Per the regulators' own registers, in Gurugram, 9 of 30 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 4 months after that date.
71 registrations · checked 6 October 2026
Gurugram · HARERA Gurugram
71
Registered projects
30 completed · 36 ongoing
30%
Finished by the date promised at registration
9 of 30 completed projects
4months
Median delay past the promised date
Across completed projects (on-time = 0)
0
Overdue now
Ongoing projects past their registration validity with no occupancy certificate on file
Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.
Every registration
Signature Global projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| TONINO LAMBORGHINI RESIDENCES GURUGRAMVILLAGE- FAZILPUR JHARSA, SEC TOR-71, GURUGRAM, HARYANA · Gurugram | Apr 2026 | Jan 2033 | None | In progress |
| SIGNATURE GLOBAL SARVAM AT DXP ESTATEVILLAGE- GADAULI KALAN, SECTO R-37D, GURUGRAM, HARYANA · Gurugram | Nov 2025 | Dec 2032 | None | In progress |
| CITY OF COLOURS NH-8 EXTN.-1VILLAGE- SIDHRAWALI, GURUGRAM , HARYANA · Gurugram | Jun 2025 | Dec 2028 | None | In progress |
| SIGNATUREGLOBAL SPECTRUM SQUAREVILLAGE- SIDHRAWALI, GURUGRAM , HARYANA · Gurugram | Jun 2025 | Dec 2028 | None | In progress |
| SIGNATUREGLOBAL CLOVERDALE SPRVILLAGE - FAIZALPUR JHARSA, S ECTOR-71, GURUGRAM, HARYANA · Gurugram | Jun 2025 | May 2031 | None | In progress |
| SIGNATURE GLOBAL PARK-I EXT.VILLAGE-DUNELA, SECTOR-36, SO HNA, GURUGRAM · Gurugram | May 2025 | Mar 2029 | None | In progress |
| SIGNATURE GLOBAL PARK-I EXT.VILLAGE-DUNELA, SECTOR-36, SO HNA, GURUGRAM · Gurugram | May 2025 | Mar 2027 | None | In progress |
| SIGNATURE GLOBAL CITY 37D-1AVILLAGE - GADAULI KALAN, SECT OR-37D, GURUGRAM, HARYANA · Gurugram | Mar 2025 | Jan 2027 | None | In progress |
| SIGNATURE GLOBAL CITY 37D EXTN.VILLAGE- GADAULI KALAN, SECTO R-37D, GURUGRAM, HARYANA · Gurugram | Mar 2025 | Jan 2027 | None | In progress |
| SIGNATURE GLOBAL CITY 37D EXTN.VILLAGE- GADAULI KALAN, SECTO R-37D, GURUGRAM, HARYANA · Gurugram | Mar 2025 | Jan 2027 | None | In progress |
| CITY OF COLOURS NH-8VILLAGE-SIDHRAWALI, GURUGRAM HARYANA · Gurugram | Oct 2024 | Dec 2028 | None | In progress |
| DAXIN GURUGRAM'S X FACTORVILLAGE- BHONDSI, GHAMROJ & M AHENDWARA, SOHNA, GURUGRAM, HARYANA · Gurugram | Sept 2024 | Dec 2028 | None | In progress |
| DAXIN VISTASVILLAGE- BHONDSI, GHAMROJ & M AHENDWARA, SOHNA, GURUGRAM, HARYANA · Gurugram | Sept 2024 | Jan 2028 | None | In progress |
| SIGNATUREGLOBAL TWIN TOWER DXPVILLAGE-HAYATPUR, SECTOR-84, GURUGRAM, HARYANA · Gurugram | Sept 2024 | May 2030 | None | In progress |
