Property Point

Delivery record · from RERA

Is Sobha reliable?

Per the regulators' own registers, in Bengaluru, 34 of 64 completed projects with a recorded completion date finished by the date promised at RERA registration; in Gurugram, 1 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 5.7 months after that date; in Tamil Nadu, 6 of 8 registered projects are marked completed, 5 of them without any extension.

137 registrations · checked 6 October 2026

Bengaluru · Karnataka RERA

119

Registered projects

64 completed · 47 ongoing

53%

Finished by the date promised at registration

34 of 64 completed projects

0months

Median delay past the promised date

Across completed projects (on-time = 0)

5

Overdue now

Ongoing projects past their latest RERA date with no completion filed

Completion = the date of the first occupancy (or completion) certificate recorded on the project's K-RERA page; where none is recorded, the date the builder applied for completion on K-RERA.

Gurugram · HARERA Gurugram

10

Registered projects

4 completed · 5 ongoing

25%

Finished by the date promised at registration

1 of 4 completed projects

5.7months

Median delay past the promised date

Across completed projects (on-time = 0)

0

Overdue now

Ongoing projects past their registration validity with no occupancy certificate on file

Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.

Tamil Nadu · TNRERA

8

Registered projects

6 completed · 2 ongoing

83%

Completed without any extension

5 of 6 completed projects

29%

Needed an extension

2 of 7 projects whose promised date has passed

2

Overdue now

Ongoing projects past their latest RERA date and not marked completed

TNRERA marks projects as completed but publishes the completion date only inside PDF certificates, so we report completions and extensions rather than months of delay.

