Is DLF reliable?

Per the regulators' own registers, in Gurugram, 30 of 32 completed projects with a recorded completion date finished by the date promised at RERA registration; in Tamil Nadu, 1 of 1 registered projects are marked completed, 1 of them without any extension.

46 registrations · checked 6 October 2026

Gurugram · HARERA Gurugram

45

Registered projects

32 completed · 13 ongoing

94%

Finished by the date promised at registration

30 of 32 completed projects

0months

Median delay past the promised date

Across completed projects (on-time = 0)

1

Overdue now

Ongoing projects past their registration validity with no occupancy certificate on file

Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.

Tamil Nadu · TNRERA

1

Registered projects

1 completed · 0 ongoing

100%

Completed without any extension

1 of 1 completed projects

—

Needed an extension

0 of 0 projects whose promised date has passed

0

Overdue now

Ongoing projects past their latest RERA date and not marked completed

TNRERA marks projects as completed but publishes the completion date only inside PDF certificates, so we report completions and extensions rather than months of delay.

Every registration

DLF projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
THE AUREVASECTOR 63, GURUGRAM, HARYANA- 122102 · GurugramSept 2026Oct 2033NoneIn progress
PRIVANA ENCLAVESECTOR 76/77 · GurugramJul 2026Apr 2033NoneIn progress
PARC SOCIALTamil NaduSept 2025—NoneCompleted · no extension
CENTRAL 84SECTOR 84, GURUGRAM, HARYANA 122004 · GurugramJul 2025Jun 2030NoneIn progress
DLF PRIVANA NORTHSECTOR 76/77 · GurugramJun 2025Sept 2034NoneIn progress
THE DAHLIASR16, DLF 5, SECTOR 54 GURUGRA M · GurugramOct 2024Dec 2031NoneIn progress
DLF PRIVANA WESTSECTOR 76/77 · GurugramApr 2024Dec 2031NoneIn progress
CLUB ARCADESECTOR 91 · GurugramApr 2024Mar 2028NoneIn progress
CENTRAL 74SECTOR 74 A GURUGRAM · GurugramFeb 2024Sept 2028NoneIn progress
DLF PRIVANA SOUTHSECTOR 76/77 · GurugramDec 2023Jun 2031NoneIn progress
CENTRAL 67SECTOR 67 · GurugramDec 2023Dec 2027NoneCompleted Aug 2026 · on time
ARCADE 68SECTOR 68, GURGAON · GurugramFeb 2023Nov 2027NoneCompleted Aug 2026 · on time
THE SIXTY THREESECTOR 63, GURUGRAM, HARYANA- 122102 · GurugramJan 2023Mar 2030NoneIn progress
INDEPENDENT FLOORS AT DLF GARDENCITY ENCLAVE PHASE 2SECTOR 93 · GurugramJan 2023Oct 2028NoneIn progress
ALAMEDA CENTRALSECTOR 73, GURUGRAM · GurugramNov 2022Sept 2027NoneCompleted Dec 2025 · on time
INDEPENDENT FLOORS AT DLF GARDENCITY ENCLAVESECTOR 93 · GurugramAug 2022Aug 2027NoneIn progress
INDEPENDENT FLOORS AT DLF CITY PHASE I, II & IIIDLF CITY PHASE I, DLF CITY PH ASE II & DLF CITY PHASE III · GurugramMay 2022May 2025NoneCompleted Mar 2025 · on time
DLF GARDENCITY ENCLAVESECTOR 93 · GurugramApr 2022Mar 2024Oct 2028 (2)Completed Jun 2024 · 3 mo late
INDEPENDENT FLOORS AT DLF CITY PHASE I & IIIDLF CITY PHASE I & DLF CITY P HASE III, GURUGRAM · GurugramApr 2022May 2025NoneCompleted Dec 2024 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE IVDLF CITY PHASE IV, SECTOR-27, GURUGRAM, HARYANA · GurugramMar 2022May 2025NoneCompleted Dec 2023 · on time
Show all 46 registrations
GARDENCITY ARCADESECTOR 92, GURUGRAM · GurugramFeb 2022Apr 2025NoneCompleted Apr 2025 · on time
THE GROVEDLF 5, SECTOR 54 · GurugramFeb 2022Dec 2025NoneCompleted Jun 2024 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE I & IIIDLF CITY PHASE I AND DLF CITY PHASE III, GURUGRAM, HARYANA · GurugramJan 2022Feb 2025NoneCompleted Dec 2024 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE IIIDLF CITY PHASE III, GURUGRAM, HARYANA · GurugramDec 2021Feb 2025NoneCompleted Mar 2024 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE I, II & IIIDLF CITY PHASE I, II & III, G URUGRAM, HARYANA · GurugramDec 2021Feb 2025NoneCompleted Aug 2024 · on time
INDEPENDENT FLOORS AT DLF GARDENCITYDLF GARDENCITY, SECTOR 91/92 · GurugramDec 2021Mar 2025NoneCompleted Jun 2024 · on time
GARDENCITY CENTRALSECTOR 84, GURUGRAM, HARYANA · GurugramNov 2021Aug 2024Aug 2025 (1)Completed Feb 2025 · 5 mo late
INDEPENDENT FLOORS AT DLF CITY PHASE I & IIDLF CITY PHASE I AND DLF CITY PHASE II, GURUGRAM · GurugramNov 2021Dec 2024NoneCompleted Oct 2024 · on time
