Is Alliance reliable?

Per the regulators' own registers, in Tamil Nadu, 3 of 13 registered projects are marked completed, 1 of them without any extension.

13 registrations · checked 6 October 2026

Tamil Nadu · TNRERA

13

Registered projects

3 completed · 9 ongoing

33%

Completed without any extension

1 of 3 completed projects

43%

Needed an extension

3 of 7 projects whose promised date has passed

4

Overdue now

Ongoing projects past their latest RERA date and not marked completed

TNRERA marks projects as completed but publishes the completion date only inside PDF certificates, so we report completions and extensions rather than months of delay.

Every registration

Alliance projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
SPRING TIDETamil NaduJun 2025Jul 2029NoneIn progress
Spring TideTamil NaduApr 2025Aug 2029NoneIn progress
THE WORLD OF JOYTamil NaduMar 2025Dec 2027NoneIn progress
Urbanrise Maheshwari The Lakes EdgeTamil NaduMar 2025Sept 2028NoneIn progress
SPRING TIDETamil NaduFeb 2025Aug 2029NoneIn progress
HUMMING GARDEN PHASETamil NaduApr 2024Jun 2025NoneOverdue
Humming Gardens Phase-2Tamil NaduOct 2019Oct 2020Jun 2021 (1)Overdue
Alliance Galleria ResidencesTamil NaduJun 2019Feb 2022NoneRegistration cancelled (fully or in part)
AMDCPL – Prozone Palm Phase-IATamil NaduMay 2019Feb 2022Aug 2025 (3)Completed · 3 extensions
Prozone Palms Phase-IBTamil NaduMay 2019Feb 2022Feb 2026 (4)Completed · 4 extensions
Construction of Block Nos. 1Tamil NaduJun 2018—Jun 2021 (1)Overdue
Construction of Basement floor + Stilt floor + First Floor + Second floor with 3Tamil NaduMay 2018Oct 2021NoneCompleted · no extension
Construction of Residential Group developmentsTamil NaduAug 2017Mar 2019NoneOverdue
Companies these projects are registered under (10)
  • . Alliance Villas Pvt Ltd (Developer) & M/s.Tamilnadu Maheswari Foundation (Owner) · Tamil Nadu
  • ALLIANCE BUDGET HOUSING INDIA PVT LTD · Tamil Nadu
  • ALLIANCE BUSINESS PARKS PVT. LTD. · Tamil Nadu
  • ALLIANCE VILLAS (P) LTD. · Tamil Nadu
  • ALLIANCE VILLAS PRIVATE LIMITED · Tamil Nadu
  • ALLIANCE VILLAS PVT LTD · Tamil Nadu
  • ALLIANCE VILLAS PVT LTD. · Tamil Nadu
  • Alliance Budget Housing India Pvt Ltd · Tamil Nadu
  • Alliance Mall Developers Co. Pvt. Ltd. · Tamil Nadu
  • Alliance Villas Pvt. Ltd. · Tamil Nadu

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • TNRERA — Tamil Nadu building projects
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Alliance Group deliver on time?+

Per the regulators' own registers, in Tamil Nadu, 3 of 13 registered projects are marked completed, 1 of them without any extension. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Alliance Group projects are registered with RERA?+

13 with TNRERA (Tamil Nadu building projects). 3 of them are completed and 9 are ongoing.

Which Alliance Group projects are running late?+

4 ongoing registrations are past the latest date allowed on RERA without a completion on file, including HUMMING GARDEN PHASE, Humming Gardens Phase-2, Construction of Block Nos. 1, Construction of Residential Group developments. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.

How can I check a Alliance project's RERA record myself?+

Search the project's registration number on TNRERA (rera.tn.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare Alliance with the other developers we track, or see the Alliance homes listed now.