Is Emaar reliable?

Per the regulators' own registers, in Gurugram, 20 of 22 completed projects with a recorded completion date finished by the date promised at RERA registration.

42 registrations · checked 6 October 2026

Gurugram · HARERA Gurugram

42

Registered projects

22 completed · 17 ongoing

91%

Finished by the date promised at registration

20 of 22 completed projects

0months

Median delay past the promised date

Across completed projects (on-time = 0)

1

Overdue now

Ongoing projects past their registration validity with no occupancy certificate on file

Completion = the date of the first occupancy (or completion) certificate filed on HARERA Gurugram.

Every registration

Emaar projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
MARBELLA TERRACESSECTOR 66 · GurugramJun 2026Dec 2031NoneIn progress
EMAAR BUSINESS DISTRICT NEXT 114VILLAGE BAGHERA, SECTOR 114 G URUGRAM · GurugramApr 2026Dec 2029NoneIn progress
SERENITY HILLS (PHASE-1)SECTOR 86, GURUGRAM, HARYANA · GurugramOct 2025Sept 2032NoneIn progress
SERENITY HILLS (PHASE-2)SECTOR 86, GURUGRAM, HARYANA · GurugramOct 2025Sept 2032NoneIn progress
URBAN ASCENTSECTOR 112, GURUGRAM, HARYANA · GurugramJan 2025Nov 2031NoneIn progress
PLAZA 62SECTOR -62, GURUGRAM, HARYANA · GurugramNov 2024Sept 2029NoneIn progress
URBAN OASIS PHASE 4REVENUE ESTATE OF VILLAGE NAN GLI UMARPUR, SECTOR 62, GURUGRAM, HARYANA · GurugramNov 2024Sept 2029NoneIn progress
AMARISSECTOR 62, GURUGRAM,HARYANA · GurugramNov 2024Aug 2030NoneIn progress
THE 88VILLAGE BAJGHERA, SECTOR 112, GURUGRAM · GurugramMar 2024Mar 2029NoneIn progress
EMAAR BUSINESS DISTRICT 83VILLAGE KHERKI DAULA, SECTOR 83, GURUGRAM, HARYANA · GurugramJan 2024Dec 2028NoneIn progress
EMAAR BUSINESS DISTRICT 65NXT (EBD 65NXT)VILLAGE - BADSHAHPUR, SECTOR 65, GURUGRAM · GurugramOct 2023Aug 2027NoneIn progress
URBAN OASIS - PHASE 1 & 2VILLAGE - MAIDAWAS AND NANGLI UMARPUR, SECTOR - 62 & 65,, GURGAON · GurugramAug 2023Sept 2028NoneIn progress
EMERALD HILLS - PHASE 2VILLAGE BADSHAHPUR, MAIDAWAS, NANGLI UMARPUR, SECTOR - 62 & 65, GURUGRAM · GurugramMay 2023Aug 2027NoneIn progress
EMAAR BUSINESS DISTRICT 114 NXTSECTOR 114, GURUGRAM · GurugramFeb 2023Aug 2027NoneCompleted Sept 2025 · on time
EMAAR BUSINESS DISTRICT 75AVILLAGE - BEGAMPUR KHATOLA, S ECTOR 75A, GURUGRAM · GurugramFeb 2023Aug 2027NoneCompleted Dec 2024 · on time
EMAAR BUSINESS DISTRICT 99 (EBD 99)SECTOR - 99, VILLAGE KHERKI M AJRA, GURUGRAM · GurugramDec 2021Aug 2026NoneRegistration lapsed
EMAAR BUSINESS DISTRICT 99 NXT (EBD 99 NXT)VILLAGE - KHERKI MAJRA, SECTO R 99, GURUGRAM · GurugramDec 2021Aug 2026NoneRegistration lapsed
EMAAR BUSINESS DISTRICT (EBD-89)VILLAGE - BADHA, SECTOR-89, G URUGRAM · GurugramNov 2021Aug 2026NoneCompleted Mar 2025 · on time
EMAAR BUSINESS DISTRICT (EBD-89 NXT)VILLAGE-BADHA, SECTOR-89, GUR UGRAM · GurugramNov 2021Aug 2026NoneCompleted Mar 2025 · on time
EMAAR BUSINESS DISTRICT (EBD) 114SECTOR-114 · GurugramApr 2021Mar 2026NoneCompleted Nov 2023 · on time
Show all 42 registrations
MARBELLA PHASE 2SECTOR 65& 66 · GurugramMar 2021Dec 2027NoneIn progress
EMAAR BUSINESS DISTRICT ( EBD) 65SECTOR 65 · GurugramSept 2020Aug 2024NoneCompleted Jan 2022 · on time
PALM DRIVE & PALM TERRACE SELECTSECTOR 66 · GurugramSept 2020Aug 2021NoneCompleted Jan 2018 · on time
