Corridor 4 of the Bengaluru Suburban Rail Project, the Kanaka Line from Heelalige near Chandapura to Rajanukunte beyond Yelahanka, is under construction at the station level. K-RIDE’s May 2026 newsletter shows work on station foundations at Huskur, Bellandur, Rajanukunte, Jakkur and others, private land acquisition ‘almost completed’, and fresh tenders invited on 13 May 2026 for the track-bed (alignment) works. There is no K-RIDE opening date in that issue; Wikipedia lists a planned opening of June 2029.

Updated 17 November 2026. We read K-RIDE’s May 2026 Samparka newsletter page by page, checked K-RIDE’s newsletter index (page updated 17 November 2026), the corridor contract report of December 2023, the 19 October 2026 land notice as reported, and Wikipedia’s Kanaka line page. K-RIDE’s later August–September 2026 issue is an image-only PDF we could not read as text, so progress figures are as of the May 2026 issue. For a station list with homes nearby, see Kanaka Line Suburban Rail Stations List and Homes Nearby.

How long is the Kanaka Line and how many stations does it have?

The corridor is 46.88 km: 8.96 km on viaduct and 37.92 km at grade (The Metro Rail Guy, 31 December 2023). Sources disagree on the station count (17, 18, 19 or 21). K-RIDE’s own station packages settle most of it: C4A has 9 stations and C4B has 9, a total of 18. Benniganahalli, the interchange with the Purple Line and the Mallige Line, is built under the separate Corridor 2 station package (C2A), which makes 19 stopping points. Bommasandra and Bagmane appear on some lists as future stations and are not in either C4 package.

Which stations are in each package, and how far along are they?

  • C4A (9 stations; 8 at grade, Marathahalli elevated): Heelalige, Singena Agrahara, Huskur, Ambedkar Nagar, Karmelaram, Bellandur, Marathahalli, Doddanakundi, Kaggadasapura.
  • Huskur: raft concrete done; 24 of 26 piers or columns done; 6 of 13 portal beams done. A casting yard was commissioned here, and the first 16.5 m T-girder of C4A was cast on 28 April 2026.
  • Bellandur: raft concrete done; 21 of 26 columns up to ground level; 327 m of 459 m retaining wall (first lift).
  • Heelalige: 27 of 126 piles done. Ambedkar Nagar: raft excavation complete. Kaggadasapura: 2 of 12 raft grids concreted. Karmelaram and Singena Agrahara: excavation in progress.
  • C4B (9 stations; 6 at grade, Hennur, R K Hegde Nagar and Yelahanka elevated): Channasandra, Horamavu, Hennur, Thanisandra, R K Hegde Nagar, Jakkur, Yelahanka, Muddanahalli, Rajanukunte.
  • Rajanukunte: excavation complete; 221 m of 247 m retaining wall; 5 of 12 raft grids concreted. Jakkur: 82 of 104 piles. Channasandra: 85 m of 205 m raft excavation. Thanisandra, Muddanahalli and Horamavu: ground investigation done or under way.

What are the new alignment and bridge packages?

  • Alignment Package 1, Benniganahalli to Jakkur: 6.259 km at grade plus 3.681 km of viaduct (chainage 22.386 km to 33.742 km), including validation of works already done. EPC tender invited 13 May 2026, bids opening 30 June 2026, 24-month completion period.
  • Alignment Package 2, Heelalige to Bellandur: 12.632 km at grade. EPC tender invited 13 May 2026, bids opening 30 June 2026, 18-month completion period.
  • Alignment Packages 3 and 4: ‘to be published shortly’ as of May 2026.
  • Road-over-bridge and road-under-bridge Package 1: 2 ROBs and 1 RUB replacing level crossings, estimated ₹59.61 crore, 18 months.
  • ROB Package 2: 2 ROBs replacing level crossings, estimated ₹49.655 crore, 18 months.
  • We found no award announcement for these packages in the sources we could read, so treat them as tendered, not awarded.

What land notices have been issued for Corridor 4?

K-RIDE said private land acquisition for Corridor 4 was almost complete in May 2026. A further Karnataka Gazette notification (No. 1150, notification CI 92 SPQ 2026, dated 19 October 2026) scheduled 57 properties totalling 8,963.81 sq m across Doddakannalli, Kodathi, Hadosiddapura, Doddanekundi, Horamavu, Horamavu Agara, Gottamaranahalli and Srirampura for alignment, utility and station entry works (NammaWard, 23 October 2026). Village-level detail: Suburban Rail Corridor 4 Land Notice: Horamavu to Doddanekundi

Where does the Kanaka Line meet metro and other rail lines?

  • Benniganahalli: Purple Line (open) and Mallige Line. K-RIDE says the Kanaka viaduct sits directly below the Blue Line viaduct for about 0.5 km near the Benniganahalli flyover, avoiding about 1.65 acres of land acquisition and saving an estimated ₹150–169 crore.
  • Marathahalli: a Blue Line station (BMRCL target May 2027) and an elevated Kanaka station; K-RIDE has not published a walking link between them. Guide: Marathahalli Metro Station Bangalore: Blue Line Status, Homes
  • Yelahanka: elevated Kanaka station; also a Sampige Line (Corridor 1) station. Guide: Bangalore Suburban Rail Route: Sampige Line KSR to Devanahalli
  • Karmelaram: listed as a future Red Line interchange (Wikipedia).

When will Corridor 4 open?

K-RIDE’s May 2026 newsletter gives no opening date. Wikipedia’s infobox lists June 2029, and its references include a 22 January 2026 The Hindu report headlined that the whole suburban project’s deadline moved to 2030. Older pages that still say 2026 or March 2027 are out of date. With alignment tenders opening in mid-2026 on 18- and 24-month periods, our arithmetic puts the earliest end of civil work around mid-2028, before signalling, electrification and safety checks. Overview of all four lines: Bangalore Suburban Rail Stations: All 4 Lines, 2026 Status

Homes near key Kanaka Line stations

K-RIDE has not published station footprints, so we list RERA-registered projects by locality, not by distance.

  • Rajanukunte: Shriram Serenity (K-RERA PRM/KA/RERA/1251/309/PR/170924/007026; RERA completion 5 July 2029; 2 and 3 BHK, about ₹77 lakh to ₹1.32 crore) and Sobha Chartered Birdsong plots (K-RERA PRM/KA/RERA/1251/472/PR/210325/007605; RERA completion 31 December 2028). Shriram Serenity and Sobha Chartered Birdsong
  • Jakkur: Mana Verdant (K-RERA PRM/KA/RERA/1251/309/PR/260523/005947; RERA completion 31 December 2030; resale only). Mana Verdant
  • Marathahalli: Century Mirai (K-RERA PRM/KA/RERA/1251/446/PR/181025/008182; about 450 m from the Blue Line station). Century Mirai
  • Chandapura side (Heelalige): Signature Regal, Madivala village (K-RERA PRM/KA/RERA/1251/308/PR/040926/008911; RERA completion 31 July 2031). Signature Regal
  • Area pages: Yelahanka, Bangalore, Thanisandra, Bangalore, Chandapura, Bangalore