Delivery record · from RERA

Is Signature Global reliable?

Per the regulators' own registers, in Gurugram, 9 of 30 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 4 months after that date.

71 registrations · checked 6 October 2026

Gurugram · HARERA Gurugram

71

Registered projects

30 completed · 36 ongoing

30%

Finished by the date promised at registration

9 of 30 completed projects

4months

Median delay past the promised date

Across completed projects (on-time = 0)

0

Overdue now

Ongoing projects past their registration validity with no occupancy certificate on file

Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.

Every registration

Signature Global projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
TONINO LAMBORGHINI RESIDENCES GURUGRAMVILLAGE- FAZILPUR JHARSA, SEC TOR-71, GURUGRAM, HARYANA · GurugramApr 2026Jan 2033NoneIn progress
SIGNATURE GLOBAL SARVAM AT DXP ESTATEVILLAGE- GADAULI KALAN, SECTO R-37D, GURUGRAM, HARYANA · GurugramNov 2025Dec 2032NoneIn progress
CITY OF COLOURS NH-8 EXTN.-1VILLAGE- SIDHRAWALI, GURUGRAM , HARYANA · GurugramJun 2025Dec 2028NoneIn progress
SIGNATUREGLOBAL SPECTRUM SQUAREVILLAGE- SIDHRAWALI, GURUGRAM , HARYANA · GurugramJun 2025Dec 2028NoneIn progress
SIGNATUREGLOBAL CLOVERDALE SPRVILLAGE - FAIZALPUR JHARSA, S ECTOR-71, GURUGRAM, HARYANA · GurugramJun 2025May 2031NoneIn progress
SIGNATURE GLOBAL PARK-I EXT.VILLAGE-DUNELA, SECTOR-36, SO HNA, GURUGRAM · GurugramMay 2025Mar 2029NoneIn progress
SIGNATURE GLOBAL PARK-I EXT.VILLAGE-DUNELA, SECTOR-36, SO HNA, GURUGRAM · GurugramMay 2025Mar 2027NoneIn progress
SIGNATURE GLOBAL CITY 37D-1AVILLAGE - GADAULI KALAN, SECT OR-37D, GURUGRAM, HARYANA · GurugramMar 2025Jan 2027NoneIn progress
SIGNATURE GLOBAL CITY 37D EXTN.VILLAGE- GADAULI KALAN, SECTO R-37D, GURUGRAM, HARYANA · GurugramMar 2025Jan 2027NoneIn progress
SIGNATURE GLOBAL CITY 37D EXTN.VILLAGE- GADAULI KALAN, SECTO R-37D, GURUGRAM, HARYANA · GurugramMar 2025Jan 2027NoneIn progress
CITY OF COLOURS NH-8VILLAGE-SIDHRAWALI, GURUGRAM HARYANA · GurugramOct 2024Dec 2028NoneIn progress
DAXIN GURUGRAM'S X FACTORVILLAGE- BHONDSI, GHAMROJ & M AHENDWARA, SOHNA, GURUGRAM, HARYANA · GurugramSept 2024Dec 2028NoneIn progress
DAXIN VISTASVILLAGE- BHONDSI, GHAMROJ & M AHENDWARA, SOHNA, GURUGRAM, HARYANA · GurugramSept 2024Jan 2028NoneIn progress
SIGNATUREGLOBAL TWIN TOWER DXPVILLAGE-HAYATPUR, SECTOR-84, GURUGRAM, HARYANA · GurugramSept 2024May 2030NoneIn progress
SIGNATURE GLOBAL PROXIMA-1 EXTN.VILLAGE - HAYATPUR, SECTOR -8 9, GURUGRAM, HARYANA · GurugramJul 2024Jun 2025Jun 2027 (2)In progress
SIGNATUREGLOBAL TITANIUM SPRVILLAGE- FAZILPUR JHARSA, SEC TOR-71, GURUGRAM, HARYANA · GurugramJun 2024Feb 2031NoneIn progress
DE-LUXE DXPVILLAGE - GADAULI KALAN, SECT OR-37D, GURUGRAM, HARYANA · GurugramFeb 2024Mar 2031NoneIn progress
SIGNATURE GLOBAL ASPIRE EXTN.VILLAGE - DHORK, SECTOR-95, G URUGRAM HARYANA · GurugramOct 2023Feb 2026Feb 2027 (1)In progress