PALM HILLS PHASE 1SECTOR 77 · GurugramMay 2020Dec 2019NoneCompleted Mar 2019 · on time
EMERALD NUEVOSECTOR 65 & 62 BADSHAHPUR NAN GLI MAIDAWAS · GurugramJan 2020Dec 2022NoneRegistration lapsed
PALM SELECTSECTOR 77 SHIKHOPUR GURUGRAM · GurugramDec 2019Aug 2021NoneCompleted Dec 2020 · on time
EMERALD CLASSICSECTOR 65 · GurugramOct 2019Dec 2022NoneCompleted Oct 2021 · on time
EMAAR DIGIHOMESSECTOR 62, GURUGRAM · GurugramMay 2019Mar 2024NoneCompleted Apr 2023 · on time
IMPERIAL GARDEN PHASE 2SECTOR- 102, GURUGRAM · GurugramMar 2019Oct 2018NoneCompleted Oct 2018 · on time
PALM HEIGHTSSECTOR-77, SIKHOPUR, GURUGRAM · GurugramNov 2018Aug 2022Feb 2024 (1)Completed Mar 2023 · 7 mo late
PALM TERRACES SELECT ( GROUP HOUSING PROJECT)SECTOR-66, BADSHAHPUR, GURUGR AM · GurugramFeb 2018Apr 2019NoneCompleted Mar 2019 · on time
PALM HILLS (TOWER A & TOWER B)SECTOR 77, VILLAGE SHIKOHPUR, GURUGRAM, HARYANA · GurugramJan 2018Feb 2022NoneCompleted Dec 2020 · on time
GURGAON GREENSSECTOR -102, VILLAGE DHANKOT, GURUGRAM · GurugramDec 2017Dec 2019NoneCompleted May 2019 · on time
CAPITAL TOWERSVILLAGE SIKANDARPUR GHOSI, SE CTOR 28, GURUGRAM, HARYANA · GurugramOct 2017Jul 2020NoneCompleted Sept 2019 · on time
PALM GARDENSSECTOR-83, VILLAGE KHERKI DAU LLA, GURUGRAM, HARYANA · GurugramOct 2017Dec 2019NoneCompleted May 2019 · on time
MARBELLASECTOR 65,66, GURUGRAM · GurugramOct 2017Oct 2022NoneOverdue
PALM HILLSSECTOR-77, VILLAGE SHIKOHPUR, GURUGRAM · GurugramOct 2017Oct 2022NoneCompleted Mar 2019 · on time
IMPERIAL GARDENSECTOR-102, KHERKI DAULLA, GU RUGRAM · GurugramSept 2017Dec 2019NoneCompleted Oct 2018 · on time
EMERALD HILLSSECTOR 62 AND 65, BADSHAHPUR, GURUGRAM · GurugramAug 2017Aug 2022Feb 2030 (1)In progress
COLONNADESECTOR-66, VILLAGE BADSHAHPUR , GURUGRAM · GurugramAug 2017Jun 2020Dec 2023 (1)Completed Mar 2022 · 21 mo late
EMERALD ESTATESECTOR 65, MAIDAWAS, GURUGRAM · GurugramAug 2017Aug 2022NoneCompleted Mar 2019 · on time
IT COLONY ( COMMERCE PARK)SECTOR- 61, GHATA, GURUGRAM · GurugramAug 2017Mar 2021Sept 2031 (1)In progress
Companies these projects are registered under (5)
  • EMAAR INDIA · Gurugram
  • EMAAR INDIA LIMITED · Gurugram
  • EMAAR MGF LAND LIMITED · Gurugram
  • EMAAR MGF LAND LTD · Gurugram
  • EMAAR MGF LAND LTD. · Gurugram

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • HARERA Gurugram — Gurugram
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Emaar India deliver on time?+

Per the regulators' own registers, in Gurugram, 20 of 22 completed projects with a recorded completion date finished by the date promised at RERA registration. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Emaar India projects are registered with RERA?+

42 with HARERA Gurugram (Gurugram). 22 of them are completed and 17 are ongoing.

Which Emaar India projects are running late?+

1 ongoing registration is past the latest date allowed on RERA without a completion on file, including MARBELLA. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.

How can I check a Emaar project's RERA record myself?+

Search the project's registration number on HARERA Gurugram (haryanarera.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare Emaar with the other developers we track, or see the Emaar homes listed now.