Delivery record · from RERA
Is Central Park reliable?
Per the regulators' own registers, in Gurugram, 2 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 2.8 months after that date.
16 registrations · checked 6 October 2026
Gurugram · HARERA Gurugram
16
Registered projects
4 completed · 11 ongoing
50%
Finished by the date promised at registration
2 of 4 completed projects
2.8months
Median delay past the promised date
Across completed projects (on-time = 0)
0
Overdue now
Ongoing projects past their registration validity with no occupancy certificate on file
Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.
Every registration
Central Park projects on RERA
Underlined names are listed on Property Point. Newest registrations first.
| Project | Registered | Promised | Extended to | Outcome |
|---|---|---|---|---|
| CENTRAL PARK FLOWER VALLEY PHASE IVRESIDENTIAL PLOTTED COLONY VI LLAGE DHUNELA, SECTOR-32, SOHNA, GURUGRAM · Gurugram | Dec 2025 | Jun 2029 | None | In progress |
| THE SKYLO TOWERVILLAGE DHUNELA, SECTOR-32, S OHNA, GURUGRAM · Gurugram | Dec 2025 | Dec 2032 | None | In progress |
| DELPHINE CENTRAL PARK ESTATES PHASE ISECTOR-104, GURUGRAM · Gurugram | Oct 2025 | Aug 2032 | None | In progress |
| DELPHINE CENTRAL PARK ESTATES PHASE IISECTOR-104, GURUGRAM · Gurugram | Oct 2025 | Aug 2032 | None | In progress |
| DELPHINE CENTRAL PARK ESTATES PHASE IIISECTOR-104, GURUGRAM · Gurugram | Oct 2025 | Nov 2032 | None | In progress |
| DESTINO CENTRAL PARKVILLAGE DHUNELA, SECTOR-33, S OHNA, GURUGRAM · Gurugram | Jul 2025 | Jun 2029 | None | In progress |
| THE SELENE TOWERTHE MEDIAN, CENTRAL PARK RESO RTS, OFF SOHNA ROAD, SECTOR-48, GURUGRAM, HARYANA-122018 · Gurugram | Jul 2025 | Jun 2030 | None | In progress |
| CENTRAL PARK BIGNONIA TOWERSVILLAGE DHUNELA, SECTOR-32 SO HNA- GURUGRAM, HARYANA · Gurugram | May 2024 | Jun 2028 | None | In progress |
| COMMERCIAL PLOTTED COLONY - MAG MILEVILLAGE DHUNELA, SECTOR-32, T EHSIL SOHNA · Gurugram | Nov 2023 | Mar 2028 | None | In progress |
| CENTRAL PARK THE ORCHARDSITUATED IN SECTOR-32, TEHSIL -SOHNA, GURUGRAM · Gurugram | Jan 2023 | Jun 2026 | None | Completed Apr 2025 · on time |
| CENTRAL PARK FLOWER VALLEY FLOORS AND VILLASVILLAGE DHUNELA & BERKA, SECT OR-29,30,32 AND 33, SOHNA · Gurugram | Oct 2022 | Dec 2024 | None | Registration lapsed |
| CENTRAL PARK FLOWER VALLEY - PHASE IIISECTOR 29,30, 32 & 33, SOHNA, DIST. GURUGRAM · Gurugram | May 2022 | Dec 2026 | None | In progress |
| CENTRAL PARK FLOWER VALLEYSECTOR 29, 30, 32 & 33 OF VIL LAGE DHUNELA & BERKA, TEHSIL SOHNA, DISTRICT GURUGRAM · Gurugram | Mar 2020 | Dec 2024 | None | Completed Nov 2022 · on time |
| BELLA VISTA - CENTRAL PARK RESORTSSECTOR 48, SOHNA ROAD, NEAR S UBHASH CHOWK, GURGAON · Gurugram | Dec 2019 | Aug 2024 | Feb 2026 (1) | Completed May 2025 · 8 mo late |
| GROUP HOUSING COLONY OF 10.925 ACRESSECTOR-32, SOHNA GURUGRAM · Gurugram | Aug 2017 | Jul 2022 | Jan 2026 (1) | Completed Jan 2023 · 6 mo late |
| RESIDENTIAL PLOTTED COLONYSECTOR 29, 30, 32 AND 33 OF S OHNA, GURUGRAM · Gurugram | Aug 2017 | Jul 2022 | Jan 2027 (1) | In progress |
Companies these projects are registered under (8)
- CENTRAL PARK FLOWER VALLEY · Gurugram
- ST PATRICKS REALTY PRIVATE LIMITED · Gurugram
- ST PATRICKS REALTY PVT LTD · Gurugram
- ST. NICHOLAS ESTATE DEVELOPMENT PVT LTD · Gurugram
- ST. PATRICKS REALTY PVT LTD · Gurugram
- ST. PATRICKS REALTY PVT. LTD. · Gurugram
- ST. PATRICKS REALTY PVT.LTD. · Gurugram
- SWETA ESTATES PVT. LTD. · Gurugram
How we measured
- Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
- Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
- Delay is counted in months between the promised date and completion; a project finished early counts as zero.
- Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.
Sources
- HARERA Gurugram — Gurugram
- Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.
Good to know
Questions buyers ask
Does Central Park deliver on time?+
Per the regulators' own registers, in Gurugram, 2 of 4 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 2.8 months after that date. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.
How many Central Park projects are registered with RERA?+
16 with HARERA Gurugram (Gurugram). 4 of them are completed and 11 are ongoing.
Which Central Park projects are running late?+
None of Central Park's ongoing registrations is past its latest RERA date as of 2026-10-06.
How can I check a Central Park project's RERA record myself?+
Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.