Is Puravankara reliable?

Per the regulators' own registers, in Bengaluru, 3 of 12 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 5.2 months after that date; in Tamil Nadu, 1 of 1 projects whose promised date has passed needed an extension.

59 registrations · checked 6 October 2026

Bengaluru · Karnataka RERA

54

Registered projects

12 completed · 42 ongoing

25%

Finished by the date promised at registration

3 of 12 completed projects

5.2months

Median delay past the promised date

Across completed projects (on-time = 0)

12

Overdue now

Ongoing projects past their latest RERA date with no completion filed

Completion = the date of the first occupancy (or completion) certificate recorded on the project's K-RERA page; where none is recorded, the date the builder applied for completion on K-RERA.

Tamil Nadu · TNRERA

5

Registered projects

0 completed · 5 ongoing

—

Completed without any extension

0 of 0 completed projects

100%

Needed an extension

1 of 1 projects whose promised date has passed

1

Overdue now

Ongoing projects past their latest RERA date and not marked completed

TNRERA marks projects as completed but publishes the completion date only inside PDF certificates, so we report completions and extensions rather than months of delay.

Every registration

Puravankara projects on RERA

Underlined names are listed on Property Point. Newest registrations first.

ProjectRegisteredPromisedExtended toOutcome
Provident Equinox 6Bengaluru South · BengaluruSept 2026Dec 2030NoneIn progress
Purva HeritageBengaluru South · BengaluruJul 2026Aug 2030NoneIn progress
Northern Lights by Puravankara KVNBengaluru North · BengaluruMar 2026Dec 2029NoneIn progress
Northern Lights by Puravankara KVN Phase 2Bengaluru North · BengaluruMar 2026Dec 2030NoneIn progress
Northern Lights by Puravankara KVN Phase 3Bengaluru North · BengaluruMar 2026Dec 2031NoneIn progress
Provident Equinox 5Bengaluru South · BengaluruJan 2026Mar 2030NoneIn progress
Purva SilverskyBengaluru South · BengaluruDec 2025Jul 2030NoneIn progress
Provident Equinox 4Bengaluru South · BengaluruMar 2025Mar 2029NoneIn progress
Provident Deansgate Phase 2Devanahalli · BengaluruMar 2025Mar 2028NoneIn progress
Provident Ecopolitan Phase 5Bengaluru North · BengaluruDec 2024Apr 2029NoneIn progress
PROVIDENT BAYSCAPETamil NaduSept 2024Aug 2028NoneIn progress
Provident Equinox 3Bengaluru South · BengaluruJul 2024Mar 2028NoneIn progress
Purva Kensho HillsAnekal · BengaluruMar 2024Jun 2028NoneIn progress
Provident BotanicoHosakote · BengaluruMar 2024Sept 2028NoneIn progress
Provident DeansgateDevanahalli · BengaluruNov 2023May 2027NoneIn progress
Provident Ecopolitan Phase 1Bengaluru North · BengaluruAug 2023Sept 2027NoneIn progress
Provident Ecopolitan Phase 1ABengaluru North · BengaluruAug 2023Sept 2027NoneIn progress
Provident Ecopolitan Phase 2Bengaluru North · BengaluruAug 2023Jun 2028NoneIn progress
Provident Ecopolitan Phase 3Bengaluru North · BengaluruAug 2023Mar 2029NoneIn progress
Provident Ecopolitan Phase 4Bengaluru North · BengaluruAug 2023Apr 2029NoneIn progress
Show all 59 registrations
Purva BlubelleBengaluru South · BengaluruMar 2023Jun 2029NoneIn progress
Purva OakshireBengaluru East · BengaluruMar 2023Dec 2026NoneIn progress
Purva Windermere Phase-4ATamil NaduJan 2023Dec 2027NoneIn progress
Purva Windermere Phase-4BTamil NaduJan 2023Dec 2028NoneIn progress
Purva Windermere Phase-4CTamil NaduJan 2023Dec 2029NoneIn progress
Purva ZentechBengaluru South · BengaluruOct 2022Jun 2027NoneIn progress
Purva Zenium 2Bengaluru North · BengaluruOct 2022Jun 2027NoneIn progress
Purva MerakiBengaluru South · BengaluruOct 2022Oct 2027NoneIn progress
Sound of Water Phase 3Bengaluru North · BengaluruJun 2022Jun 2027NoneIn progress
Purva Park Hill (Wing A)Bengaluru South · BengaluruJun 2022Dec 2027NoneIn progress
Purva Park Hill (Wing B)Bengaluru South · BengaluruJun 2022Dec 2027NoneIn progress
Purva Park Hill (Wing C)Bengaluru South · BengaluruJun 2022Dec 2027NoneIn progress
Purva Park Hill (Wing D)Bengaluru South · BengaluruJun 2022Dec 2027NoneIn progress
Purva Orient GrandBengaluru South · BengaluruSept 2021Jun 2027NoneIn progress
Sound of Water Phase 2Bengaluru South · BengaluruSept 2021Jun 2026NoneOverdue
Provident Park Square 5Bengaluru South · BengaluruFeb 2020Dec 2024Jun 2026 (2)Overdue
Provident WoodfieldAnekal · BengaluruFeb 2020Dec 2023Sept 2024 (1)Completed May 2023 · on time
Purva PromenadeBengaluru East · BengaluruFeb 2020Dec 2023Sept 2024 (1)Overdue
Provident Capella 2Hosakote · BengaluruJul 2019Sept 2024Jun 2025 (1)Overdue
Provident Capella 1Hosakote · BengaluruJun 2019Dec 2023Sept 2024 (1)Overdue
Provident Equinox 2Bengaluru South · BengaluruMay 2019Sept 2022Jun 2025 (3)Overdue
Provident Equinox 1 (4N, 4P, 4Q, 4R)Bengaluru South · BengaluruMay 2019Mar 2022Dec 2023 (2)Overdue
Purva Zentech Business ParkBengaluru South · BengaluruFeb 2019Mar 2023Dec 2023 (1)Overdue
Purva AtmosphereYelahanka · BengaluruFeb 2019Mar 2024Dec 2025 (2)Overdue
Provident Park Square 4Bengaluru South · BengaluruJan 2019Aug 2022May 2024 (2)Overdue
Purva Westend 2 (Block F)Bengaluru South · BengaluruJan 2019Mar 2022Dec 2022 (1)Completed Mar 2023 · 12 mo late
Purva Zenium 1Bengaluru North · BengaluruJan 2019Mar 2023Dec 2024 (2)Overdue
Purva Somerset HouseTamil NaduJan 2019Mar 2023Sept 2024 (1)Overdue
Provident NeoraYelahanka · BengaluruAug 2018Dec 2021Sept 2023 (2)Completed Apr 2024 · 27 mo late
Provident Park Square Phase 2Bengaluru South · BengaluruMay 2018Oct 2021Jul 2023 (2)Completed Aug 2022 · 9 mo late
Provident Park Square Phase 3 (Towers 5A and 5B)Bengaluru South · BengaluruMay 2018Oct 2021Jul 2023 (2)Completed Aug 2022 · 9 mo late
PROVIDENT PARKWOODSBengaluru North · BengaluruApr 2018Dec 2020Dec 2021 (1)Overdue
Provident Park Square Phase - 1Bengaluru South · BengaluruFeb 2018Dec 2021Sept 2023 (2)Completed Aug 2022 · 7 mo late
Purva SunflowerBengaluru South · BengaluruOct 2017Jun 2018NoneCompleted Feb 2018 · on time
Sound of Water Phase 1 by PuravankaraBengaluru South · BengaluruSept 2017Dec 2019NoneCompleted Aug 2020 · 7 mo late
Purva Coronation SquareBengaluru South · BengaluruSept 2017Sept 2019NoneCompleted Jan 2020 · 3 mo late
Purva WestendBengaluru South · BengaluruSept 2017Dec 2018NoneCompleted Jan 2019 · <1 mo late
Purva Westend Phase 1Bengaluru South · BengaluruSept 2017Dec 2018NoneCompleted Jan 2019 · <1 mo late
Purva PalmbeachBengaluru East · BengaluruSept 2017Mar 2019NoneCompleted Mar 2019 · on time
Companies these projects are registered under (14)
  • ARUN SHELTERS PRIVATE LIMITED · Bengaluru
  • KVN Property Holdings LLP · Bengaluru
  • PROVIDENT WHITE OAKS LLP · Bengaluru
  • Provident Housing Limited · Bengaluru
  • Provident White Oaks LLP · Bengaluru
  • Puravankara Limited · Bengaluru
  • Puravankara Ltd · Bengaluru
  • Puravankara limited · Bengaluru
  • Purva Ruby Properties Limited · Bengaluru
  • Purva Ruby Properties Pvt Ltd · Bengaluru
  • Purva Star Properties Ltd · Bengaluru
  • Purva Star Properties Private Limited · Bengaluru
  • PURAVANKARA LIMITED · Tamil Nadu
  • Puravankara Limited · Tamil Nadu