SIGNATURE GLOBAL CITY 37D-2VILLAGE - GADAULI KALAN, SECT OR-37D, GURUGRAM, HARYANA · GurugramOct 2023Feb 2026NoneCompleted Feb 2026 · on time
SIGNATURE GLOBAL CITY 93VILLAGE WAZIRPUR, SECTOR 93, GURUGRAM, HARYANA · GurugramJan 2023Nov 2027NoneIn progress
Show all 71 registrations
SIGNATURE GLOBAL CITY 93VILLAGE WAZIRPUR, SECTOR 93, GURUGRAM, HARYANA · GurugramJan 2023Apr 2025Apr 2027 (2)In progress
SIGNATURE GLOBAL CITY 92-2VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · GurugramJan 2023Mar 2024Mar 2026 (2)Completed Jul 2026 · 27 mo late
SIGNATURE GLOBAL CITY 92-2VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · GurugramJan 2023Dec 2026NoneIn progress
SIGNATURE GLOBAL CITY 92-(II)VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · GurugramJan 2023Mar 2025Mar 2027 (2)In progress
SIGNATURE GLOBAL CITY 79B -1VILLAGE, NAUNGRANPUR, SECTOR- 79B GURUGRAM, HARYANA · GurugramJan 2023Dec 2026NoneIn progress
SIGNATURE GLOBAL PARK-I (2)VILLAGE DHUNELA, SECTOR 36, G URUGRAM · GurugramJan 2023Mar 2025Mar 2027 (2)In progress
SIGNATURE GLOBAL CITY 79BVILLAGE, NAUNGRANPUR, SECTOR- 79B GURUGRAM, HARYANA · GurugramDec 2022Apr 2024Apr 2027 (3)In progress
SIGNATURE GLOBAL CITY 37D-(2)VILLAGE GADULI KALAN, SECTOR- 37D, GURUGRAM · GurugramOct 2022Feb 2026NoneCompleted Nov 2025 · on time
SIGNATURE GLOBAL CITY 81(2)VILLAGE NAKHDOLA,SECTOR-81, G URUGRAM · GurugramOct 2022Feb 2026Feb 2027 (1)In progress
SIGNATURE GLOBAL CITY 37D II(2)VILLAGE-GADOLIKALAN, SECTOR-3 7/D, GURUGRAM · GurugramOct 2022Feb 2026NoneRegistration lapsed
SIGNATURE GLOBAL CITY 63A(2)VILLAGE-KADARPUR, SECTOR-63A, GURUGRAM · GurugramOct 2022Feb 2026NoneRegistration lapsed
SIGNATURE GLOBAL SCO 88AVILLAGE-HARSARU, SECTOR-88A, GURUGRAM · GurugramSept 2022Jul 2023Jul 2025 (2)Completed Jun 2025 · 22 mo late
SIGNATURE GLOBAL SCOII 88AVILLAGE-HARSARU, SECTOR-88A, GURUGRAM · GurugramSept 2022Jul 2023Jul 2025 (2)Completed Jun 2025 · 22 mo late
SIGNATURE GLOBAL 37D II(1)VILLAGE-GADOLI KALAN, SECTOR- 37/D, GURUGRAM · GurugramJul 2022Feb 2025Feb 2027 (2)In progress
SIGNATURE GLOBAL CITY 63A (1)VILLAGE KADARPUR SECTOR 63 · GurugramJun 2022Feb 2025Feb 2027 (2)In progress
SIGNATURE GLOBAL SCO - 37DVILLAGE-BASAI, SECTOR-37/D, G URUGRAM · GurugramJun 2022Mar 2023Mar 2025 (2)Completed May 2024 · 13 mo late
SIGNATUEGLOBAL PARK V (2)VILLAGE DHUNELA, SECTOR 36, S OHNA DISTRICT,GURUGRAM · GurugramJun 2022Sept 2024NoneCompleted Jul 2026 · 21 mo late
SIGNATURE GLOBAL PARK IV(2)VILLAGE HARIYAHARA, SECTOR 36 , SOHNA, DISTT. GURUGRAM · GurugramJun 2022Sept 2024Sept 2025 (1)Completed Oct 2024 · <1 mo late
SIGNATURE GLOBAL SCO 36 SOHNAVILLAGE DHUNELA, SECTOR 36, S OHNA DISTRICT,GURUGRAM · GurugramJun 2022Jun 2023Jun 2025 (2)Completed Dec 2024 · 18 mo late
SIGNATUREGLOBAL CITY 37D IIVILLAGE-GADOLI KALAN, SECTOR- 37D, GURUGRAM · GurugramMar 2022Feb 2023Feb 2027 (4)In progress
SIGNATURE GLOBAL CITY 63AVILLAGE KADARPUR SECTOR 63 · GurugramMar 2022Feb 2023Feb 2027 (4)In progress