Every registration

Sobha projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
ONE RESIDENCES AT SOBHA ONE WORLD Ph1 W1 and 2Hosakote · BengaluruMay 2026Jul 2032NoneIn progress
ONE RESIDENCES AT SOBHA ONE WORLD Ph3 W5 and 6Hosakote · BengaluruMay 2026Sept 2033NoneIn progress
ONE RESIDENCES AT SOBHA ONE WORLD Ph4 W7 and 8Hosakote · BengaluruMay 2026Sept 2033NoneIn progress
ONE RESIDENCES AT SOBHA ONE WORLD Ph2 W3 and 4Hosakote · BengaluruMay 2026Nov 2032NoneIn progress
ONE RESIDENCES AT SOBHA ONE WORLD Ph5 W9,10,11Hosakote · BengaluruMay 2026Feb 2033NoneIn progress
ONE RESIDENCES AT SOBHA ONE WORLD Ph6 W12,13,14Hosakote · BengaluruMay 2026Aug 2032NoneIn progress
SOBHA CRESCENT PHASE - 1SECTOR 63A, VILLAGE BEHRAMPUR , GURUGRAM MANESAR URBAN COMPLEX · GurugramApr 2026Mar 2033NoneIn progress
SOBHA ALTAIRBengaluru East · BengaluruJan 2026May 2031NoneIn progress
SOBHA MAGNUSBengaluru South · BengaluruOct 2025May 2030NoneIn progress
Sobha Hamptons -Townpark Phase 2 W1 to 3Anekal · BengaluruJan 2025Jun 2033NoneIn progress
Sobha Hamptons -Townpark Phase 1 W4 to 6Anekal · BengaluruJan 2025Jun 2031NoneIn progress
Sobha Madison Heights-Townpark Phase 1 W5 to 7Anekal · BengaluruJan 2025Dec 2030NoneIn progress
Sobha Madison Heights-Townpark Phase 2 W1 to 4Anekal · BengaluruJan 2025Dec 2032NoneIn progress
SOBHA VERDURETamil NaduDec 2024—NoneCompleted · no extension
Sobha Infinia Phase 2A Block 5 Wing 5Bengaluru East · BengaluruAug 2024Jun 2030NoneIn progress
Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2Bengaluru East · BengaluruAug 2024Dec 2030NoneIn progress
SOBHA Ayana at Dream Acres Wing 60 to 71Bengaluru East · BengaluruAug 2024Dec 2031NoneIn progress
SOBHA ALTUSREVENUE ESTATE OF VILLAGE PAW ALA KHUSRUPUR, SECTOR-106, GURUGRAM · GurugramMay 2024Dec 2031NoneIn progress
SOBHA ARANYA PHASE-1SECTOR-80, REVENUE ESTATE OF VILLAGE NAURANGPUR, GURUGRAM · GurugramApr 2024Oct 2030NoneIn progress
SOBHA Crystal Meadows Phase 1 Wing 1 to 6Bengaluru East · BengaluruMar 2024Dec 2029NoneWITHDRAWN As per the Hon'ble Authority Order dated 29/06/2026 application for project Withdrawal is Approved.
Show all 137 registrations
SOBHA Crystal Meadows Phase 2 Wing 7 and 8Bengaluru East · BengaluruMar 2024Jun 2031NoneWITHDRAWN As per the Hon'ble Authority Order dated 29/06/2026 application for project Withdrawal is Approved.
SOBHA Crystal Meadows Phase 3 Wing 9 to 15Bengaluru East · BengaluruMar 2024Dec 2032NoneWITHDRAWN As per the Hon'ble Authority Order dated 29/06/2026 application for project Withdrawal is Approved.
SOBHA Crystal Meadows Phase 4 Wing 23 to 28Bengaluru East · BengaluruMar 2024Dec 2033NoneWITHDRAWN As per the Hon'ble Authority Order dated 29/06/2026 application for project Withdrawal is Approved.
SOBHA Crystal Meadows Phase 5 Wing 16 to 22Bengaluru East · BengaluruMar 2024Dec 2035NoneWITHDRAWN As per the Hon'ble Authority Order dated 29/06/2026 application for project Withdrawal is Approved.
Sobha Neopolis Phase 3 - W 1, 2, 10 & 11Bengaluru East · BengaluruSept 2023Dec 2029NoneIn progress
Sobha Neopolis Phase 4 - 3, 4, 8 & 9Bengaluru East · BengaluruSept 2023Dec 2031NoneIn progress
Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19Bengaluru East · BengaluruSept 2023Dec 2028NoneIn progress
Sobha Neopolis Phase 2 - W 12 & 13Bengaluru East · BengaluruSept 2023Dec 2030NoneIn progress
Sobha Neopolis Phase 5 - W 5, 6 & 7Bengaluru East · BengaluruSept 2023Dec 2031NoneIn progress
Sobha Gardenia AnnexeTamil NaduSept 2023Dec 2024NoneCompleted · no extension
Sobha Westhill Phase-I, II & IIITamil NaduJun 2023Nov 2025NoneCompleted · no extension
Sobha Oakshire Phase 1 Wing 1,2,7 and 8Devanahalli · BengaluruMar 2023Dec 2026NoneIn progress
Sobha Oakshire Phase 2 Wing 3,4,9 and 10Devanahalli · BengaluruMar 2023Jun 2027NoneIn progress
Sobha Oakshire Phase 3 Wing 5,6,11 and 12Devanahalli · BengaluruMar 2023Dec 2027NoneIn progress
Sobha GaleraBengaluru East · BengaluruJan 2023Dec 2026NoneIn progress
Sobha Dream Gardens Phase 5 - Wing 10Bengaluru North · BengaluruDec 2022Dec 2028NoneIn progress
