Delivery record · from RERA
Is M3M reliable?
Per the regulators' own registers, in Gurugram, 19 of 25 completed projects with a recorded completion date finished by the date promised at RERA registration.
45 registrations · checked 6 October 2026
Gurugram · HARERA Gurugram
45
Registered projects
25 completed · 17 ongoing
76%
Finished by the date promised at registration
19 of 25 completed projects
0months
Median delay past the promised date
Across completed projects (on-time = 0)
0
Overdue now
Ongoing projects past their registration validity with no occupancy certificate on file
Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.
Every registration
M3M projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| M3M CAPITAL FINANCIAL CENTRESECTOR 113 · Gurugram | Jul 2026 | Jun 2033 | None | In progress |
| M3M SOULITUDE CENTRALSECTOR 89 · Gurugram | Feb 2026 | Jul 2030 | None | In progress |
| M3M FORESTIA EAST ISECTOR M9, M10 AND M11 · Gurugram | Jan 2026 | Jun 2034 | None | In progress |
| M3M FORESTIA WEST ISECTOR M9, M10 AND M11, MANES AR · Gurugram | Jan 2026 | Jun 2034 | None | In progress |
| GURGAON INTERNATIONAL CITYSECTOR- M9, M10, M11 · Gurugram | Oct 2025 | Sept 2034 | None | In progress |
| M3M ELIE SAAB AT SCDASECTOR-111,GURUGRAM · Gurugram | Oct 2025 | Feb 2032 | None | In progress |
| M3M SOULITUDE 3SECTOR 89, GURUGRAM · Gurugram | May 2025 | Mar 2029 | None | In progress |
| M3M MANSION PH-2SECTOR 113, VILL CHAUMA,GURUG RAM · Gurugram | Feb 2025 | Feb 2031 | None | In progress |
| M3M OPUS AT M3M MERLINSECTOR-67, GURUGRAM · Gurugram | Oct 2024 | Nov 2029 | None | In progress |
| M3M SOULITUDE 2SECTOR-89, GURUGRAM, HARYANA · Gurugram | Aug 2024 | Apr 2027 | None | Completed Apr 2026 · on time |
| M3M ANTALYA HILLS 3SECTOR 79 & 79B, GURUGRAM · Gurugram | Jul 2024 | Oct 2028 | None | In progress |
| M3M ESCALASECTOR -70A, GURUGRAM · Gurugram | Jun 2024 | Aug 2018 | None | Completed Aug 2018 · on time |
| M3M ANTALYA HILLS PHASE IISECTOR-79, GURUGRAM, HARYANA · Gurugram | Jun 2024 | Jun 2026 | None | Registration lapsed |
| M3M CAPITAL PHASE-3SECTOR-113, VILLAGE CHAUMA, G URUGRAM, HARYANA · Gurugram | May 2024 | Feb 2028 | None | Completed May 2026 · on time |
| M3M ALTITUDESECTOR 65, GURUGRAM · Gurugram | Apr 2024 | Jul 2031 | None | In progress |
| M3M GOLF HILLS PHASE 2SECTOR-79 & 79B, GURUGRAM, HA RYANA · Gurugram | Apr 2024 | May 2030 | None | In progress |
| M3M ROUTE65VILLAGE MAIDAWAS, SECTOR-65, GURUGRAM, HARYANA · Gurugram | Mar 2024 | Feb 2027 | None | Completed Jun 2025 · on time |
| M3M MANSIONVILLAGE CHAUMA,SECTOR 113,GUR UGRAM · Gurugram | Mar 2024 | Mar 2030 | None | In progress |
| M3M JEWELSECTOR-25, GURUGRAM, HARYANA · Gurugram | May 2023 | Mar 2026 | Mar 2027 (1) | Completed Sept 2026 · 5 mo late |