| SIGNATURE GLOBAL PROXIMA-1 EXTN.VILLAGE - HAYATPUR, SECTOR -8 9, GURUGRAM, HARYANA · Gurugram | Jul 2024 | Jun 2025 | Jun 2027 (2) | In progress |
| SIGNATUREGLOBAL TITANIUM SPRVILLAGE- FAZILPUR JHARSA, SEC TOR-71, GURUGRAM, HARYANA · Gurugram | Jun 2024 | Feb 2031 | None | In progress |
| DE-LUXE DXPVILLAGE - GADAULI KALAN, SECT OR-37D, GURUGRAM, HARYANA · Gurugram | Feb 2024 | Mar 2031 | None | In progress |
| SIGNATURE GLOBAL ASPIRE EXTN.VILLAGE - DHORK, SECTOR-95, G URUGRAM HARYANA · Gurugram | Oct 2023 | Feb 2026 | Feb 2027 (1) | In progress |
| SIGNATURE GLOBAL CITY 37D-2VILLAGE - GADAULI KALAN, SECT OR-37D, GURUGRAM, HARYANA · Gurugram | Oct 2023 | Feb 2026 | None | Completed Feb 2026 · on time |
| SIGNATURE GLOBAL CITY 93VILLAGE WAZIRPUR, SECTOR 93, GURUGRAM, HARYANA · Gurugram | Jan 2023 | Nov 2027 | None | In progress |
Show all 71 registrationsShow fewer
| SIGNATURE GLOBAL CITY 93VILLAGE WAZIRPUR, SECTOR 93, GURUGRAM, HARYANA · Gurugram | Jan 2023 | Apr 2025 | Apr 2027 (2) | In progress |
| SIGNATURE GLOBAL CITY 92-2VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · Gurugram | Jan 2023 | Mar 2024 | Mar 2026 (2) | Completed Jul 2026 · 27 mo late |
| SIGNATURE GLOBAL CITY 92-2VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · Gurugram | Jan 2023 | Dec 2026 | None | In progress |
| SIGNATURE GLOBAL CITY 92-(II)VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · Gurugram | Jan 2023 | Mar 2025 | Mar 2027 (2) | In progress |
| SIGNATURE GLOBAL CITY 79B -1VILLAGE, NAUNGRANPUR, SECTOR- 79B GURUGRAM, HARYANA · Gurugram | Jan 2023 | Dec 2026 | None | In progress |
| SIGNATURE GLOBAL PARK-I (2)VILLAGE DHUNELA, SECTOR 36, G URUGRAM · Gurugram | Jan 2023 | Mar 2025 | Mar 2027 (2) | In progress |
| SIGNATURE GLOBAL CITY 79BVILLAGE, NAUNGRANPUR, SECTOR- 79B GURUGRAM, HARYANA · Gurugram | Dec 2022 | Apr 2024 | Apr 2027 (3) | In progress |
| SIGNATURE GLOBAL CITY 37D-(2)VILLAGE GADULI KALAN, SECTOR- 37D, GURUGRAM · Gurugram | Oct 2022 | Feb 2026 | None | Completed Nov 2025 · on time |
| SIGNATURE GLOBAL CITY 81(2)VILLAGE NAKHDOLA,SECTOR-81, G URUGRAM · Gurugram | Oct 2022 | Feb 2026 | Feb 2027 (1) | In progress |
| SIGNATURE GLOBAL CITY 37D II(2)VILLAGE-GADOLIKALAN, SECTOR-3 7/D, GURUGRAM · Gurugram | Oct 2022 | Feb 2026 | None | Registration lapsed |
| SIGNATURE GLOBAL CITY 63A(2)VILLAGE-KADARPUR, SECTOR-63A, GURUGRAM · Gurugram | Oct 2022 | Feb 2026 | None | Registration lapsed |