SIGNATURE GLOBAL IMPERIALVILLAGE-HARSARU, SECTOR-88A, GURUGRAM · GurugramMar 2022Feb 2026Feb 2027 (1)In progress
SIGNATURE GLOBAL INFINITYSECTOR-36 · GurugramDec 2021Feb 2026Feb 2027 (1)In progress
SIGNATURE GLOBAL PARK III EXT.(PHASE-2)VILLAGE DHUNELA, SECTOR-36, S OHNA, GURUGRAM · GurugramOct 2021Jun 2024Jun 2025 (1)Completed Oct 2024 · 4 mo late
SIGNATURE GLOBAL PARK III-(PHASE-2)VILLAGE DHUNELA, SECTOR 36, S OHNA, DISTT. GURUGRAM · GurugramOct 2021Aug 2024Aug 2025 (1)Completed Feb 2024 · on time
SIGNATURE GLOBAL PARK-1(1)VILLAGE DHUNELA, SECTOR 36 · GurugramOct 2021Oct 2024Oct 2026 (2)In progress
SIGNATURE GLOBAL CITY 81VILLAGE NAKHDOLA, SECTOR 81 · GurugramJul 2021Jun 2023Jun 2026 (3)Registration lapsed
SIGNATURE GLOBAL CITY 81-(1)VILLAGE NAKHDOLA, SECTOR 81 · GurugramJul 2021Feb 2024Feb 2026 (2)Registration lapsed
SIGNATURE GLOBAL CITY 92VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · GurugramJul 2021Apr 2023Apr 2026 (3)Completed Jul 2026 · 38 mo late
SIGNATURE GLOBAL CITY 92-(1)VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · GurugramJul 2021Dec 2023Dec 2026 (3)In progress
SIGNATURE GLOBAL PARK -II (PHASE II)VILLAGE DHUNELA, SECTOR-36 · GurugramJul 2021Mar 2023Mar 2025 (2)Completed Jul 2024 · 16 mo late
SIGNATURE GLOBAL CITY 37DVILLAGE GADULI KALAN, SECTOR- 37D, GURUGRAM · GurugramJul 2021Apr 2023Apr 2025 (2)Registration lapsed
SIGNATURE GLOBAL CITY 37D - 1VILLAGE GADULI KALAN, SECTOR- 37D, GURUGRAM · GurugramJul 2021Sept 2023Sept 2025 (2)Completed Feb 2024 · 5 mo late
SIGNATURE GLOBAL PARK -III EXT.VILLAGE DHUNELA, SECTOR 36 · GurugramJan 2021Dec 2023Dec 2025 (2)Completed Feb 2024 · 2 mo late
SIGNATURE GLOBAL PARK-III1309 13TH FLOOR DR. GOPAL DAS BHAWAN 28 BARAKHAMBA ROAD NEW DELHI 110001 · GurugramNov 2020Sept 2022NoneCompleted Sept 2021 · on time
SIGNATURE GLOBAL PARK IIVILLAGE DHUNELA, SECTOR 36 · GurugramNov 2020Dec 2022Dec 2023 (1)Completed Mar 2022 · on time
SIGNATURE GLOBAL PARK IIIVILLAGE DHUNELA, SECTOR 36 · GurugramNov 2020Dec 2022Dec 2023 (1)Completed Mar 2022 · on time
SIGNATURE GLOBAL SUPERBIAVILLAGE DHORKA, SECTOR 95, GU RUGRAM, HARYANA · GurugramNov 2020Dec 2024Dec 2026 (2)In progress
SIGNATURE GLOBAL PARK IVVILLAGE HARIYAHARA,SECTOR-36 · GurugramOct 2020Jul 2022Jul 2023 (1)Completed Jul 2022 · on time
SIGNATURE GLOBAL PARK VVILLAGE HARIYAHARA, SECTOR-36 · GurugramOct 2020Jul 2022Jul 2023 (1)Completed Nov 2022 · 4 mo late
SIGNATURE GLOBAL PARK IVVILLAGE HARIYAHARA, SECTOR-36 · GurugramJul 2020Dec 2021NoneCompleted May 2022 · 4 mo late
SIGNATURE GLOBAL PARK VVILLAGE HARIYAHARA, SECTOR-36 · GurugramJul 2020Dec 2021NoneCompleted May 2022 · 4 mo late
GOLF GREENS-79VILLAGE NAURANGPUR, SECTOR 79 · GurugramJun 2020Jul 2024NoneCompleted Sept 2024 · 1 mo late
SIGNATUREGLOBAL PROXIMA 2VILLAGE HAYATPUR, SECTOR 89 G URUGRAM-MANESAR URBAN COMPLEX, HARYANA · GurugramJan 2020Dec 2023NoneCompleted Mar 2024 · 3 mo late