Sobha Dream Gardens Phase 4 - Wing 1 and 2Bengaluru North · BengaluruDec 2022Dec 2028NoneIn progress
Sobha Dream Gardens Phase 3 - Wing 3 and 4Bengaluru North · BengaluruDec 2022Dec 2027NoneIn progress
SOBHA CITY, PHASE-6REVENUE ESTATE OF BABUPUR VIL LAGE, VILLAGE BABUPUR, SECTOR-108, GURUGRAM, HARYANA · GurugramOct 2022Dec 2028NoneIn progress
Sobha Brooklyn Towers - Town Park Phase 1, W1Anekal · BengaluruSept 2022Dec 2027NoneIn progress
Sobha Brooklyn Towers - Town Park Phase 3, W5Anekal · BengaluruSept 2022Jun 2029NoneIn progress
Sobha Brooklyn Towers - Town Park Phase 4, W4Anekal · BengaluruSept 2022Jun 2029NoneIn progress
Sobha InsigniaBengaluru East · BengaluruSept 2022Mar 2026NoneCompleted Jan 2026 · on time
Sobha Royal CrestBengaluru South · BengaluruMay 2022Dec 2028NoneIn progress
Sobha Sentosa Phase 1 Wing 7Bengaluru East · BengaluruMar 2022Jun 2026NoneCompleted Dec 2024 · on time
Sobha Sentosa Phase 2 Wing 5 and 6Bengaluru East · BengaluruMar 2022Dec 2026NoneCompleted Mar 2025 · on time
Sobha Sentosa Phase 3 Wing 3 and 4Bengaluru East · BengaluruMar 2022Jun 2027NoneIn progress
Sobha Sentosa Phase 4 Wing 1 and 2Bengaluru East · BengaluruMar 2022Dec 2027NoneIn progress
Sobha Victoria park phase 1Bengaluru North · BengaluruMar 2022Dec 2027NoneIn progress
Sobha Victoria Park Phase 2Bengaluru North · BengaluruMar 2022Dec 2027NoneIn progress
Sobha Brooklyn Towers - Town Park Phase 2, W2Anekal · BengaluruJan 2022Dec 2027NoneIn progress
Sobha Brooklyn Towers - Town Park Phase 5, W3Anekal · BengaluruJan 2022Jun 2028NoneIn progress
Sobha ArborTamil NaduSept 2021Jun 2026NoneCompleted · no extension
Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5Anekal · BengaluruMay 2021Dec 2026NoneIn progress
Sobha Manhattan Towers-Town Park Phase 2 W 1 & 2Anekal · BengaluruMay 2021Sept 2028NoneIn progress
Sobha Windsor Phase 2 Wing 3, 4 and 5Bengaluru East · BengaluruFeb 2021Apr 2026NoneCompleted Nov 2025 · on time
Sobha Windsor Phase 3 Wing 6, 7 and 8Bengaluru East · BengaluruFeb 2021Sept 2027NoneIn progress
Sobha Windsor Phase 4 Wing 9, 10 and 11Bengaluru East · BengaluruFeb 2021Mar 2028NoneIn progress
Sobha Windsor Phase 1 Wing 1 and 2Bengaluru East · BengaluruFeb 2021Nov 2025NoneCompleted Jan 2025 · on time
SOBHA CITY, PHASE-5REVENUE ESTATE OF BABUPUR VIL LAGE, VILLAGE BABUPUR, SECTOR-108, GURUGRAM, HARYANA · GurugramSept 2020Dec 2026NoneIn progress
Sobha Gardenia AnnexeTamil NaduJul 2020Mar 2023NoneCompleted · no extension
Sobha City AthenaBengaluru North · BengaluruMay 2020Dec 2026Sept 2027 (1)In progress
Sobha Dream Acres - Oasis Phase 27 Wing 55, 56, 57 and 58Bengaluru East · BengaluruJan 2020Dec 2025Sept 2026 (1)Completed Oct 2026 · 9 mo late
Sobha Dream Acres - Palm Springs Phase 16 Wing 50Bengaluru East · BengaluruSept 2019Jun 2022Mar 2023 (1)Completed Mar 2023 · 9 mo late
SOBHA CITY PHASE IVSECTOR-108, GURUGRAM · GurugramMay 2019Dec 2024NoneCompleted Jan 2024 · on time
Sobha VerdureTamil NaduApr 2019Jul 2020Jan 2024 (3)Overdue
Sobha PalaciaTamil NaduMar 2019Dec 2023NoneOverdue
SOBHA CITY PHASE IIISECTOR-108, GURUGRAM · GurugramFeb 2019Oct 2023NoneCompleted May 2024 · 7 mo late
Sobha Dream Acres - Tropical Greens Phase 26 Wing 35, 36, 37 and 38Bengaluru East · BengaluruFeb 2019Dec 2023Sept 2024 (1)Completed Mar 2023 · on time
Sobha Dream Acres - Tropical Greens Phase 25 Wing 32, 33 and 34Bengaluru East · BengaluruFeb 2019Jun 2024Mar 2025 (1)Completed Apr 2025 · 10 mo late
Sobha Royal Pavilion Phase 7 - Wing 12, 13 and 14Bengaluru East · BengaluruFeb 2019Sept 2025Jun 2026 (1)Completed Feb 2026 · 4 mo late
Sobha Royal Pavilion Phase 3 - Wing 16Bengaluru East · BengaluruFeb 2019Sept 2023Jun 2024 (1)Overdue
Sobha Royal Pavilion Phase 4 - Wing 1, 2 and 3Bengaluru East · BengaluruFeb 2019Sept 2023Jun 2024 (1)Overdue
Sobha Royal Pavilion Phase 6 - Wing 10 and 11Bengaluru East · BengaluruFeb 2019Sept 2025Jun 2026 (1)Completed Mar 2025 · on time
Sobha Royal Pavilion Phase 1 - Wing 6 and 7Bengaluru East · BengaluruFeb 2019Sept 2023Jun 2024 (1)Completed Mar 2024 · 5 mo late