| M3M XPRESSWAY 114SECTOR 114, GURUGRAM · Gurugram | May 2023 | Apr 2025 | None | Completed Aug 2025 · 4 mo late |
Show all 45 registrationsShow fewer
| M3M GOLF HILLS PHASE 1SECTOR 79/ 79B · Gurugram | Mar 2023 | Feb 2031 | None | In progress |
| M3M BROADWAY (INCLUDING (RETAIL, OFFICE , MULTIPLEX) AND SERVICE APARTMENTS(M3M SKY LOFT)SECTOR 71, GURUGRAM · Gurugram | Mar 2023 | Apr 2024 | None | Completed Dec 2021 · on time |
| M3M CROWN PHASE 1SECTOR-111 · Gurugram | Feb 2023 | Jan 2028 | None | In progress |
| M3M ANTALYA HILLS PHASE IISECTOR 79, GURUGRAM · Gurugram | Jan 2023 | Jun 2026 | None | Registration lapsed |
| M3M ANTALYA HILLS PHASE 1SECTOR 79, GURUGRAM · Gurugram | Dec 2022 | Dec 2025 | Dec 2026 (1) | In progress |
| M3M PARAGON57BLOCK A SUSHANT LOK- III, SEC TOR-57 GURUGRAM MANESAR URBAN COMPLEX · Gurugram | Dec 2022 | Aug 2026 | Aug 2027 (1) | In progress |
| M3M JEWELSECTOR-25, GURUGRAM · Gurugram | Nov 2022 | Mar 2026 | None | Completed Sept 2026 · 5 mo late |
| M3M CAPITAL PHASE -2SECTOR -113, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA. · Gurugram | Sept 2022 | Dec 2026 | None | Completed May 2026 · on time |
| M3M ROUTE65VILLAGE MAIDAWAS, SECTOR-65, GURUGRAM, HARYANA · Gurugram | Aug 2022 | Feb 2027 | None | Completed Jan 2026 · on time |
| M3M FLORA68SECTOR -68, GURUGRAM · Gurugram | Jul 2022 | Jul 2024 | None | Completed Oct 2023 · on time |
| M3M 114 MARKETSECTOR -114, GURUGRAM MANESAR URBAN COMPLEX, HARYANA · Gurugram | Jul 2022 | Aug 2024 | None | Completed Nov 2024 · 3 mo late |
| M3M INTERNATIONAL FINANCIAL CENTER INCLUDING PHASE I & IISECTOR-66, GURUGRAM · Gurugram | May 2022 | Dec 2024 | None | Completed Dec 2020 · on time |
| M3M CAPITALSECTOR -113, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA. · Gurugram | Feb 2022 | Jun 2026 | Jun 2027 (1) | Completed May 2026 · on time |
| M3M ATRIUM57BLOCK-H SUSHANT LOK III SECTO R 57 GURUGRAM HARYANA · Gurugram | Nov 2021 | May 2025 | None | Completed Jul 2024 · on time |
| M3M SOULITUDESECTOR-89, GURUGRAM MANESAR U RBAN COMPLEX, GURUGRAM, HARYANA. · Gurugram | Oct 2021 | Sept 2025 | None | Completed Aug 2024 · on time |
| M3M 84 MARKETSECTOR-84, GURUGRAM · Gurugram | Oct 2019 | Oct 2021 | Apr 2023 (1) | Completed Sept 2024 · 35 mo late |
| M3M URBANASECTOR-67, GURUGRAM · Gurugram | Jun 2019 | Dec 2021 | None | Completed Jul 2020 · on time |
| M3M PRIVE 73SECTOR-73, GURUGRAM · Gurugram | May 2019 | Feb 2024 | None | Completed Aug 2021 · on time |
| M3M BROADWAYVILLAGE- FAZILPUR JHARSA, SEC TOR-71, GURUGRAM · Gurugram | Dec 2018 | Oct 2023 | None | Registration lapsed |
| M3M TEE POINTSECTOR-65, VILLAGE MAIDAWAS A ND BADSHAHPUR, GURUGRAM, HARYANA · Gurugram | Nov 2017 | Jul 2021 | None | Completed Aug 2020 · on time |
