Delivery record · from RERA
Is Alliance reliable?
Per the regulators' own registers, in Tamil Nadu, 3 of 13 registered projects are marked completed, 1 of them without any extension.
13 registrations · checked 6 October 2026
Tamil Nadu · TNRERA
13
Registered projects
3 completed · 9 ongoing
33%
Completed without any extension
1 of 3 completed projects
43%
Needed an extension
3 of 7 projects whose promised date has passed
4
Overdue now
Ongoing projects past their latest RERA date and not marked completed
TNRERA marks projects as completed but publishes the completion date only inside PDF certificates, so we report completions and extensions rather than months of delay.
Every registration
Alliance projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| SPRING TIDETamil Nadu | Jun 2025 | Jul 2029 | None | In progress |
| Spring TideTamil Nadu | Apr 2025 | Aug 2029 | None | In progress |
| THE WORLD OF JOYTamil Nadu | Mar 2025 | Dec 2027 | None | In progress |
| Urbanrise Maheshwari The Lakes EdgeTamil Nadu | Mar 2025 | Sept 2028 | None | In progress |
| SPRING TIDETamil Nadu | Feb 2025 | Aug 2029 | None | In progress |
| HUMMING GARDEN PHASETamil Nadu | Apr 2024 | Jun 2025 | None | Overdue |
| Humming Gardens Phase-2Tamil Nadu | Oct 2019 | Oct 2020 | Jun 2021 (1) | Overdue |
| Alliance Galleria ResidencesTamil Nadu | Jun 2019 | Feb 2022 | None | Registration cancelled (fully or in part) |
| AMDCPL – Prozone Palm Phase-IATamil Nadu | May 2019 | Feb 2022 | Aug 2025 (3) | Completed · 3 extensions |
| Prozone Palms Phase-IBTamil Nadu | May 2019 | Feb 2022 | Feb 2026 (4) | Completed · 4 extensions |
| Construction of Block Nos. 1Tamil Nadu | Jun 2018 | — | Jun 2021 (1) | Overdue |
| Construction of Basement floor + Stilt floor + First Floor + Second floor with 3Tamil Nadu | May 2018 | Oct 2021 | None | Completed · no extension |
| Construction of Residential Group developmentsTamil Nadu | Aug 2017 | Mar 2019 | None | Overdue |
Companies these projects are registered under (10)
- . Alliance Villas Pvt Ltd (Developer) & M/s.Tamilnadu Maheswari Foundation (Owner) · Tamil Nadu
- ALLIANCE BUDGET HOUSING INDIA PVT LTD · Tamil Nadu
- ALLIANCE BUSINESS PARKS PVT. LTD. · Tamil Nadu
- ALLIANCE VILLAS (P) LTD. · Tamil Nadu
- ALLIANCE VILLAS PRIVATE LIMITED · Tamil Nadu
- ALLIANCE VILLAS PVT LTD · Tamil Nadu
- ALLIANCE VILLAS PVT LTD. · Tamil Nadu
- Alliance Budget Housing India Pvt Ltd · Tamil Nadu
- Alliance Mall Developers Co. Pvt. Ltd. · Tamil Nadu
- Alliance Villas Pvt. Ltd. · Tamil Nadu
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- TNRERA — Tamil Nadu building projects
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does Alliance Group deliver on time?+
Per the regulators' own registers, in Tamil Nadu, 3 of 13 registered projects are marked completed, 1 of them without any extension. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many Alliance Group projects are registered with RERA?+
13 with TNRERA (Tamil Nadu building projects). 3 of them are completed and 9 are ongoing.
Which Alliance Group projects are running late?+
4 ongoing registrations are past the latest date allowed on RERA without a completion on file, including HUMMING GARDEN PHASE, Humming Gardens Phase-2, Construction of Block Nos. 1, Construction of Residential Group developments. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.
How can I check a Alliance project's RERA record myself?+
Search the project's registration number on TNRERA (rera.tn.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.