| SIGNATURE GLOBAL SCO 88AVILLAGE-HARSARU, SECTOR-88A, GURUGRAM · Gurugram | Sept 2022 | Jul 2023 | Jul 2025 (2) | Completed Jun 2025 · 22 mo late |
| SIGNATURE GLOBAL SCOII 88AVILLAGE-HARSARU, SECTOR-88A, GURUGRAM · Gurugram | Sept 2022 | Jul 2023 | Jul 2025 (2) | Completed Jun 2025 · 22 mo late |
| SIGNATURE GLOBAL 37D II(1)VILLAGE-GADOLI KALAN, SECTOR- 37/D, GURUGRAM · Gurugram | Jul 2022 | Feb 2025 | Feb 2027 (2) | In progress |
| SIGNATURE GLOBAL CITY 63A (1)VILLAGE KADARPUR SECTOR 63 · Gurugram | Jun 2022 | Feb 2025 | Feb 2027 (2) | In progress |
| SIGNATURE GLOBAL SCO - 37DVILLAGE-BASAI, SECTOR-37/D, G URUGRAM · Gurugram | Jun 2022 | Mar 2023 | Mar 2025 (2) | Completed May 2024 · 13 mo late |
| SIGNATUEGLOBAL PARK V (2)VILLAGE DHUNELA, SECTOR 36, S OHNA DISTRICT,GURUGRAM · Gurugram | Jun 2022 | Sept 2024 | None | Completed Jul 2026 · 21 mo late |
| SIGNATURE GLOBAL PARK IV(2)VILLAGE HARIYAHARA, SECTOR 36 , SOHNA, DISTT. GURUGRAM · Gurugram | Jun 2022 | Sept 2024 | Sept 2025 (1) | Completed Oct 2024 · <1 mo late |
| SIGNATURE GLOBAL SCO 36 SOHNAVILLAGE DHUNELA, SECTOR 36, S OHNA DISTRICT,GURUGRAM · Gurugram | Jun 2022 | Jun 2023 | Jun 2025 (2) | Completed Dec 2024 · 18 mo late |
| SIGNATUREGLOBAL CITY 37D IIVILLAGE-GADOLI KALAN, SECTOR- 37D, GURUGRAM · Gurugram | Mar 2022 | Feb 2023 | Feb 2027 (4) | In progress |
| SIGNATURE GLOBAL CITY 63AVILLAGE KADARPUR SECTOR 63 · Gurugram | Mar 2022 | Feb 2023 | Feb 2027 (4) | In progress |
| SIGNATURE GLOBAL IMPERIALVILLAGE-HARSARU, SECTOR-88A, GURUGRAM · Gurugram | Mar 2022 | Feb 2026 | Feb 2027 (1) | In progress |
| SIGNATURE GLOBAL INFINITYSECTOR-36 · Gurugram | Dec 2021 | Feb 2026 | Feb 2027 (1) | In progress |
| SIGNATURE GLOBAL PARK III EXT.(PHASE-2)VILLAGE DHUNELA, SECTOR-36, S OHNA, GURUGRAM · Gurugram | Oct 2021 | Jun 2024 | Jun 2025 (1) | Completed Oct 2024 · 4 mo late |
| SIGNATURE GLOBAL PARK III-(PHASE-2)VILLAGE DHUNELA, SECTOR 36, S OHNA, DISTT. GURUGRAM · Gurugram | Oct 2021 | Aug 2024 | Aug 2025 (1) | Completed Feb 2024 · on time |
| SIGNATURE GLOBAL PARK-1(1)VILLAGE DHUNELA, SECTOR 36 · Gurugram | Oct 2021 | Oct 2024 | Oct 2026 (2) | In progress |
| SIGNATURE GLOBAL CITY 81VILLAGE NAKHDOLA, SECTOR 81 · Gurugram | Jul 2021 | Jun 2023 | Jun 2026 (3) | Registration lapsed |
| SIGNATURE GLOBAL CITY 81-(1)VILLAGE NAKHDOLA, SECTOR 81 · Gurugram | Jul 2021 | Feb 2024 | Feb 2026 (2) | Registration lapsed |
| SIGNATURE GLOBAL CITY 92VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · Gurugram | Jul 2021 | Apr 2023 | Apr 2026 (3) | Completed Jul 2026 · 38 mo late |
