Sattva Group (formerly Salarpuria Sattva) has 15 ongoing RERA-registered residential projects in Bangalore as of 20 November 2026, with K-RERA completion dates from 30 December 2026 (Sattva Bhumi plots) to 21 October 2032 (Sattva Aangane). The builder's own ‘onwards’ prices run from ₹39.61 lakh at Sattva Lumina in Yelahanka to ₹5.17 crore for Sattva Springs villas on Kanakapura Road. Three were registered in September–October 2026: Aangane on Old Madras Road, Ekatra plots near STRR and Amritya at Jigani.
Updated 20 November 2026. We read Sattva's Bengaluru residential page for prices and status, matched every project to the Karnataka RERA register for Bengaluru Urban and Bengaluru Rural (register of 11 November 2026), and checked K-RERA's applied-for-completion list. Most new Sattva projects are registered by Sattva Resi Pvt Ltd; plots and a few others use Shirasa Construction, Trinayani Realtors, Sattva City Pvt Ltd and older Salarpuria companies.
Sattva ongoing projects: summary table with RERA numbers
Ordered by K-RERA completion date. Format: Project — Area — RERA no. — Configs — Builder's price — K-RERA completion.
- Sattva Bhumi — Devanahalli — PRM/KA/RERA/1250/303/PR/211024/007160 — plots — price on request — 30 December 2026
- Sattva Springs — Kanakapura Road — PRM/KA/RERA/1251/310/PR/240724/006948 — 4 BHK villas — from ₹5.17 Cr — 18 September 2027
- Sattva Aeropolis Phase 2 (Aeropolis II) — NH 44, near the airport — PRM/KA/RERA/1250/303/PR/250925/008119 — studio, 1, 3 BHK — price on request — 16 October 2028
- Sattva Ekatra — off Doddaballapur Main Road, 300 m from STRR — PRM/KA/RERA/1250/301/PR/180926/008945 — plots — price on request — 19 March 2029
- Sattva Songbird — Budigere Main Road, off Old Madras Road — PRM/KA/RERA/1251/446/PR/060924/007008 — studio, 1, 2, 3 BHK — from ₹53.07 lakh — 6 May 2029
- Sattva Park Cubix Phase 2 — Devanahalli town, NH 207 — PRM/KA/RERA/1250/303/PR/280225/007529 — studio, 1, 2, 3 BHK — price on request — 15 September 2029
- Sattva Lumina — Doddaballapura Main Road, Yelahanka — PRM/KA/RERA/1251/472/PR/060924/007009 — studio, 1, 2, 3 BHK — from ₹39.61 lakh — 1 November 2029
- Sattva Forest Ridge — JP Nagar 9th Phase — PRM/KA/RERA/1251/310/PR/241224/007315 — 1, 2, 3 BHK — price on request — 31 December 2029
- Sattva Vasanta Cove — Sattva City, Airport Road — PRM/KA/RERA/1250/303/PR/041225/008310 — studio, 1 BHK — price on request — 27 December 2030
- Sattva Aaranya — Mysore Road, near Jnanabharathi metro — PRM/KA/RERA/1251/310/PR/241225/008358 — 3, 4 BHK — price on request — 23 January 2031
- Sattva Vasanta Skye — Kannamangala, near the airport — PRM/KA/RERA/1250/303/PR/080525/007730 — studio to 4 BHK — price on request — 6 May 2031
- Sattva Songbird Phase 2 — Budigere Main Road — PRM/KA/RERA/1251/310/PR/270326/008557 — 2, 3 BHK — price on request — 27 June 2031
- Sattva Amritya — Jigani Main Road, Anekal taluk — PRM/KA/RERA/1251/308/PR/301026/009061 — 1, 2, 3 BHK — price on request — 28 October 2031
- Sattva City — Airport Road, near the toll gate — PRM/KA/RERA/1251/472/PR/270226/008494 — 2, 3, 4 BHK — price on request — 28 February 2032
- Sattva Aangane — Old Madras Road, near Budigere Cross — PRM/KA/RERA/1251/446/PR/180926/008944 — 3, 4 BHK — price on request — 21 October 2032
Sattva new launch 2026: Aangane, Ekatra and Amritya
Sattva Aangane, Old Madras Road: K-RERA registered it on 18 September 2026 under Sattva Resi Pvt Ltd in Bengaluru East taluk, with a completion date of 21 October 2032. Sattva's site lists it as a new launch of 3 and 4 BHK homes near Budigere Cross. Some listings give ‘Dec 2030 onwards’ for the first phase; the registered completion date is 21 October 2032. Page: Sattva Aangané; detail: Sattva Aangane Budigere 2026: Price, RERA, Sizes, Possession.