Sobha Royal Pavilion Phase 8 - Wing 15Bengaluru East · BengaluruFeb 2019Sept 2025Jun 2026 (1)Completed Mar 2025 · on time
Sobha Royal Pavilion Phase 2 - Wing 4 and 5Bengaluru East · BengaluruFeb 2019Sept 2023Jun 2024 (1)Completed Mar 2024 · 5 mo late
Sobha Royal Pavilion Phase 5 - Wing 8 and 9Bengaluru East · BengaluruFeb 2019Sept 2025Jun 2026 (1)Completed Nov 2024 · on time
Sobha Dream Gardens Phase 2 – Wing 5, 6 and 7Bengaluru North · BengaluruJan 2019Feb 2024Nov 2024 (1)Completed Mar 2024 · <1 mo late
Sobha Dream Gardens Phase 3 – Wing 3 and 4Bengaluru North · BengaluruJan 2019Feb 2025Nov 2025 (1)WITHDRAWN As per Hon'ble Authority order dated 23/03/2022, application for withdrawal is approved
Sobha Dream Gardens Phase 1 – Wing 8 and 9Bengaluru North · BengaluruNov 2018Feb 2024Nov 2024 (1)Completed Oct 2024 · 8 mo late
Sobha Dream Gardens Phase 4 – Wing 1 and 2Bengaluru North · BengaluruNov 2018Feb 2025Nov 2025 (1)WITHDRAWN As per Hon'ble Authority order dated 23/03/2022, application for withdrawal is approved
Sobha Dream Gardens Phase 5 – Wing 10Bengaluru North · BengaluruNov 2018Feb 2025Nov 2025 (1)WITHDRAWN As per Hon'ble Authority order dated 23/03/2022, application for withdrawal is approved
Sobha RajvilasBengaluru North · BengaluruNov 2018Jun 2024Mar 2025 (1)Completed Jul 2024 · <1 mo late
Sobha Dream Acres - Tropical Greens Phase 21 Wing 21 and 22Bengaluru East · BengaluruOct 2018Jun 2025Mar 2026 (1)Completed Feb 2026 · 8 mo late
Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24Bengaluru East · BengaluruOct 2018Jun 2025Mar 2026 (1)Completed Feb 2026 · 7 mo late
Sobha Dream Acres - Tropical Greens Phase 23 Wing 25, 26, 27 and 28Bengaluru East · BengaluruOct 2018Dec 2023Sept 2024 (1)Completed Mar 2024 · 2 mo late
Sobha Dream Acres - Tropical Greens Phase 24 Wing 29 and 30Bengaluru East · BengaluruOct 2018Jun 2024Mar 2025 (1)Completed Mar 2024 · on time
SOBHA CITY (PHASE-2, PART-1)SECTOR-108, GURUGRAM · GurugramJul 2018Oct 2022NoneRegistration lapsed
Sobha Dream Acres - Tropical Greens Phase 20 Wing 18Bengaluru East · BengaluruJun 2018Mar 2023Dec 2023 (1)Completed Dec 2020 · on time
Sobha Lake Gardens Phase 1Bengaluru East · BengaluruJun 2018May 2023Feb 2024 (1)Completed Aug 2023 · 3 mo late
Sobha Lake Gardens Phase 2Bengaluru East · BengaluruJun 2018Mar 2024Dec 2025 (2)Completed Nov 2025 · 20 mo late
Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20Bengaluru East · BengaluruJun 2018Dec 2022Sept 2023 (1)Completed Dec 2020 · on time
Sobha Arena - Pebble Court (Block 1)Bengaluru South · BengaluruMay 2018Apr 2022Jan 2023 (1)Completed Jan 2023 · 9 mo late
Sobha Arena - The Square (Block 4)Bengaluru South · BengaluruApr 2018Dec 2021Sept 2022 (1)Completed Apr 2021 · on time
Sobha Forest EdgeBengaluru South · BengaluruFeb 2018Sept 2022Jun 2023 (1)Completed Sept 2023 · 11 mo late
Construction of Ground Floor+ First Floor VillasTamil NaduJan 2018Feb 2022Aug 2023 (1)Completed · 1 extension
Sobha HRC Pristine Phase 1 Block 1Bengaluru North · BengaluruNov 2017Jul 2022Apr 2023 (1)Completed May 2023 · 11 mo late
Sobha HRC Pristine Phase 4 Block 4 and 5Bengaluru North · BengaluruNov 2017Jul 2022Apr 2023 (1)Completed May 2023 · 11 mo late
Sobha - HRC Pristine Phase 3 Block 3Bengaluru North · BengaluruNov 2017Jul 2022Apr 2023 (1)Completed May 2023 · 11 mo late
Sobha HRC Pristine Phase 2 Block 2Bengaluru North · BengaluruNov 2017Jul 2022Apr 2023 (1)Completed May 2023 · 11 mo late
Sobha Dream Acres - Palm Springs Phase 17 Wing 54Bengaluru East · BengaluruOct 2017Apr 2022Jan 2023 (1)Completed Dec 2020 · on time
Sobha Dream Acres - Tropical Greens Phase 18 Wing 39 and 40Bengaluru East · BengaluruOct 2017Oct 2022Jul 2023 (1)Completed Dec 2020 · on time
Sobha City - Casa Paradiso Block 4Bengaluru North · BengaluruOct 2017Dec 2018NoneCompleted Dec 2016 · on time
Sobha ClovellyBengaluru South · BengaluruOct 2017Apr 2020Oct 2020 (1)Completed Dec 2019 · on time
Sobha Arena - The Plaza (Block 3)Bengaluru South · BengaluruSept 2017Oct 2019NoneCompleted Oct 2019 · 1 mo late
Sobha Morzaria Grandeur 2 (W1)Bengaluru South · BengaluruSept 2017May 2021Feb 2022 (1)Completed May 2022 · 12 mo late