| SIGNATURE GLOBAL CITY 92-(1)VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM · Gurugram | Jul 2021 | Dec 2023 | Dec 2026 (3) | In progress |
| SIGNATURE GLOBAL PARK -II (PHASE II)VILLAGE DHUNELA, SECTOR-36 · Gurugram | Jul 2021 | Mar 2023 | Mar 2025 (2) | Completed Jul 2024 · 16 mo late |
| SIGNATURE GLOBAL CITY 37DVILLAGE GADULI KALAN, SECTOR- 37D, GURUGRAM · Gurugram | Jul 2021 | Apr 2023 | Apr 2025 (2) | Registration lapsed |
| SIGNATURE GLOBAL CITY 37D - 1VILLAGE GADULI KALAN, SECTOR- 37D, GURUGRAM · Gurugram | Jul 2021 | Sept 2023 | Sept 2025 (2) | Completed Feb 2024 · 5 mo late |
| SIGNATURE GLOBAL PARK -III EXT.VILLAGE DHUNELA, SECTOR 36 · Gurugram | Jan 2021 | Dec 2023 | Dec 2025 (2) | Completed Feb 2024 · 2 mo late |
| SIGNATURE GLOBAL PARK-III1309 13TH FLOOR DR. GOPAL DAS BHAWAN 28 BARAKHAMBA ROAD NEW DELHI 110001 · Gurugram | Nov 2020 | Sept 2022 | None | Completed Sept 2021 · on time |
| SIGNATURE GLOBAL PARK IIVILLAGE DHUNELA, SECTOR 36 · Gurugram | Nov 2020 | Dec 2022 | Dec 2023 (1) | Completed Mar 2022 · on time |
| SIGNATURE GLOBAL PARK IIIVILLAGE DHUNELA, SECTOR 36 · Gurugram | Nov 2020 | Dec 2022 | Dec 2023 (1) | Completed Mar 2022 · on time |
| SIGNATURE GLOBAL SUPERBIAVILLAGE DHORKA, SECTOR 95, GU RUGRAM, HARYANA · Gurugram | Nov 2020 | Dec 2024 | Dec 2026 (2) | In progress |
| SIGNATURE GLOBAL PARK IVVILLAGE HARIYAHARA,SECTOR-36 · Gurugram | Oct 2020 | Jul 2022 | Jul 2023 (1) | Completed Jul 2022 · on time |
| SIGNATURE GLOBAL PARK VVILLAGE HARIYAHARA, SECTOR-36 · Gurugram | Oct 2020 | Jul 2022 | Jul 2023 (1) | Completed Nov 2022 · 4 mo late |
| SIGNATURE GLOBAL PARK IVVILLAGE HARIYAHARA, SECTOR-36 · Gurugram | Jul 2020 | Dec 2021 | None | Completed May 2022 · 4 mo late |
| SIGNATURE GLOBAL PARK VVILLAGE HARIYAHARA, SECTOR-36 · Gurugram | Jul 2020 | Dec 2021 | None | Completed May 2022 · 4 mo late |
| GOLF GREENS-79VILLAGE NAURANGPUR, SECTOR 79 · Gurugram | Jun 2020 | Jul 2024 | None | Completed Sept 2024 · 1 mo late |
| SIGNATUREGLOBAL PROXIMA 2VILLAGE HAYATPUR, SECTOR 89 G URUGRAM-MANESAR URBAN COMPLEX, HARYANA · Gurugram | Jan 2020 | Dec 2023 | None | Completed Mar 2024 · 3 mo late |
| SIGNATUREGLOBAL PROXIMA 1VILLAGE HAYATPUR, SECTOR 89 G URUGRAM, HARYANA · Gurugram | Dec 2019 | Dec 2023 | Jun 2026 (2) | Completed Mar 2026 · 27 mo late |
| SIGNATUREGLOBAL ASPIREVILLAGE DHORKA, SECTOR 95 GUR UGRAM, HARYANA · Gurugram | Nov 2019 | Oct 2023 | Apr 2027 (4) | In progress |
| SIGNATUREGLOBAL PRIMEVILLAGE KADARPUR, SECTOR 63AG URUGRAM-MANESAR URBAN COMPLEX,DIST.GURUGRAM, HARYANA · Gurugram | Nov 2019 | Oct 2023 | Apr 2025 (1) | Completed Dec 2024 · 14 mo late |
