
Show all 32 registrationsShow fewer
| SALARPURIA-SATTVA ANUGRAHABengaluru North · Bengaluru | Sept 2021 | Dec 2024 | None | Completed Jun 2024 · on time |
| SALARPURIA-SATTVA SIGNETBengaluru East · Bengaluru | Jan 2021 | Aug 2024 | None | Completed May 2024 · on time |
| SALARPURIA-SATTVA EXOTICBengaluru North · Bengaluru | Apr 2019 | Nov 2023 | Aug 2024 (1) | Completed Apr 2024 · 4 mo late |
| Salarpuria Sattva Serene LifeDevanahalli · Bengaluru | Dec 2018 | Jun 2019 | None | Completed Jan 2024 · 55 mo late |
| SALARPURIA SATTVA MISTY CHARM LAND OWNER SHAREBengaluru South · Bengaluru | Sept 2018 | Jan 2023 | Oct 2023 (1) | Overdue |
| SALARPURIA SATTVA MISTY CHARMBengaluru South · Bengaluru | May 2018 | Jan 2023 | Oct 2024 (2) | Completed Jan 2024 · 11 mo late |
| salarpuria sattva park cubixDevanahalli · Bengaluru | Oct 2017 | Mar 2022 | Dec 2023 (2) | Overdue |
| DIVINITY, a project jointly promoted by Salarpuria and Sattva GroupBengaluru South · Bengaluru | Oct 2017 | Jun 2021 | Mar 2022 (1) | Completed Mar 2020 · on time |
| SALARPURIA-SATTVA ANUGRAHABengaluru North · Bengaluru | Oct 2017 | Jun 2021 | Mar 2022 (1) | Completed Apr 2021 · on time |
| SALARPURIA-SATTVA OPUSBengaluru North · Bengaluru | Sept 2017 | Jun 2021 | Sept 2023 (3) | Overdue |
| SALARPURIA-SATTVA EAST CRESTBengaluru East · Bengaluru | Sept 2017 | Sept 2020 | Jun 2021 (1) | Completed Mar 2019 · on time |
| SALARPURIA-SATTVA CADENZABengaluru South · Bengaluru | Sept 2017 | Jun 2019 | None | Completed Dec 2018 · on time |
Companies these projects are registered under (15)
- Darshita Southern India Happy Homes Private Limited · Bengaluru
- K M Srinivasa Murthy · Bengaluru
- PLUTO REALTORS PVT. LTD. · Bengaluru
- S S DEVELOPERS · Bengaluru
- SALARPURIA HOUSING PRIVATE LIMITED · Bengaluru
- SALARPURIA PROPERTIES PRIVATE LIMITED · Bengaluru
- SALARPURIA REAL ESTATES PRIVATE LIMITED · Bengaluru
- SATTVA CITY PRIVATE LIMITED · Bengaluru
- SATTVA DEVELOPERS PRIVATE LIMITED · Bengaluru
- SATTVA INFRASTRUCTURE INDIA PRIVATE LIMITED · Bengaluru
- SATTVA REAL ESTATE PRIVATE LIMITED · Bengaluru
- SHIRASA CONSTRUCTION PRIVATE LIMITED · Bengaluru
- Sattva Resi Private Limited · Bengaluru
- TRINAYANI REALTOR PRIVATE LIMITED · Bengaluru
- TRINAYANI REALTORS PRIVATE LIMITED · Bengaluru
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- Karnataka RERA — Bengaluru Urban and Bengaluru Rural districts
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does Sattva Group deliver on time?+
Per the regulators' own registers, in Bengaluru, 8 of 12 completed projects with a recorded completion date finished by the date promised at RERA registration. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many Sattva Group projects are registered with RERA?+
32 with Karnataka RERA (Bengaluru Urban and Bengaluru Rural districts). 12 of them are completed and 20 are ongoing.
Which Sattva Group projects are running late?+
6 ongoing registrations are past the latest date allowed on RERA without a completion on file, including Green Groves, La Vita, Aeropolis, a project of Sattva Group, SALARPURIA SATTVA MISTY CHARM LAND OWNER SHARE, salarpuria sattva park cubix. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.
How can I check a Sattva project's RERA record myself?+
Search the project's registration number on Karnataka RERA (rera.karnataka.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.