Sobha Arena - The Park ( Block 2 )Bengaluru South · BengaluruSept 2017May 2018NoneCompleted May 2018 · <1 mo late
Sobha AvenueBengaluru East · BengaluruSept 2017Jul 2019NoneCompleted Jun 2019 · on time
Sobha Dream Acres - Rain forest Phase 15 Wing 17Bengaluru East · BengaluruSept 2017Nov 2019NoneCompleted Jul 2019 · on time
Sobha 25 RichmondBengaluru East · BengaluruSept 2017Jul 2019NoneOverdue
Sobha Valley View - HeritageBengaluru South · BengaluruSept 2017Feb 2019NoneOverdue
Sobha Palm CourtBengaluru North · BengaluruSept 2017May 2021Feb 2022 (1)Completed Mar 2022 · 11 mo late
Sobha IndraprasthaBengaluru North · BengaluruSept 2017Dec 2018NoneCompleted Jun 2019 · 7 mo late
Sobha Dream Acres - Palm Springs Phase 12 Wing 48 and 49Bengaluru East · BengaluruSept 2017Oct 2021Jul 2022 (1)Completed Dec 2020 · on time
Sobha Dream Acres - Rain Forest Phase 3 Wing 5 and 6Bengaluru East · BengaluruSept 2017Jan 2021NoneCompleted Jul 2019 · on time
Sobha Silicon Oasis Phase 7 Block 2 and 3 (Row House No. 9, 10)Bengaluru South · BengaluruSept 2017Apr 2019NoneCompleted Jul 2019 · 4 mo late
Sobha Dream Acres - Rain forest Phase 1 Wing 1 and 2Bengaluru East · BengaluruSept 2017Nov 2019NoneCompleted Dec 2019 · 1 mo late
Sobha Dream Acres - Tropical Greens Phase 8 Wing 43 and 44Bengaluru East · BengaluruSept 2017Jan 2021Jul 2021 (1)Completed Jan 2020 · on time
Sobha Dream Acres - Rain Forest Phase 2 Wing 3 and 4Bengaluru East · BengaluruSept 2017Oct 2020NoneCompleted Jul 2019 · on time
Sobha Dream Acres - Palm Springs Phase 11 Wing 47Bengaluru East · BengaluruSept 2017Mar 2021Dec 2021 (1)Completed Jan 2020 · on time
Sobha Dream Acres - Rain Forest Phase 5 Wing 16Bengaluru East · BengaluruSept 2017Sept 2019NoneCompleted Jul 2019 · on time
Sobha Dream Acres - Tropical Greens Phase 6 Wing 41Bengaluru East · BengaluruSept 2017May 2020Nov 2020 (1)Completed Jan 2020 · on time
Sobha Dream Acres - Tropical Greens Phase 10 Wing 46Bengaluru East · BengaluruSept 2017Jul 2021Jan 2022 (1)Completed Jan 2020 · on time
Sobha Dream Acres - Palm Springs Phase 13 Wing 52Bengaluru South · BengaluruSept 2017Jul 2021Apr 2022 (1)Completed Dec 2020 · on time
Sobha Dream Acres - Rain Forest Phase 4 Wing 11Bengaluru East · BengaluruSept 2017Jul 2020NoneCompleted Jul 2019 · on time
Sobha Dream Acres - Tropical Greens Phase 7 Wing 42Bengaluru East · BengaluruSept 2017Jul 2020Jan 2021 (1)Completed Jan 2020 · on time
Sobha Dream Acres - Tropical Greens Phase 9 Wing 45Bengaluru East · BengaluruSept 2017Jan 2021Jul 2021 (1)Completed Jan 2020 · on time
Sobha Dream Acres - Palm Springs Phase 14 Wing 53Bengaluru East · BengaluruSept 2017Oct 2021Jul 2022 (1)Completed Dec 2020 · on time
Sobha Silicon Oasis Phase 2 Wing 7Bengaluru South · BengaluruSept 2017Jan 2020NoneOverdue
Sobha Silicon Oasis Phase 5 Wing 10 & 11Bengaluru South · BengaluruSept 2017Jan 2021Oct 2021 (1)Completed Aug 2020 · on time
Sobha Silicon Oasis Phase 6 Block 2 and 3 (Row house No. 1 to 8 & 11 to 17)Bengaluru South · BengaluruSept 2017Apr 2019NoneCompleted Aug 2020 · 17 mo late
Sobha Silicon Oasis Phase 4 Wing 9Bengaluru South · BengaluruSept 2017Jan 2021Oct 2021 (1)Completed Aug 2020 · on time
SOBHA CITY- PHASE 1,PART 2VILLAGE BABUPUR,SECTOR-108, G URUGRAM · GurugramAug 2017May 2022NoneCompleted Nov 2022 · 6 mo late
Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6Bengaluru South · BengaluruAug 2017Apr 2019NoneCompleted Jul 2019 · 4 mo late
Sobha Silicon Oasis Phase 3 Wing 8Bengaluru South · BengaluruAug 2017Jul 2020Apr 2021 (1)Completed Aug 2020 · 2 mo late
SOBHA CITY PHASE 1, PART 1SECTOR 108, BABUPUR, GURUGRAM · GurugramAug 2017Oct 2021NoneCompleted Apr 2022 · 5 mo late
Companies these projects are registered under (10)
  • SOBHA LIMITED · Gurugram
  • SOBHA LTD · Gurugram
  • SOBHA LTD. · Gurugram
  • SOBHA LIMITED · Bengaluru
  • Sobha Limited · Bengaluru
  • 1) M/s. Sobha Limited · Tamil Nadu
  • SOBHA LIMITED · Tamil Nadu
  • SOBHA Ltd & M/s. Tarapur Constructions Pvt. Ltd. · Tamil Nadu
  • Sobha Limited · Tamil Nadu
  • Sobha Ltd. · Tamil Nadu