| SIGNATURE GLOBAL PARK-IIVILLAGE DHUNELA, SECTOR- 36, SOHNA · Gurugram | Aug 2019 | Jun 2021 | None | Completed May 2021 · on time |
| SIGNATURE GLOBAL PARK-IIIVILLAGE DHUNELA, SECTOR-36, S OHNA · Gurugram | Aug 2019 | Dec 2020 | None | Completed Sept 2021 · 8 mo late |
| SYNERASECTOR-81, GURURGAM · Gurugram | Jun 2017 | May 2021 | None | Completed Oct 2019 · on time |
| GROUP HOUSING COLONYSEC-37-D, SOHNA, GURUGRAM · Gurugram | Jun 2017 | May 2021 | Jan 2023 (1) | Completed Jan 2023 · 20 mo late |
Companies these projects are registered under (24)
- FOREVER BUILDTECH PRIVATE LIMITED · Gurugram
- JMK HOLDINGS PVT. LTD. · Gurugram
- ROSE BUILDING SOLUTIONS PRIVATE LIMITED · Gurugram
- SIGNATTUREGLOBAL HOMES LIMITED · Gurugram
- SIGNATURE BUILDERS PRIVATE LIMITED · Gurugram
- SIGNATURE GLOBAL (INDIA) PVT.LTD · Gurugram
- SIGNATURE GLOBAL DEVELOPERS PRIVATE LIMITED · Gurugram
- SIGNATURE INFRABUILD PRIVATE LIMITED · Gurugram
- SIGNATURE INFRABUILD PVT. LTD. · Gurugram
- SIGNATURE INFRBUILD PVT. LTD. · Gurugram
- SIGNATUREGLOBAL (INDIA) LIMITED · Gurugram
- SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED · Gurugram
- SIGNATUREGLOBAL (INDIA)LIMITED · Gurugram
- SIGNATUREGLOBAL BUSINESS PARK PRIVATE LIMITED · Gurugram
- SIGNATUREGLOBAL DEVELOPERS PRIVATE LIMITED · Gurugram
- SIGNATUREGLOBAL DEVELOPERS PVT LTD · Gurugram
- SIGNATUREGLOBAL DEVELOPERS PVT. LTD. · Gurugram
- SIGNATUREGLOBAL DEVELPERS PVT. LTD · Gurugram
- SIGNATUREGLOBAL HOMES PRIVATE LIMITED · Gurugram
- SIGNATUREGLOBAL HOMES PVT LTD · Gurugram
- SIGNATUREGLOBAL HOMES PVT. LTD. · Gurugram
- SINATUREGLOBAL HOMES PVT LTD · Gurugram
- STERNAL BUILDCON PRIVATE LIMITED · Gurugram
- STERNAL BUILDCON PVT.LTD. · Gurugram
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- HARERA Gurugram — Gurugram
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does Signature Global deliver on time?+
Per the regulators' own registers, in Gurugram, 9 of 30 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 4 months after that date. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many Signature Global projects are registered with RERA?+
71 with HARERA Gurugram (Gurugram). 30 of them are completed and 36 are ongoing.
Which Signature Global projects are running late?+
None of Signature Global's ongoing registrations is past its latest RERA date as of 2026-10-06.
How can I check a Signature Global project's RERA record myself?+
Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.