Delivery record · from RERA

Is Embassy reliable?

Per the regulators' own registers, in Bengaluru, 2 of 5 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 2.2 months after that date.

15 registrations · checked 6 October 2026

Bengaluru · Karnataka RERA

15

Registered projects

5 completed · 10 ongoing

40%

Finished by the date promised at registration

2 of 5 completed projects

2.2months

Median delay past the promised date

Across completed projects (on-time = 0)

0

Overdue now

Ongoing projects past their latest RERA date with no completion filed

Completion = the date of the first occupancy (or completion) certificate recorded on the project's K-RERA page; where none is recorded, the date the builder applied for completion on K-RERA.

Every registration

Embassy projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
EMBASSY RIVERINEBengaluru North · BengaluruSept 2026Sept 2032NoneIn progress
EMBASSY SOUTH RESERVEBengaluru North · BengaluruSept 2026Mar 2032NoneIn progress
EMBASSY EDENYelahanka · BengaluruDec 2025Dec 2031NoneIn progress
EMBASSY VERDE PHASE 2Devanahalli · BengaluruNov 2025Jun 2031NoneIn progress
EMBASSY GREENSHOREDevanahalli · BengaluruNov 2025Dec 2031NoneIn progress
EMBASSY PARADISODevanahalli · BengaluruJul 2025Aug 2027NoneIn progress
EMBASSY VERDEDevanahalli · BengaluruDec 2024Dec 2030NoneIn progress
EMBASSY EAST AVENUEBengaluru East · BengaluruFeb 2024Sept 2028NoneIn progress
Serene Amara by Columbia PacificBengaluru North · BengaluruFeb 2023Dec 2026NoneCompleted Dec 2025 · on time
Embassy Springs - Phase 2A, ApartmentsDevanahalli · BengaluruMay 2018Feb 2023Dec 2027 (3)In progress
Embassy GroveBengaluru East · BengaluruOct 2017Jun 2019Mar 2023 (3)Completed Sept 2019 · 2 mo late
Embassy Lake TerracesBengaluru North · BengaluruOct 2017Jun 2019Mar 2023 (3)Completed May 2022 · 35 mo late
Embassy Springs - Phase 1, Plotted DevelopmentDevanahalli · BengaluruOct 2017Aug 2018Mar 2023 (2)Completed Jul 2023 · 58 mo late
Embassy BoulevardBengaluru North · BengaluruOct 2017Jun 2019NoneCompleted May 2019 · on time
Embassy OneBengaluru North · BengaluruOct 2017Jun 2019Apr 2027 (3)In progress
Companies these projects are registered under (8)
  • EMBASSY DEVELOPMENTS LIMITED · Bengaluru
  • EMBASSY ONE DEVELOPERS LIMITED · Bengaluru
  • Embassy Property Development Private Limited · Bengaluru
  • Embassy-Columbia Pacific ASL Pvt Ltd · Bengaluru
  • NAM Estates Private Limited · Bengaluru
  • SION EDEN DEVELOPERS LIMITED · Bengaluru
  • SUMMIT DEVELOPMENTS LIMITED · Bengaluru
  • VIGOR DEVELOPMENTS LIMITED · Bengaluru

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • Karnataka RERA — Bengaluru Urban and Bengaluru Rural districts
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Embassy Group deliver on time?+

Per the regulators' own registers, in Bengaluru, 2 of 5 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 2.2 months after that date. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Embassy Group projects are registered with RERA?+

15 with Karnataka RERA (Bengaluru Urban and Bengaluru Rural districts). 5 of them are completed and 10 are ongoing.

Which Embassy Group projects are running late?+

None of Embassy Group's ongoing registrations is past its latest RERA date as of 2026-10-06.

How can I check a Embassy project's RERA record myself?+

Search the project's registration number on Karnataka RERA (rera.karnataka.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.