The Parijaata line is Corridor 3 of the Bengaluru Suburban Rail Project, running about 35.5 km from Kengeri to Whitefield through KSR Bengaluru, Cantonment, Benniganahalli and KR Puram. It is approved on paper but not under construction: K-RIDE's May 2026 newsletter says South Western Railway approved the alignment in December 2025 and the land requirement is still being finalised. The whole project's completion target was moved to March 2030 in January 2026.
Updated 17 November 2026. We checked K-RIDE's project page and its May and July 2026 newsletters, The Hindu's January 2026 report, Wikipedia's corridor table and BMRCL's Purple Line station list. For all four lines with station lists, see Bangalore Suburban Rail Stations: All 4 Lines, 2026 Status.
What is approved and what is still proposed?
- Approved: the project as a whole. K-RIDE's July 2026 newsletter says it was approved by the Ministry of Railways on 21 October 2020, at an estimated cost it now gives as ₹23,342 crore.
- Approved: the Corridor 3 alignment, by South Western Railway in December 2025 (K-RIDE, May 2026).
- Still being finalised: the land needed along that alignment (K-RIDE, May 2026).
- Not started: civil construction. K-RIDE's July 2026 newsletter says works are under way at 30 stations, all on Corridor 2 (Benniganahalli–Chikkabanavara) and Corridor 4 (Heelalige–Rajanukunte).
- Not published: a final, dated station list for Corridor 3. K-RIDE's project page on 17 November 2026 carried documents for Corridors 2 and 4 only.
How long is the Parijaata line and how many stations will it have?
Wikipedia's corridor table gives 35.52 km and 14 stations, and its text gives 35.2 km. Our October 2026 post cited a Parliament reply listing 9 stations. K-RIDE has not published a count for this corridor, so treat both numbers as provisional until a station list appears with the land notifications.
Wikipedia names the route points Whitefield, KR Puram, Benniganahalli, Bengaluru Cantonment, KSR Bengaluru and Kengeri.
When will the Parijaata line open?
The Hindu reported on 22 January 2026 that the project's completion was extended from October 2026 to March 2030, with separate deadlines for each corridor, after a PRAGATI review. Wikipedia says the Sampige and Parijaata lines were pushed to 2030 and records a minister's statement that Parijaata had been moved below Corridors 2 and 4 in priority because it runs parallel to the metro. With land not yet finalised in May 2026, no opening year should be treated as firm.
Which areas would it serve, and how does it overlap the Purple Line?
The suburban line and the Purple Line share both ends and several stops. BMRCL's Purple Line already runs Whitefield–KR Puram–Benniganahalli–Baiyappanahalli–Majestic–Mysore Road–Rajarajeshwari Nagar–Kengeri–Challaghatta. What the suburban line would add is fewer stops, higher capacity per train and a direct link to KSR Bengaluru and Cantonment railway stations.
- West end: Kengeri. The metro already stops at Kengeri and Kengeri Bus Terminal; see Kengeri, Bangalore.
- Centre: KSR Bengaluru (Majestic) and Cantonment, where the Pink Line's underground section is being built.
- East: Benniganahalli (planned interchange with the Mallige line and the Purple Line), KR Puram (Purple Line, and Blue Line under construction) and Whitefield. See Kr Puram, Bangalore and Whitefield, Bangalore.
How is suburban rail different from Namma Metro?
K-RIDE's 2026 newsletters describe a system built to Indian Railways standards but run like a metro. These features are set for the whole project; Parijaata would use them only once it is built.
- Trains: on 6 May 2026, Bi-RIDE gave the Integral Coach Factory, Chennai, a ₹1,513.75 crore work order for 153 air-conditioned ‘broad-gauge metro type’ coaches, with supply to begin within 18 months, aimed first at the Chikkabanavara–Yeshwanthpur section of Corridor 2 (May 2026 issue).
- Power: 25 kV AC overhead traction, like main-line railways, rather than the metro's 750 V third rail listed by BMRCL (July 2026 issue).
- Signalling: ETCS Level-2 train control across all corridors (July 2026 issue).
- Depots: Soladevanahalli, near Chikkabanavara, will maintain trains for Corridors 2 and 4, and a depot at Akkupete has its government order (July 2026 issue). No depot for Corridor 3 has been announced in these issues.
- Name: K-RIDE now calls the scheme the Bengaluru Suburban Transport Project (BSTP) in its newsletters, implemented by K-RIDE/Bi-RIDE.
Should the Parijaata line affect where you buy?
At both ends, the metro is what works today, so judge homes on distance to a Purple Line station. Near Kengeri, RERA-registered options include Provident Equinox 6 (Provident Equinox 6; PRM/KA/RERA/1251/310/PR/180926/008948, registered 18 September 2026, proposed completion 31 December 2030) and Brigade Horizon on Mysore Road (PRM/KA/RERA/1251/310/PR/190722/005086, registered 19 July 2022). At the Whitefield end, Embassy East Avenue on ITPL Main Road is registered as PRM/KA/RERA/1251/446/PR/200224/006649 (20 February 2024, proposed completion 30 September 2028). All three were checked on the Karnataka RERA list on 17 November 2026.
Treat any sales claim that a project is ‘next to the Parijaata station’ with care until K-RIDE publishes the station list.