In east Bangalore, the Outer Ring Road Blue Line from Silk Board to KR Puram (19.75 km) is 87% built, with public service targeted for around mid-2027. The Sarjapur–Hebbal Red Line (Phase 3A) is awaiting central approval, according to an October 2026 report; BMRCL's own page still says its DPR is being prepared. The KR Puram–Hoskote metro is at the DPR stage. On the roads, the Bangalore–Chennai Expressway is open for about 100 km from Hoskote, and the STRR Hoskote–Hosur stretch may open in phases from December 2026.
Updated 17 November 2026. We checked BMRCL's own Phase 3A figures, the October 2026 Blue Line progress report, the Hoskote metro station list, the expressway and STRR status, Business Corridor packages, Sarjapur Road work orders and K-RIDE's corridor dates. A changelog below records what moved.
When will the Outer Ring Road metro (Blue Line) open?
- Silk Board–KR Puram, 19.75 km: 87% built. Trial runs were due by the end of October 2026, and the minister asked for sectional test trains from the first week of November. Public service is targeted for around mid-2027, subject to statutory clearances (The Indian Express, via Transclew, 23 October 2026).
- Works still pending in August 2026: Marathahalli and Central Silk Board stations, the Baiyappanahalli depot link, and utility shifting at Iblur. A travellator to the Yellow Line station at Silk Board was still at tender stage (Swarajya, 16 August 2026).
- Early opening towards Marathahalli: BMRCL wants it, but an official told The Indian Express that permissions may not be granted (via Transclew).
- KR Puram–Hebbal: early 2028. Full Blue Line: March 2028 (New Indian Express table, via Transclew).
Detail: Blue Line Opening Date: Silk Board–KR Puram Now Mid-2027 and Blue Line Metro Trial Run KR Puram to Marathahalli: Nov 2026.
Is there a metro coming to Sarjapur Road and Hoskote?
- Phase 3A Red Line, Sarjapur–Hebbal: BMRCL's own page lists 36.59 km (14.45 km tunnel, 22.14 km elevated) with 28 stations (11 underground, 17 elevated), and says the detailed project report is being prepared. A 16 October 2026 report gives 37.8 km, says Karnataka has submitted the DPR and a revised, lower cost, and says the Union housing ministry is examining it with no deadline. BMRCL has started geotechnical tests along Sarjapur Road (Asianet Newsable). We use BMRCL's length. See Sarjapur Road Metro (Phase 3A, Red Line): What Is Actually Sanctioned in 2026.
- KR Puram–Hoskote: 16.3 km, 11 stations (KR Puram, ITI Bhavan, TC Palya, Bhattarahalli, Bhattarahalli Junction, Medahalli Junction, Avalahalli, Budigere Cross, Katamnallur Gate, Hoskote Toll Plaza, Hoskote Government Hospital). The DPR is under preparation, and no dates have been set (Construction World, 8 October 2026). See KR Puram to Hoskote Metro Plan (Nov 2026): 11 Stops, Status.
- Phase 4 proposal, Kalena Agrahara–Kadugodi Tree Park: about 69 km via Jigani, Attibele and Sarjapur Road. Its feasibility study is still being prepared, and it is not approved (Oneindia, 27 October 2026).
What is the status of expressways and ring roads in the east?
- Bangalore–Chennai Expressway: the Karnataka stretch, Hoskote–Bethamangala (71 km), has been open since 9 December 2024. A 25 km Andhra section to Baireddipalle opened in June 2026. NHAI officials target December 2026 for the full road (The Hans India, 29 June 2026).
- STRR Hoskote–Hosur (21 km): phased opening as early as December 2026. The railway overbridge girder at Lingadeeramallasandra is due in December 2026 and the second girder by March 2027 (Oneindia, 23 October 2026).
- Bengaluru Business Corridor: Package 2, Bellary Road to Old Madras Road (17 km), and Package 3 (14.6 km, linking to Sarjapur Road) were due for tender in August 2026. Package 4 (15.6 km to Hosur Road, partly elevated) was expected in September–October 2026 (Construction World, 31 July 2026).
- ORR white-topping: ₹450 crore of work planned between October 2026 and January 2027 (Swarajya, 16 August 2026). See ORR White-Topping, Silk Board–KR Puram: ₹450 Cr Plan (2026).
What is being done on Sarjapur Road, Varthur and Dommasandra?
- Dommasandra flyover: under construction, with no completion date announced. On 12 October 2026 the Greater Bengaluru Development Minister told KRDCL, PWD and the Greater Bengaluru Authority to work together, ease congestion at Dommasandra–Kadugodi junctions within 15 days, widen roads wherever land is available, and build drains along the flyover (Oneindia). See Dommasandra Flyover Status 2026: Sarjapur–Varthur Road.
- Koramangala–Iblur buffer road: 5.5 km from the Inner Ring Road to Iblur Junction on Sarjapur Road, built by B-SMILE, for cars, two-wheelers and pedestrians only. The target was March 2026 (Newsfirst, 23 December 2025). We could not find a later report confirming it is open.
- Suburban rail Corridor-4: Heelalige–Bennigenahalli (22.5 km) and Bennigenahalli–Rajanukunte (24.6 km), target March 2029. Corridor-2, Yeshwanthpur–Bennigenahalli: December 2028 (K-RIDE, via Knight Frank H1 2026).
Will Hoskote get Cauvery water?
Hoskote is one of the eight local bodies in Cauvery Stage 6, approved on 26 February 2026 at about ₹7,000 crore. Funding was still being sought from the World Bank, JICA and others, and no completion date was given (Oneindia, 27 February 2026). Inside the city, water service and connection rules are set by BWSSB. See BWSSB New Areas 2026: Sarjapur, Anekal, Jigani Water Explained to check whether a Sarjapur or Anekal address falls inside its area.
What changed since our last east Bangalore update?
- 17 November 2026: first tracker version. Added Blue Line ORR progress (87%) and the mid-2027 target; BMRCL's official Phase 3A figures (36.59 km, 28 stations) next to the 37.8 km press figure; the Hoskote metro station list; Business Corridor packages 2 to 4; the Dommasandra work orders of 12 October 2026.
- Compared with Whitefield–Hoskote Investment Zone 2026–2030: The Drivers: no new official opening date for any metro line in the east.
- Next check: Blue Line trial-run notice, the STRR Hoskote–Hosur phased opening in December 2026, and any central approval for Phase 3A.