INDEPENDENT FLOORS AT DLF ALAMEDA, SEC 73SECTOR 73 · GurugramSept 2021Nov 2024NoneCompleted Jun 2024 · on time
SUMMIT PLAZADLF CITY PHASE V, SECTOR 54 · GurugramSept 2021Jun 2026NoneCompleted Nov 2025 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE IVDLF CITY PHASE IV, GURUGRAM, HARYANA · GurugramSept 2021Nov 2024NoneCompleted Dec 2023 · on time
INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDENCITY, SECTOR 91/92, GURUGRAM, HARYANA · GurugramAug 2021Nov 2024NoneCompleted Mar 2024 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE IIDLF CITY PHASE II · GurugramJul 2021Jun 2024NoneCompleted May 2024 · on time
DLF GARDENCITYDLF GARDENCITY, SECTOR 91/92 · GurugramJun 2021Jun 2023NoneOverdue
INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDENCITY, SECTOR 91 / 9 2, · GurugramJun 2021Jun 2024NoneCompleted May 2023 · on time
INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDEN CITY, SECTOR 91 / 92, · GurugramJun 2021Jun 2024NoneCompleted Jul 2023 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE IDLF CITY PHASE - I · GurugramMar 2021Feb 2024NoneCompleted Jun 2023 · on time
INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDENCITY, SECTOR 91 / 9 2, · GurugramMar 2021Jun 2025NoneCompleted May 2023 · on time
INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDEN CITY, SECTOR 91 / 92, · GurugramMar 2021Jun 2024NoneCompleted May 2023 · on time
INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDENCITY, SECTOR 91 / 9 2, · GurugramMar 2021Jun 2025NoneCompleted May 2023 · on time
INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92DLF GARDEN CITY, SECTOR 91 / 92, · GurugramMar 2021Jun 2024NoneCompleted May 2023 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE IIIDLF CITY PHASE-III, SECTOR 24 , GURUGRAM, HARYANA · GurugramFeb 2021Mar 2025NoneCompleted Jun 2023 · on time
INDEPENDENT FLOORS AT DLF CITY PHASE IIIDLF CITY PHASE-III, SECTOR 24 , GURUGRAM, HARYANA · GurugramDec 2020Dec 2024NoneCompleted Feb 2023 · on time
SIRIS ESTATEDLF CITY PHASE III SECTOR 24, GURUGRAM HARYANA · GurugramOct 2020Oct 2024NoneCompleted Feb 2023 · on time
MOULSARI ENCLAVEDLF CITY PHASE-III, SECTOR 24 , GURUGRAM, HARYANA · GurugramOct 2020Oct 2024NoneCompleted Feb 2023 · on time
ULTIMA PHASE-IIVILLAGE LAKHNOLA, SECTOR 81, GURUGRAM, HARYANA · GurugramSept 2019Nov 2020NoneCompleted Jun 2018 · on time
Companies these projects are registered under (16)
  • DLF BUILDERS & DEVELOPERS PRIVATE LIMITED · Gurugram
  • DLF HOME DEVELEOPERS LIMITED · Gurugram
  • DLF HOME DEVELOPERS LIMITED · Gurugram
  • DLF HOME DEVELOPERSLIMITED · Gurugram
  • DLF HOMES PANCHKULA PRIVATE LIMITED · Gurugram
  • DLF LIMITED · Gurugram
  • DLF LUXURY HOMES LIMITED · Gurugram
  • DLF PROJECTS LIMITED · Gurugram
  • DLF PROPERTY DEVELOPERS LIMITED · Gurugram
  • DLF REAL ESTATE BUILDERS LIMITED · Gurugram
  • DLF RESIDENTIAL DEVELOPERS LIMITED · Gurugram
  • DLF RESIDENTIAL PARTNERS LIMITED · Gurugram
  • DLF UTILITIES LIMITED · Gurugram
  • M/S DLF EXCLUSIVE FLOORS PRIVATE LIMITED · Gurugram
  • M/S. DLF LIMITED · Gurugram
  • DLF Southern Towns Private Limited · Tamil Nadu

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • HARERA Gurugram — Gurugram
  • TNRERA — Tamil Nadu building projects
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does DLF Limited deliver on time?+

Per the regulators' own registers, in Gurugram, 30 of 32 completed projects with a recorded completion date finished by the date promised at RERA registration; in Tamil Nadu, 1 of 1 registered projects are marked completed, 1 of them without any extension. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many DLF Limited projects are registered with RERA?+

45 with HARERA Gurugram (Gurugram); 1 with TNRERA (Tamil Nadu building projects). 33 of them are completed and 13 are ongoing.

Which DLF Limited projects are running late?+

1 ongoing registration is past the latest date allowed on RERA without a completion on file, including DLF GARDENCITY. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.

How can I check a DLF project's RERA record myself?+

Search the project's registration number on HARERA Gurugram (haryanarera.gov.in) or TNRERA (rera.tn.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare DLF with the other developers we track, or see the DLF homes listed now.