Delivery record · from RERA
Is Century reliable?
Per the regulators' own registers, in Bengaluru, 6 of 14 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 4.5 months after that date.
32 registrations · checked 6 October 2026
Bengaluru · Karnataka RERA
32
Registered projects
14 completed · 18 ongoing
43%
Finished by the date promised at registration
6 of 14 completed projects
4.5months
Median delay past the promised date
Across completed projects (on-time = 0)
7
Overdue now
Ongoing projects past their latest RERA date with no completion filed
Completion = the date of the first occupancy (or completion) certificate recorded on the project's K-RERA page; where none is recorded, the date the builder applied for completion on K-RERA.
Every registration
Century projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| Century OneWorld Seraya Phase 3Bengaluru North · Bengaluru | Aug 2026 | Jan 2030 | None | In progress |
| Century AstoriaBengaluru North · Bengaluru | May 2026 | Feb 2031 | None | In progress |
| Century BlissDoddaballapura · Bengaluru | Apr 2026 | Apr 2031 | None | In progress |
| Century Kindle Phase 1Bengaluru North · Bengaluru | Mar 2026 | Mar 2031 | None | In progress |
| Century Mirai Ph1Bengaluru East · Bengaluru | Oct 2025 | Oct 2030 | None | In progress |
| Century OneWorld Seraya Phase 2Bengaluru North · Bengaluru | Sept 2025 | Aug 2029 | None | In progress |
| Century OneWorld Seraya Phase 1Bengaluru North · Bengaluru | Jul 2025 | May 2029 | None | In progress |
| Century Trails Phase 2Devanahalli · Bengaluru | Jun 2025 | May 2028 | None | Completed Sept 2026 · on time |
| Century Regalia (Project 2)Bengaluru East · Bengaluru | Mar 2025 | Feb 2030 | None | In progress |
| Century LivaBengaluru North · Bengaluru | Sept 2024 | Dec 2028 | None | In progress |
| Century Eden Phase 5Doddaballapura · Bengaluru | Jul 2024 | Apr 2027 | None | Completed Jan 2026 · on time |
| Century Regalia (Project 1)Bengaluru East · Bengaluru | May 2024 | Apr 2029 | None | In progress |
| Century TrailsDevanahalli · Bengaluru | Dec 2023 | Mar 2027 | None | Completed Feb 2026 · on time |
| Century XenonBengaluru North · Bengaluru | Sept 2023 | Dec 2024 | None | Overdue |
| Century Wintersun Phase 2Yelahanka · Bengaluru | Jul 2023 | Jun 2026 | None | Completed Feb 2025 · on time |
| Century Eden Phase 4Doddaballapura · Bengaluru | Jun 2023 | Feb 2026 | None | Completed May 2024 · on time |
| Century Eden Phase 3Doddaballapura · Bengaluru | May 2023 | Feb 2026 | None | Completed Aug 2024 · on time |
| Century NovusBengaluru North · Bengaluru | Apr 2023 | Aug 2027 | None | In progress |
| Century Seasons Phase 2Devanahalli · Bengaluru | Jul 2022 | Jan 2025 | None | Overdue |
| CENTURY SEASONSDevanahalli · Bengaluru | Mar 2021 | Jan 2024 | None | Overdue |
Show all 32 registrationsShow fewer
| CENTURY GREENS PHASE 2Doddaballapura · Bengaluru | Jan 2021 | Dec 2021 | None | Completed Apr 2022 · 3 mo late |
| CENTURY ETHOS (SHELTORS SHARE)Bengaluru North · Bengaluru | Oct 2020 | Jun 2021 | Jun 2022 (1) | Overdue |
| CENTURY EDEN PHASE 2Doddaballapura · Bengaluru | Mar 2020 | Mar 2022 | Dec 2023 (2) | Overdue |
| Century HorizonBengaluru North · Bengaluru | Nov 2019 | Mar 2024 | Dec 2024 (1) | Completed Mar 2025 · 12 mo late |
| Century GreensDevanahalli · Bengaluru | Sept 2018 | Jun 2020 | Dec 2021 (2) | Completed Jul 2022 · 24 mo late |
| Century ArtizanBengaluru North · Bengaluru | Nov 2017 | Jun 2018 | Jun 2019 (1) | Completed Jun 2019 · 11 mo late |
| Century CentralBengaluru South · Bengaluru | Oct 2017 | Jun 2018 | Jun 2019 (1) | Completed Dec 2019 · 17 mo late |
| Century EthosBengaluru North · Bengaluru | Oct 2017 | Dec 2020 | Sept 2022 (2) | Overdue |
| Century RenataBengaluru East · Bengaluru | Sept 2017 | Mar 2018 | Mar 2019 (1) | Completed Jul 2019 · 15 mo late |
| Century BreezeBengaluru North · Bengaluru | Sept 2017 | Dec 2019 | Sept 2021 (2) | Overdue |
| Century InfinitiBengaluru East · Bengaluru | Sept 2017 | Jun 2018 | Jun 2019 (1) | Completed Dec 2018 · 6 mo late |
| Century Indus Phase 2Bengaluru South · Bengaluru | Sept 2017 | Dec 2018 | Dec 2019 (1) | Completed Dec 2019 · 11 mo late |
Companies these projects are registered under (22)
- Archway Realty LLP · Bengaluru
- CENTURY AUSTRAL · Bengaluru
- CENTURY NORTHSIDE · Bengaluru
- CENTURY SHELTORS DEVELOPERS PRIVATE LIMITED · Bengaluru
- CENTURY STAR · Bengaluru
- Century Dwellings Private Limited · Bengaluru
- Century Prime Properties Private Limited · Bengaluru
- Century Real Estate Holdings Private Limited · Bengaluru
- Century Silicon City Private Limited · Bengaluru
- Century Star · Bengaluru
- Century Trails LLP · Bengaluru
- Century joint Development Private Limited · Bengaluru
- GEETANJALI EFFECTIVE REALTY SOLUTIONS PRIVATE LIMITED · Bengaluru
- Geetanjali Effective Realty Solutions Private Limited · Bengaluru
- Green Orchards Farm Houses · Bengaluru
- Hebbal Properties Private Limited · Bengaluru
- Paraag Constructions and Developers · Bengaluru
- REALKRAFT VENTURES LLP · Bengaluru
- Suruchi Properties Private Limited · Bengaluru
- TALREJA REALTY LLP · Bengaluru
- Vigneshwara Estates · Bengaluru
- Vinayaka Builders and Developers · Bengaluru
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- Karnataka RERA — Bengaluru Urban and Bengaluru Rural districts
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does Century Real Estate deliver on time?+
Per the regulators' own registers, in Bengaluru, 6 of 14 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 4.5 months after that date. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many Century Real Estate projects are registered with RERA?+
32 with Karnataka RERA (Bengaluru Urban and Bengaluru Rural districts). 14 of them are completed and 18 are ongoing.
Which Century Real Estate projects are running late?+
7 ongoing registrations are past the latest date allowed on RERA without a completion on file, including Century Xenon, Century Seasons Phase 2, CENTURY SEASONS, CENTURY ETHOS (SHELTORS SHARE), CENTURY EDEN PHASE 2. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.
How can I check a Century project's RERA record myself?+
Search the project's registration number on Karnataka RERA (rera.karnataka.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.