SIGNATUREGLOBAL PROXIMA 1VILLAGE HAYATPUR, SECTOR 89 G URUGRAM, HARYANA · GurugramDec 2019Dec 2023Jun 2026 (2)Completed Mar 2026 · 27 mo late
SIGNATUREGLOBAL ASPIREVILLAGE DHORKA, SECTOR 95 GUR UGRAM, HARYANA · GurugramNov 2019Oct 2023Apr 2027 (4)In progress
SIGNATUREGLOBAL PRIMEVILLAGE KADARPUR, SECTOR 63AG URUGRAM-MANESAR URBAN COMPLEX,DIST.GURUGRAM, HARYANA · GurugramNov 2019Oct 2023Apr 2025 (1)Completed Dec 2024 · 14 mo late
SIGNATURE GLOBAL PARK-IIVILLAGE DHUNELA, SECTOR- 36, SOHNA · GurugramAug 2019Jun 2021NoneCompleted May 2021 · on time
SIGNATURE GLOBAL PARK-IIIVILLAGE DHUNELA, SECTOR-36, S OHNA · GurugramAug 2019Dec 2020NoneCompleted Sept 2021 · 8 mo late
SYNERASECTOR-81, GURURGAM · GurugramJun 2017May 2021NoneCompleted Oct 2019 · on time
GROUP HOUSING COLONYSEC-37-D, SOHNA, GURUGRAM · GurugramJun 2017May 2021Jan 2023 (1)Completed Jan 2023 · 20 mo late
Companies these projects are registered under (24)
  • FOREVER BUILDTECH PRIVATE LIMITED · Gurugram
  • JMK HOLDINGS PVT. LTD. · Gurugram
  • ROSE BUILDING SOLUTIONS PRIVATE LIMITED · Gurugram
  • SIGNATTUREGLOBAL HOMES LIMITED · Gurugram
  • SIGNATURE BUILDERS PRIVATE LIMITED · Gurugram
  • SIGNATURE GLOBAL (INDIA) PVT.LTD · Gurugram
  • SIGNATURE GLOBAL DEVELOPERS PRIVATE LIMITED · Gurugram
  • SIGNATURE INFRABUILD PRIVATE LIMITED · Gurugram
  • SIGNATURE INFRABUILD PVT. LTD. · Gurugram
  • SIGNATURE INFRBUILD PVT. LTD. · Gurugram
  • SIGNATUREGLOBAL (INDIA) LIMITED · Gurugram
  • SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED · Gurugram
  • SIGNATUREGLOBAL (INDIA)LIMITED · Gurugram
  • SIGNATUREGLOBAL BUSINESS PARK PRIVATE LIMITED · Gurugram
  • SIGNATUREGLOBAL DEVELOPERS PRIVATE LIMITED · Gurugram
  • SIGNATUREGLOBAL DEVELOPERS PVT LTD · Gurugram
  • SIGNATUREGLOBAL DEVELOPERS PVT. LTD. · Gurugram
  • SIGNATUREGLOBAL DEVELPERS PVT. LTD · Gurugram
  • SIGNATUREGLOBAL HOMES PRIVATE LIMITED · Gurugram
  • SIGNATUREGLOBAL HOMES PVT LTD · Gurugram
  • SIGNATUREGLOBAL HOMES PVT. LTD. · Gurugram
  • SINATUREGLOBAL HOMES PVT LTD · Gurugram
  • STERNAL BUILDCON PRIVATE LIMITED · Gurugram
  • STERNAL BUILDCON PVT.LTD. · Gurugram

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • HARERA Gurugram — Gurugram
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Signature Global deliver on time?+

Per the regulators' own registers, in Gurugram, 9 of 30 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 4 months after that date. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Signature Global projects are registered with RERA?+

71 with HARERA Gurugram (Gurugram). 30 of them are completed and 36 are ongoing.

Which Signature Global projects are running late?+

None of Signature Global's ongoing registrations is past its latest RERA date as of 2026-10-06.

How can I check a Signature Global project's RERA record myself?+

Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare Signature Global with the other developers we track, or see the Signature Global homes listed now.