| M3M URBANA BUSINESS PARKSECTOR-67, VILLAGE MAIDAWAS A ND BADSHAHPUR, GURUGRAM, HARYANA · Gurugram | Nov 2017 | Nov 2021 | None | Completed Sept 2020 · on time |
| M3M URBANA PREMIUMSECTOR-67, VILLAGE MAIDAWAS, GURUGRAM, HARYANA · Gurugram | Nov 2017 | Aug 2024 | None | Completed Feb 2021 · on time |
| M3M LATITUDE ( TOWER R-01)SECTOR-65, GURUGRAM, HARYANA · Gurugram | Aug 2017 | Jan 2023 | None | Completed Jan 2021 · on time |
| M3M MARINA/M3M SIERRA 68 ( GROUP HOUSING COLONY)SECTOR-68, GURUGRAM · Gurugram | Aug 2017 | Nov 2022 | None | Completed Sept 2020 · on time |
| M3M 113 MARKETSECTOR-113, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA · Gurugram | — | Oct 2021 | Apr 2023 (1) | Completed Nov 2023 · 24 mo late |
Companies these projects are registered under (24)
- AAWAM RESIDENCY PRIVATE LIMITED · Gurugram
- CONSOLIDATE REALTORS PRIVATE LIMITED · Gurugram
- GENEROUS REALTORS PRIVATE LIMITED · Gurugram
- GENTLE REALTORS PRIVATE LIMITED · Gurugram
- GOLDEN GATE PROPBUILD PRIVATE LIMITED · Gurugram
- HAAMID REAL ESTATE PVT. LTD. ,RAPID INFRACON PVT. LTD., M3M INDIA PVT. LTD. · Gurugram
- HANS PROPCON PVT. LTD · Gurugram
- HANS PROPCON PVT. LTD., GLORY INFRACON PVT. LTD., BLOSSOM PROPBUILD PVT. LTD. · Gurugram
- LAVISH BUILDMART PVT. LTD. · Gurugram
- LEKH BUILDTECH PRIVATE LIMITED · Gurugram
- LOON LAND DEVELOPMENT LIMITED · Gurugram
- M3M INDIA INFRASTRUCTURES PRIVATE LIMITED · Gurugram
- M3M INDIA PRIVATE LIMITED · Gurugram
- M3M INDIA PVT. LTD. & MARTIAL BUILDCOM PVT. LTD. · Gurugram
- MANGLAM MULTIPLEX PRIVATE LIMITED · Gurugram
- MANGLAM MULTIPLEX PVT. LTD AND OTHERS · Gurugram
- MARCONI INFRATECH PVT. LTD. · Gurugram
- MARTIAL BUILDCON PVT. LTD. · Gurugram
- METRO EDUCATION & WELFARE PRIVATE LIMITED · Gurugram
- PARYAPT INFRASTRUCTURE PRIVATE LIMITED · Gurugram
- PARYAPT INFRASTRUCTUREPRIVATE LIMITED · Gurugram
- ROSHNI BUILDERS PRIVATE LIMITED · Gurugram
- ROSHNI BUILDERS PVT. LTD. · Gurugram
- UNION BUILDMART PRIVATE LIMITED · Gurugram
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- HARERA Gurugram — Gurugram
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does M3M India deliver on time?+
Per the regulators' own registers, in Gurugram, 19 of 25 completed projects with a recorded completion date finished by the date promised at RERA registration. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many M3M India projects are registered with RERA?+
45 with HARERA Gurugram (Gurugram). 25 of them are completed and 17 are ongoing.
Which M3M India projects are running late?+
None of M3M India's ongoing registrations is past its latest RERA date as of 2026-10-06.
How can I check a M3M project's RERA record myself?+
Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.
Compare M3M with the other developers we track, or see the M3M homes listed now.