Includes Provident Housing, Puravankara's wholly owned subsidiary.

How we measured

  • Promised is the completion date the builder declared when the project was registered with RERA. For projects already under way in 2017, that is the date declared at registration, not the original launch promise.
  • Extended to is the latest date allowed after extensions. These include the blanket COVID-19 extensions regulators granted in 2020–21, so part of some delays was not the builder's doing.
  • Delay is counted in months between the promised date and completion; a project finished early counts as zero.
  • Projects are matched to builders by the registered promoter company and, for joint ventures, by the project name. A registration is left out when the match is uncertain.

Sources

  • Karnataka RERA — Bengaluru Urban and Bengaluru Rural districts
  • TNRERA — Tamil Nadu building projects
  • Data as filed by builders on each regulator's public register, last checked Oct 2026 (6 October 2026). Registers can lag; verify any figure on the regulator's site before you rely on it.

Good to know

Questions buyers ask

Does Puravankara Limited deliver on time?+

Per the regulators' own registers, in Bengaluru, 3 of 12 completed projects with a recorded completion date finished by the date promised at RERA registration, and the median project finished 5.2 months after that date; in Tamil Nadu, 1 of 1 projects whose promised date has passed needed an extension. "Promised" means the completion date declared at RERA registration; delays include the blanket COVID-19 extensions of 2020–21.

How many Puravankara Limited projects are registered with RERA?+

54 with Karnataka RERA (Bengaluru Urban and Bengaluru Rural districts); 5 with TNRERA (Tamil Nadu building projects). 12 of them are completed and 47 are ongoing.

Which Puravankara Limited projects are running late?+

13 ongoing registrations are past the latest date allowed on RERA without a completion on file, including Sound of Water Phase 2, Provident Park Square 5, Purva Promenade, Provident Capella 2, Provident Capella 1. A missing filing can lag the work on site, so check the regulator's page before concluding a project is stalled.

How can I check a Puravankara project's RERA record myself?+

Search the project's registration number on Karnataka RERA (rera.karnataka.gov.in) or TNRERA (rera.tn.gov.in). Compare the completion date at registration with the current date, read any extension orders, and look for an occupancy or completion certificate.

Compare Puravankara with the other developers we track, or see the Puravankara homes listed now.