Delivery record · from RERA
Is DLF reliable?
Per the regulators' own registers, in Gurugram, 30 of 32 completed projects with a recorded completion date finished by the date promised at RERA registration; in Tamil Nadu, 1 of 1 registered projects are marked completed, 1 of them without any extension.
46 registrations · checked 6 October 2026
Gurugram · HARERA Gurugram
45
Registered projects
32 completed · 13 ongoing
94%
Finished by the date promised at registration
30 of 32 completed projects
0months
Median delay past the promised date
Across completed projects (on-time = 0)
1
Overdue now
Ongoing projects past their registration validity with no occupancy certificate on file
Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.
Tamil Nadu · TNRERA
1
Registered projects
1 completed · 0 ongoing
100%
Completed without any extension
1 of 1 completed projects
—
Needed an extension
0 of 0 projects whose promised date has passed
0
Overdue now
Ongoing projects past their latest RERA date and not marked completed
TNRERA marks projects as completed but publishes the completion date only inside PDF certificates, so we report completions and extensions rather than months of delay.
Every registration
DLF projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| THE AUREVASECTOR 63, GURUGRAM, HARYANA- 122102 · Gurugram | Sept 2026 | Oct 2033 | None | In progress |
| PRIVANA ENCLAVESECTOR 76/77 · Gurugram | Jul 2026 | Apr 2033 | None | In progress |
| PARC SOCIALTamil Nadu | Sept 2025 | — | None | Completed · no extension |
| CENTRAL 84SECTOR 84, GURUGRAM, HARYANA 122004 · Gurugram | Jul 2025 | Jun 2030 | None | In progress |
| DLF PRIVANA NORTHSECTOR 76/77 · Gurugram | Jun 2025 | Sept 2034 | None | In progress |
| THE DAHLIASR16, DLF 5, SECTOR 54 GURUGRA M · Gurugram | Oct 2024 | Dec 2031 | None | In progress |
| DLF PRIVANA WESTSECTOR 76/77 · Gurugram | Apr 2024 | Dec 2031 | None | In progress |
| CLUB ARCADESECTOR 91 · Gurugram | Apr 2024 | Mar 2028 | None | In progress |
| CENTRAL 74SECTOR 74 A GURUGRAM · Gurugram | Feb 2024 | Sept 2028 | None | In progress |
| DLF PRIVANA SOUTHSECTOR 76/77 · Gurugram | Dec 2023 | Jun 2031 | None | In progress |
| CENTRAL 67SECTOR 67 · Gurugram | Dec 2023 | Dec 2027 | None | Completed Aug 2026 · on time |
| ARCADE 68SECTOR 68, GURGAON · Gurugram | Feb 2023 | Nov 2027 | None | Completed Aug 2026 · on time |
| THE SIXTY THREESECTOR 63, GURUGRAM, HARYANA- 122102 · Gurugram | Jan 2023 | Mar 2030 | None | In progress |
| INDEPENDENT FLOORS AT DLF GARDENCITY ENCLAVE PHASE 2SECTOR 93 · Gurugram | Jan 2023 | Oct 2028 | None | In progress |
| ALAMEDA CENTRALSECTOR 73, GURUGRAM · Gurugram | Nov 2022 | Sept 2027 | None | Completed Dec 2025 · on time |
| INDEPENDENT FLOORS AT DLF GARDENCITY ENCLAVESECTOR 93 · Gurugram | Aug 2022 | Aug 2027 | None | In progress |
| INDEPENDENT FLOORS AT DLF CITY PHASE I, II & IIIDLF CITY PHASE I, DLF CITY PH ASE II & DLF CITY PHASE III · Gurugram | May 2022 | May 2025 | None | Completed Mar 2025 · on time |
| DLF GARDENCITY ENCLAVESECTOR 93 · Gurugram | Apr 2022 | Mar 2024 | Oct 2028 (2) | Completed Jun 2024 · 3 mo late |
| INDEPENDENT FLOORS AT DLF CITY PHASE I & IIIDLF CITY PHASE I & DLF CITY P HASE III, GURUGRAM · Gurugram | Apr 2022 | May 2025 | None | Completed Dec 2024 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE IVDLF CITY PHASE IV, SECTOR-27, GURUGRAM, HARYANA · Gurugram | Mar 2022 | May 2025 | None | Completed Dec 2023 · on time |
Show all 46 registrationsShow fewer
| GARDENCITY ARCADESECTOR 92, GURUGRAM · Gurugram | Feb 2022 | Apr 2025 | None | Completed Apr 2025 · on time |
| THE GROVEDLF 5, SECTOR 54 · Gurugram | Feb 2022 | Dec 2025 | None | Completed Jun 2024 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE I & IIIDLF CITY PHASE I AND DLF CITY PHASE III, GURUGRAM, HARYANA · Gurugram | Jan 2022 | Feb 2025 | None | Completed Dec 2024 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE IIIDLF CITY PHASE III, GURUGRAM, HARYANA · Gurugram | Dec 2021 | Feb 2025 | None | Completed Mar 2024 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE I, II & IIIDLF CITY PHASE I, II & III, G URUGRAM, HARYANA · Gurugram | Dec 2021 | Feb 2025 | None | Completed Aug 2024 · on time |
| INDEPENDENT FLOORS AT DLF GARDENCITYDLF GARDENCITY, SECTOR 91/92 · Gurugram | Dec 2021 | Mar 2025 | None | Completed Jun 2024 · on time |
| GARDENCITY CENTRALSECTOR 84, GURUGRAM, HARYANA · Gurugram | Nov 2021 | Aug 2024 | Aug 2025 (1) | Completed Feb 2025 · 5 mo late |
| INDEPENDENT FLOORS AT DLF CITY PHASE I & IIDLF CITY PHASE I AND DLF CITY PHASE II, GURUGRAM · Gurugram | Nov 2021 | Dec 2024 | None | Completed Oct 2024 · on time |
