Delivery record · from RERA
Is Smartworld reliable?
Per the regulators' own registers, in Gurugram, 3 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration.
14 registrations · checked 6 October 2026
Gurugram · HARERA Gurugram
14
Registered projects
4 completed · 8 ongoing
75%
Finished by the date promised at registration
3 of 4 completed projects
0months
Median delay past the promised date
Across completed projects (on-time = 0)
0
Overdue now
Ongoing projects past their registration validity with no occupancy certificate on file
Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.
Every registration
Smartworld projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| SMARTWORLD NATURE'S COURT ISECTOR M9, M10 AND M11 · Gurugram | Jan 2026 | Jun 2033 | None | In progress |
| SMARTWORLD GEMS 3SECTOR 89 · Gurugram | May 2025 | Mar 2028 | None | In progress |
| SMARTWORLD SKY ARCSECTOR 69 · Gurugram | Oct 2024 | May 2032 | None | In progress |
| SMARTWORLD GEMS 2SECTOR-89, GURUGRAM HARYANA · Gurugram | Aug 2024 | Apr 2027 | None | In progress |
| SMARTWORLD ONE DXP PHASE-2SECTOR 113, VILLAGE CHAUMA,GU RUGRAM · Gurugram | Jun 2024 | Aug 2031 | None | In progress |
| SMARTWORLD ORCHARD STREETSECTOR 61,GURUGRAM.HARYANA · Gurugram | Dec 2023 | Jun 2026 | None | Completed May 2026 · on time |
| SMARTWORLD THE EDITIONSECTOR-66, GURUGRAM, HARYANA · Gurugram | Nov 2023 | Feb 2031 | None | In progress |
| SMARTWORLD ONE DXP STREETSECTOR-113, GURUGRAM · Gurugram | Dec 2022 | Dec 2027 | None | In progress |
| SMARTWORLD ONE DXPSEC-113 · Gurugram | Dec 2022 | Dec 2027 | None | In progress |
| SMARTWORLD ORCHARDSECTOR -61, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA · Gurugram | Oct 2022 | Oct 2023 | Oct 2026 (2) | Completed Jul 2024 · 9 mo late |
| SMARTWORLD ORCHARDSECTOR-61 · Gurugram | Oct 2022 | Dec 2024 | Dec 2025 (1) | Completed Jul 2024 · on time |
| SMARTWORLD ORCHARDSECTOR -61, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA. · Gurugram | Nov 2021 | Dec 2024 | None | Registration lapsed |
| SMARTWORLD ORCHARDSECTOR -61, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA. · Gurugram | Oct 2021 | Oct 2023 | None | Registration lapsed |
| SMARTWORLD GEMSSECTOR-89, GURUGRAM MANESAR U RBAN COMPLEX, GURUGRAM, HARYANA. · Gurugram | Oct 2021 | Sept 2025 | Sept 2026 (1) | Completed Jul 2024 · on time |
Companies these projects are registered under (6)
- ADHIKAANSH REALTORS PRIVATE LIMITED · Gurugram
- ETSY REALCON PRIVATE LIMITED · Gurugram
- NOURISH DEVELOPERS PRIVATE LIMITED · Gurugram
- RIVERDAY INFRASTRUCTURE PRIVATE LIMITED · Gurugram
- SUPOSHAA REALCON PRIVATE LIMITED · Gurugram
- SVABHUMI REALTORS PRIVATE LIMITED · Gurugram
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- HARERA Gurugram — Gurugram
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does Smartworld Developers deliver on time?+
Per the regulators' own registers, in Gurugram, 3 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many Smartworld Developers projects are registered with RERA?+
14 with HARERA Gurugram (Gurugram). 4 of them are completed and 8 are ongoing.
Which Smartworld Developers projects are running late?+
None of Smartworld Developers's ongoing registrations is past its latest RERA date as of 2026-10-06.
How can I check a Smartworld project's RERA record myself?+
Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.
Compare Smartworld with the other developers we track, or see the Smartworld homes listed now.