Trains between Porur and Vadapalani run in manual mode at a maximum of 40 km/h under a provisional authorisation, and CMRL is asking for that approval to be extended to March 2027, when the six skipped stations and their signalling are due to be finished (Elets Smart City and Chennaionline, 29 October 2026). Services on the whole Poonamallee Bypass–Vadapalani line run from 6 am to 9 pm, every 10 minutes at weekday peaks and every 15 minutes otherwise (CMRL, 21 October 2026).

Updated 8 November 2026. We read CMRL's Press Release No. 68/2026 and the two 29 October reports. The reports say the Commissioner of Railway Safety had set 31 October 2026 as the deadline for this section; we found no report on whether the extension has been granted.

Official timetable (CMRL, 21 October 2026)

  • Hours: 6 am to 9 pm in both directions from 23 October 2026 (earlier 7 am start advanced after commuter feedback).
  • Monday to Saturday peak (8–11 am and 5–8 pm): every 10 minutes.
  • Monday to Saturday non-peak (6–8 am, 11 am–5 pm, 8–9 pm): every 15 minutes.
  • Sundays and holidays: every 15 minutes, 6 am to 9 pm, no peak service.
  • Last trains: 9 pm from Poonamallee Bypass and from Vadapalani.
  • Line: 11 elevated stations over about 15 km, in passenger service since 11 October 2026.

What manual mode means on this stretch

  • Provisional authorisation: the Porur–Vadapalani section opened under a provisional approval because six stations and part of the signalling were unfinished (Elets, 29 October 2026).
  • Speed: trains are driven manually with a maximum of 40 km/h on this section (Elets). The corridor is designed for up to 80 km/h (DT Next, 12 October 2026).
  • Deadline: the Commissioner of Railway Safety set 31 October 2026 for this section; CMRL planned to seek more time (Elets).
  • Extension sought: until March 2027 (Chennaionline, 29 October 2026).
  • Design: the corridor has CBTC signalling with automatic train control and protection and is built for driverless running (DT Next, 12 October 2026). Those features are not yet in full use on the Porur–Vadapalani stretch.

Timeline of the line since opening

  • 11 October 2026: passenger service begins on the 15 km Poonamallee Bypass–Vadapalani section with 11 stations (CMRL, 21 October 2026); 4 pm to 9 pm on the first day (DT Next, 12 October 2026).
  • 12 October 2026: regular service 7 am to 9 pm, every 10 minutes at weekday peaks and 15 minutes otherwise (DT Next, 12 October 2026).
  • 23 October 2026: first trains advanced to 6 am after commuter feedback; frequencies unchanged (CMRL, 21 October 2026).
  • 29 October 2026: reports say the Porur–Vadapalani section runs in manual mode at up to 40 km/h on a provisional authorisation, with a 31 October deadline from the Commissioner of Railway Safety and an extension to be sought to March 2027 (Elets; Chennaionline).
  • 2 November 2026: CMRL lists a new Metro Connect feeder service linking a private campus with Porur Bypass station (CMRL press-release list).

What this means for daily travel

Frequency is set by the timetable, not by the speed limit: CMRL's published intervals of 10 and 15 minutes apply to the whole line. What the 40 km/h limit affects is the running time on the Porur–Vadapalani stretch, which is slower than the design speed of 80 km/h. Neither CMRL nor the reports give an end-to-end journey time under the current limit, so we do not quote one.

For people renting or buying along the line, the practical point is that the western half (Poonamallee to Porur) already runs as designed, while the eastern half into Vadapalani is in an interim mode until the six stations and their signalling are finished.

The 11 open stations

  • Poonamallee Bypass, Poonamallee Bus Stand, Poonamallee Government Hospital, Karayanchavadi, Kumananchavadi, Kattupakkam, Iyyappanthangal, Thelliyaragaram, Porur Bypass, Porur Junction, Vadapalani (DT Next, 12 October 2026).
  • Skipped until about March 2027: Alapakkam, Karambakkam, Valasaravakkam, Alwarthirunagar, Saligramam Warehouse and Saligramam (see Alapakkam, Karambakkam Metro Opening: March 2027 Target).

What is not decided yet

  • Whether the Commissioner of Railway Safety has granted the extension, and to what date.
  • When automatic signalling takes over and the 40 km/h limit is lifted on this stretch.
  • Any change in frequency after the six stations open. CMRL's 21 October timetable is the current one.