| INDEPENDENT FLOORS AT DLF ALAMEDA, SEC 73SECTOR 73 · Gurugram | Sept 2021 | Nov 2024 | None | Completed Jun 2024 · on time |
| SUMMIT PLAZADLF CITY PHASE V, SECTOR 54 · Gurugram | Sept 2021 | Jun 2026 | None | Completed Nov 2025 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE IVDLF CITY PHASE IV, GURUGRAM, HARYANA · Gurugram | Sept 2021 | Nov 2024 | None | Completed Dec 2023 · on time |
| INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDENCITY, SECTOR 91/92, GURUGRAM, HARYANA · Gurugram | Aug 2021 | Nov 2024 | None | Completed Mar 2024 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE IIDLF CITY PHASE II · Gurugram | Jul 2021 | Jun 2024 | None | Completed May 2024 · on time |
| DLF GARDENCITYDLF GARDENCITY, SECTOR 91/92 · Gurugram | Jun 2021 | Jun 2023 | None | Overdue |
| INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDENCITY, SECTOR 91 / 9 2, · Gurugram | Jun 2021 | Jun 2024 | None | Completed May 2023 · on time |
| INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDEN CITY, SECTOR 91 / 92, · Gurugram | Jun 2021 | Jun 2024 | None | Completed Jul 2023 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE IDLF CITY PHASE - I · Gurugram | Mar 2021 | Feb 2024 | None | Completed Jun 2023 · on time |
| INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDENCITY, SECTOR 91 / 9 2, · Gurugram | Mar 2021 | Jun 2025 | None | Completed May 2023 · on time |
| INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDEN CITY, SECTOR 91 / 92, · Gurugram | Mar 2021 | Jun 2024 | None | Completed May 2023 · on time |
| INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDENCITY, SECTOR 91 / 9 2, · Gurugram | Mar 2021 | Jun 2025 | None | Completed May 2023 · on time |
| INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDEN CITY, SECTOR 91 / 92, · Gurugram | Mar 2021 | Jun 2024 | None | Completed May 2023 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE IIIDLF CITY PHASE-III, SECTOR 24 , GURUGRAM, HARYANA · Gurugram | Feb 2021 | Mar 2025 | None | Completed Jun 2023 · on time |
| INDEPENDENT FLOORS AT DLF CITY PHASE IIIDLF CITY PHASE-III, SECTOR 24 , GURUGRAM, HARYANA · Gurugram | Dec 2020 | Dec 2024 | None | Completed Feb 2023 · on time |
| SIRIS ESTATEDLF CITY PHASE III SECTOR 24, GURUGRAM HARYANA · Gurugram | Oct 2020 | Oct 2024 | None | Completed Feb 2023 · on time |
| MOULSARI ENCLAVEDLF CITY PHASE-III, SECTOR 24 , GURUGRAM, HARYANA · Gurugram | Oct 2020 | Oct 2024 | None | Completed Feb 2023 · on time |
| ULTIMA PHASE-IIVILLAGE LAKHNOLA, SECTOR 81, GURUGRAM, HARYANA · Gurugram | Sept 2019 | Nov 2020 | None | Completed Jun 2018 · on time |
Companies these projects are registered under (16)
- DLF BUILDERS & DEVELOPERS PRIVATE LIMITED · Gurugram
- DLF HOME DEVELEOPERS LIMITED · Gurugram
- DLF HOME DEVELOPERS LIMITED · Gurugram
- DLF HOME DEVELOPERSLIMITED · Gurugram
- DLF HOMES PANCHKULA PRIVATE LIMITED · Gurugram
- DLF LIMITED · Gurugram
- DLF LUXURY HOMES LIMITED · Gurugram
- DLF PROJECTS LIMITED · Gurugram
- DLF PROPERTY DEVELOPERS LIMITED · Gurugram
- DLF REAL ESTATE BUILDERS LIMITED · Gurugram
- DLF RESIDENTIAL DEVELOPERS LIMITED · Gurugram
- DLF RESIDENTIAL PARTNERS LIMITED · Gurugram
- DLF UTILITIES LIMITED · Gurugram
- M/S DLF EXCLUSIVE FLOORS PRIVATE LIMITED · Gurugram
- M/S. DLF LIMITED · Gurugram
- DLF Southern Towns Private Limited · Tamil Nadu
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- HARERA Gurugram — Gurugram
- TNRERA — Tamil Nadu building projects
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does DLF Limited deliver on time?+
Per the regulators' own registers, in Gurugram, 30 of 32 completed projects with a recorded completion date finished by the date promised at RERA registration; in Tamil Nadu, 1 of 1 registered projects are marked completed, 1 of them without any extension. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many DLF Limited projects are registered with RERA?+
45 with HARERA Gurugram (Gurugram); 1 with TNRERA (Tamil Nadu building projects). 33 of them are completed and 13 are ongoing.
Which DLF Limited projects are running late?+
1 ongoing registration is past the latest date allowed on RERA without a completion on file, including DLF GARDENCITY. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.
How can I check a DLF project's RERA record myself?+
Search the project's registration number on HARERA Gurugram (haryanarera.gov.in) or TNRERA (rera.tn.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.
Compare DLF with the other developers we track, or see the DLF homes listed now.