Delivery record · from RERA
Is Elan reliable?
Per the regulators' own registers, in Gurugram, 3 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration.
13 registrations · checked 6 October 2026
Gurugram · HARERA Gurugram
13
Registered projects
4 completed · 7 ongoing
75%
Finished by the date promised at registration
3 of 4 completed projects
0months
Median delay past the promised date
Across completed projects (on-time = 0)
0
Overdue now
Ongoing projects past their registration validity with no occupancy certificate on file
Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.
Every registration
Elan projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| ELAN THE STATEMENTSECTOR 49, GURUGRAM · Gurugram | Dec 2025 | Sept 2033 | None | In progress |
| ELAN THE EMPERORSITUATED IN SECTOR 106 IN THE REVENUE ESTATE OF VILLAGE PAWALA KHUSRUPUR TEHSIL KADIPUR DISTRICT GURUGRAM, HARYANA · Gurugram | Jan 2025 | Sept 2032 | None | In progress |
| ELAN IMPERIALVILLAGE- NAKHNOULA, SECTOR-82 , GURUGRAM · Gurugram | Feb 2024 | Dec 2028 | None | In progress |
| ELAN EMPIREREVENUE ESTATE VILLAGE MAIDAW AS , SECTOR-66 , GURUGRAM , HARYANA · Gurugram | Jul 2023 | Apr 2028 | None | In progress |
| ELAN THE MARKSITUATED IN SECTOR 106 IN THE REVENUE ESTATE OF VILLAGE PAWALA KHUSRUPUR TEHSIL KADIPUR DISTRICT GURUGRAM, HARYANA · Gurugram | Mar 2023 | Jan 2028 | None | In progress |
| ELAN THE PRESIDENTIALSITUATED IN SECTOR 106 IN THE REVENUE ESTATE OF VILLAGE PAWALA KHUSRUPUR TEHSIL KADIPUR DISTRICT GURUGRAM, HARYANA · Gurugram | Nov 2022 | Oct 2027 | None | In progress |
| ELAN PARADISEREVENUE ESTATE OF VILLAGE ADA MPUR, SUB TEHSIL- WAZIRABAD, SECTOR-50, DISTRICT GURUGRAM, HARYANA · Gurugram | Jul 2022 | Jun 2026 | Jun 2027 (1) | In progress |
| ELAN EMPIREREVENUE ESTATE VILLAGE MAIDAW AS , SECTOR-66 , GURUGRAM , HARYANA · Gurugram | Jul 2021 | Apr 2026 | None | Registration lapsed |
| ELAN PARADISEREVENUE ESTATE OF VILLAGE ADA MPUR, SUB TEHSIL- WAZIRABAD, SECTOR-50, DISTRICT GURUGRAM, HARYANA · Gurugram | Mar 2021 | Sept 2025 | None | Registration lapsed |
| ELAN EPICSECTOR - 70, GURUGRAM · Gurugram | Dec 2018 | Dec 2023 | None | Completed Oct 2023 · on time |
| ELAN TOWN CENTRE, COMMERCIAL PROJECTSECTOR-67, BADSHAHPUR, GURUGR AM · Gurugram | Feb 2018 | Feb 2022 | None | Completed Mar 2021 · on time |
| COMMERCIAL COLONYSECTOR 84, VILLAGE HAYATPUR, GURUGRAM · Gurugram | Sept 2017 | Sept 2023 | None | Completed Mar 2023 · on time |
| COMMERCIAL PROJECTSECTOR 80, VILLAGE NAURANGPUR , GURUGRAM · Gurugram | Sept 2017 | Sept 2022 | None | Completed Oct 2022 · 1 mo late |
Companies these projects are registered under (8)
- ELAN AVENUE LIMITED · Gurugram
- ELAN AVENUE LIMITED (FORMERLY KNOWN AS AIRMID DEVELOPERS LIMITED) · Gurugram
- ELAN BUILDCON PVT. LTD · Gurugram
- ELAN BUILDCON PVT. LTD. · Gurugram
- ELAN CITY LLP · Gurugram
- ELAN ENCLAVE PRIVATE LIMITED · Gurugram
- ELAN IMPERIAL PVT LTD (FORMERLY KNOWN AS AMBIENCE INFRASTRUCTURE DEVELOPERS PVT LTD) · Gurugram
- ELAN LIMITED · Gurugram
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- HARERA Gurugram — Gurugram
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does Elan Group deliver on time?+
Per the regulators' own registers, in Gurugram, 3 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many Elan Group projects are registered with RERA?+
13 with HARERA Gurugram (Gurugram). 4 of them are completed and 7 are ongoing.
Which Elan Group projects are running late?+
None of Elan Group's ongoing registrations is past its latest RERA date as of 2026-10-06.
How can I check a Elan project's RERA record myself?+
Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.