Delivery record · from RERA

Is Experion reliable?

Per the regulators' own registers, in Gurugram, 8 of 11 completed projects with a recorded completion date finished by the date promised at RERA registration.

17 registrations · checked 6 October 2026

Gurugram · HARERA Gurugram

17

Registered projects

11 completed · 3 ongoing

73%

Finished by the date promised at registration

8 of 11 completed projects

0months

Median delay past the promised date

Across completed projects (on-time = 0)

0

Overdue now

Ongoing projects past their registration validity with no occupancy certificate on file

Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.

Every registration

Experion projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
THE TRILLIONPLOT NO. GH3, SECTOR 48, GURU GRAM · GurugramFeb 2025Dec 2032NoneIn progress
ONE42 GOLF COURSE ROADPLOT NO. GH-1 , SECTOR 42, GU RUGRAM · GurugramDec 2024Dec 2034NoneIn progress
WINDCHANTS PHASE CSECTOR 112 GURUGRAM · GurugramOct 2024Mar 2030NoneIn progress
WESTERLIES PHASE-2SECTOR 108 · GurugramFeb 2023Sept 2024NoneCompleted Mar 2018 · on time
HUB 108SECTOR 108, GURUGRAM, HARYANA · GurugramOct 2022May 2024NoneRegistration lapsed
WESTERLIES PHASE 1SECTOR 108 · GurugramJul 2022Sept 2024NoneCompleted Jul 2017 · on time
WESTERLIESSECTOR 108 · GurugramNov 2021Sept 2024NoneCompleted Jan 2024 · on time
ZEPHYR AT THE WESTERLIESSECTOR 108, GURUGRAM · GurugramJun 2020Jul 2024NoneRegistration lapsed
WESTERLIESSECTOR 108 · GurugramNov 2019Jul 2020Jan 2024 (1)Completed Jan 2024 · 42 mo late
HEARTSONG PHASE 6SECTOR 108 · GurugramOct 2019May 2020NoneCompleted Feb 2020 · on time
COMMERCIAL COLONYPART-II, SECTOR-15, GURUGRAM, HARYANA · GurugramOct 2017Oct 2018NoneCompleted Jan 2019 · 3 mo late
THE HEARTSONGSECTOR 108, GURUGRAM · GurugramOct 2017Oct 2018NoneCompleted May 2018 · on time
THE HEARTSONG PHASE-5,2 NO. NURSERY SCHOOLVILLAGE DHARAMPUR,SECTOR-108, GURUGRAM · GurugramAug 2017Aug 2020NoneCompleted Jan 2022 · 17 mo late
WINDCHANTS PHASE -4,NURSERY SCHOOL SITEVILLAGE CHOMA,SECTOR-112,GURU GRAM · GurugramAug 2017Aug 2020NoneRegistration lapsed
RESIDENTIAL PLOTTED COLONY (WESTERLIES)SECTOR 108, GURUGRAM · GurugramAug 2017Aug 2020NoneCompleted Mar 2018 · on time
WINDCHANTS PHASE 3SECTOR 112, CHOMA, GURUGRAM · GurugramAug 2017Aug 2020NoneCompleted Dec 2018 · on time
WINDCHANTS PHASE-2 ( T2, T3. S3 AND S4)SECTOR-112, GURUGRAM · GurugramAug 2017Aug 2018NoneCompleted Jul 2018 · on time
Companies these projects are registered under (6)
  • EXPERION DEVELOPERS PRIVATE LIMITED · Gurugram
  • EXPERION DEVELOPERS PVT LTD · Gurugram
  • EXPERION DEVELOPERS PVT. LTD · Gurugram
  • EXPERION DEVELOPERS PVT. LTD. · Gurugram
  • EXPERION DEVELOPERS PVT. LTD. & OTHERS · Gurugram
  • EXPERION DEVELOPERS PVT.LTD. · Gurugram

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • HARERA Gurugram — Gurugram
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Experion Developers deliver on time?+

Per the regulators' own registers, in Gurugram, 8 of 11 completed projects with a recorded completion date finished by the date promised at RERA registration. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Experion Developers projects are registered with RERA?+

17 with HARERA Gurugram (Gurugram). 11 of them are completed and 3 are ongoing.

Which Experion Developers projects are running late?+

None of Experion Developers's ongoing registrations is past its latest RERA date as of 2026-10-06.

How can I check a Experion project's RERA record myself?+

Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare Experion with the other developers we track, or see the Experion homes listed now.