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • Karnataka RERA — Bengaluru Urban and Bengaluru Rural districts
  • HARERA Gurugram — Gurugram
  • TNRERA — Tamil Nadu building projects
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Sobha Limited deliver on time?+

Per the regulators' own registers, in Bengaluru, 34 of 64 completed projects with a recorded completion date finished by the date promised at RERA registration; in Gurugram, 1 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 5.7 months after that date; in Tamil Nadu, 6 of 8 registered projects are marked completed, 5 of them without any extension. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Sobha Limited projects are registered with RERA?+

119 with Karnataka RERA (Bengaluru Urban and Bengaluru Rural districts); 10 with HARERA Gurugram (Gurugram); 8 with TNRERA (Tamil Nadu building projects). 74 of them are completed and 54 are ongoing.

Which Sobha Limited projects are running late?+

7 ongoing registrations are past the latest date allowed on RERA without a completion on file, including Sobha Verdure, Sobha Palacia, Sobha Royal Pavilion Phase 3 - Wing 16, Sobha Royal Pavilion Phase 4 - Wing 1, 2 and 3, Sobha 25 Richmond. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.

How can I check a Sobha project's RERA record myself?+

Search the project's registration number on Karnataka RERA (rera.karnataka.gov.in) or HARERA Gurugram (haryanarera.gov.in) or TNRERA (rera.tn.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare Sobha with the other developers we track, or see the Sobha homes listed now.