Per the regulators' own registers, in Gurugram, 2 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 2.8 months after that date.

16 registrations · checked 6 October 2026

Gurugram · HARERA Gurugram

16

Registered projects

4 completed · 11 ongoing

50%

Finished by the date promised at registration

2 of 4 completed projects

2.8months

Median delay past the promised date

Across completed projects (on-time = 0)

0

Overdue now

Ongoing projects past their registration validity with no occupancy certificate on file

Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.

Every registration

Central Park projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
CENTRAL PARK FLOWER VALLEY PHASE IVRESIDENTIAL PLOTTED COLONY VI LLAGE DHUNELA, SECTOR-32, SOHNA, GURUGRAM · GurugramDec 2025Jun 2029NoneIn progress
THE SKYLO TOWERVILLAGE DHUNELA, SECTOR-32, S OHNA, GURUGRAM · GurugramDec 2025Dec 2032NoneIn progress
DELPHINE CENTRAL PARK ESTATES PHASE ISECTOR-104, GURUGRAM · GurugramOct 2025Aug 2032NoneIn progress
DELPHINE CENTRAL PARK ESTATES PHASE IISECTOR-104, GURUGRAM · GurugramOct 2025Aug 2032NoneIn progress
DELPHINE CENTRAL PARK ESTATES PHASE IIISECTOR-104, GURUGRAM · GurugramOct 2025Nov 2032NoneIn progress
DESTINO CENTRAL PARKVILLAGE DHUNELA, SECTOR-33, S OHNA, GURUGRAM · GurugramJul 2025Jun 2029NoneIn progress
THE SELENE TOWERTHE MEDIAN, CENTRAL PARK RESO RTS, OFF SOHNA ROAD, SECTOR-48, GURUGRAM, HARYANA-122018 · GurugramJul 2025Jun 2030NoneIn progress
CENTRAL PARK BIGNONIA TOWERSVILLAGE DHUNELA, SECTOR-32 SO HNA- GURUGRAM, HARYANA · GurugramMay 2024Jun 2028NoneIn progress
COMMERCIAL PLOTTED COLONY - MAG MILEVILLAGE DHUNELA, SECTOR-32, T EHSIL SOHNA · GurugramNov 2023Mar 2028NoneIn progress
CENTRAL PARK THE ORCHARDSITUATED IN SECTOR-32, TEHSIL -SOHNA, GURUGRAM · GurugramJan 2023Jun 2026NoneCompleted Apr 2025 · on time
CENTRAL PARK FLOWER VALLEY FLOORS AND VILLASVILLAGE DHUNELA & BERKA, SECT OR-29,30,32 AND 33, SOHNA · GurugramOct 2022Dec 2024NoneRegistration lapsed
CENTRAL PARK FLOWER VALLEY - PHASE IIISECTOR 29,30, 32 & 33, SOHNA, DIST. GURUGRAM · GurugramMay 2022Dec 2026NoneIn progress
CENTRAL PARK FLOWER VALLEYSECTOR 29, 30, 32 & 33 OF VIL LAGE DHUNELA & BERKA, TEHSIL SOHNA, DISTRICT GURUGRAM · GurugramMar 2020Dec 2024NoneCompleted Nov 2022 · on time
BELLA VISTA - CENTRAL PARK RESORTSSECTOR 48, SOHNA ROAD, NEAR S UBHASH CHOWK, GURGAON · GurugramDec 2019Aug 2024Feb 2026 (1)Completed May 2025 · 8 mo late
GROUP HOUSING COLONY OF 10.925 ACRESSECTOR-32, SOHNA GURUGRAM · GurugramAug 2017Jul 2022Jan 2026 (1)Completed Jan 2023 · 6 mo late
RESIDENTIAL PLOTTED COLONYSECTOR 29, 30, 32 AND 33 OF S OHNA, GURUGRAM · GurugramAug 2017Jul 2022Jan 2027 (1)In progress
Companies these projects are registered under (8)
  • CENTRAL PARK FLOWER VALLEY · Gurugram
  • ST PATRICKS REALTY PRIVATE LIMITED · Gurugram
  • ST PATRICKS REALTY PVT LTD · Gurugram
  • ST. NICHOLAS ESTATE DEVELOPMENT PVT LTD · Gurugram
  • ST. PATRICKS REALTY PVT LTD · Gurugram
  • ST. PATRICKS REALTY PVT. LTD. · Gurugram
  • ST. PATRICKS REALTY PVT.LTD. · Gurugram
  • SWETA ESTATES PVT. LTD. · Gurugram

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • HARERA Gurugram — Gurugram
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Central Park deliver on time?+

Per the regulators' own registers, in Gurugram, 2 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 2.8 months after that date. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Central Park projects are registered with RERA?+

16 with HARERA Gurugram (Gurugram). 4 of them are completed and 11 are ongoing.

Which Central Park projects are running late?+

None of Central Park's ongoing registrations is past its latest RERA date as of 2026-10-06.

How can I check a Central Park project's RERA record myself?+

Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.