Delivery record · from RERA

Is Krisumi reliable?

Per the regulators' own registers, in Gurugram, 1 of 1 projects whose promised date has passed needed an extension.

7 registrations · checked 6 October 2026

Gurugram · HARERA Gurugram

7

Registered projects

1 completed · 6 ongoing

1

Completed projects with a date on record

Too few to score fairly

—

Median delay past the promised date

Too few completions to compute

0

Overdue now

Ongoing projects past their registration validity with no occupancy certificate on file

Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.

Every registration

Krisumi projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
KRISUMI CITY PHASE 7 (COMMUNITY BUILDINGS)SECTOR- 36A · GurugramJun 2026Mar 2036NoneIn progress
WATERSIDE RESIDENCES THE FOREST RESERVESECTOR- 36A · GurugramMay 2025Jun 2031NoneIn progress
WATERSIDE RESIDENCES THE FOREST RESERVE-IISECTOR- 36A · GurugramMay 2025Jun 2031NoneIn progress
WATERFALL SUITES-IISECTOR- 36A · GurugramApr 2024Dec 2029NoneIn progress
KRISUMI WATERSIDE RESIDENCESSECTOR- 36A, GURUGRAM, HARYAN A · GurugramApr 2024Oct 2029NoneIn progress
WATERFALL SUITESSECTOR 36A · GurugramMay 2023Dec 2028NoneIn progress
WATERFALL RESIDENCEVILLAGE SIHI & HARSARU,SECTOR -36A,GURUGRAM-MANESAR · GurugramMay 2018Dec 2023Dec 2024 (1)Completed Dec 2024 · 11 mo late
Companies these projects are registered under (2)
  • KRISUMI CORPORATION PRIVATE LIMITED · Gurugram
  • KRISUMI CORPORATION PVT. LTD. · Gurugram

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • HARERA Gurugram — Gurugram
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Krisumi Corporation deliver on time?+

Per the regulators' own registers, in Gurugram, 1 of 1 projects whose promised date has passed needed an extension. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Krisumi Corporation projects are registered with RERA?+

7 with HARERA Gurugram (Gurugram). 1 of them are completed and 6 are ongoing.

Which Krisumi Corporation projects are running late?+

None of Krisumi Corporation's ongoing registrations is past its latest RERA date as of 2026-10-06.

How can I check a Krisumi project's RERA record myself?+

Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare Krisumi with the other developers we track, or see the Krisumi homes listed now.