Sattva Ekatra, Doddaballapur: a plotted project registered the same day (18 September 2026) by Shirasa Construction Pvt Ltd, with completion on 19 March 2029. The builder lists plots of 20×30, 30×40 and 40×50 ft plus odd sizes, 300 m from STRR. Page: Sattva Ekatra; detail: Sattva Ekatra Plots Doddaballapur: 503 Sites, RERA 2029.
Sattva Amritya, Jigani: registered on 30 October 2026 in Anekal taluk with completion on 28 October 2031; the builder lists 1, 2 and 3 BHK homes on Jigani Main Road, behind HCL. Amritya does not have a page in our catalogue yet; see Sattva Amritya Jigani: RERA, 432 Homes, 1–3 BHK, 2031.
Sattva Lumina, Yelahanka
Lumina is Sattva's lowest-priced current launch in the city, from ₹39.61 lakh for studio to 3 BHK homes (builder). K-RERA registered it on 6 September 2024 in Yelahanka taluk with completion on 1 November 2029. Page: Sattva Lumina; area: Yelahanka, Bangalore.
Sattva Songbird, Budigere (Old Madras Road)
Songbird is on Budigere Main Road off Old Madras Road and runs from ₹53.07 lakh for studio to 3 BHK homes (builder). The first phase was registered on 6 September 2024 (completion 6 May 2029) and Songbird Phase 2, listed by Sattva as a new launch of 2 and 3 BHK homes, on 27 March 2026 (completion 27 June 2031). Page: Sattva Songbird; area: Budigere Cross, Bangalore.
Sattva projects near the airport: Sattva City, Vasanta Skye, Vasanta Cove, Aeropolis II, Park Cubix II, Bhumi
Six Sattva registrations sit on the airport side of North Bengaluru. Sattva City on Airport Road near the toll gate (registered 27 February 2026, completion 28 February 2032) is the township; Vasanta Cove (studio and 1 BHK, completion 27 December 2030) and Vasanta Skye (studio to 4 BHK, completion 6 May 2031) are near it. Aeropolis II on NH 44 (completion 16 October 2028) shows October 2026 construction photos on Sattva's site. Park Cubix Phase 2 in Devanahalli town (completion 15 September 2029) and the Sattva Bhumi plots (completion 30 December 2026) complete the cluster.
Pages: Sattva City, Sattva Vasanta Skye, Sattva Vasanta Cove, Sattva Aeropolis II, Sattva Park Cubix II and Sattva Bhumi. Area: Devanahalli, Bangalore.
Sattva projects in South and West Bangalore: Springs, Forest Ridge, Aaranya
Sattva Springs on Kanakapura Road is a 4 BHK villa project from ₹5.17 crore (completion 18 September 2027). Sattva Forest Ridge in JP Nagar 9th Phase offers 1 to 3 BHK homes (completion 31 December 2029). Sattva Aaranya on Mysore Road near Jnanabharathi metro station offers 3 and 4 BHK homes (registered 24 December 2025, completion 23 January 2031). Pages: Sattva Springs, Sattva Forest Ridge and Sattva Aaranya.
Sattva ready to move projects in Bangalore
Two Sattva projects appear on K-RERA's applied-for-completion list: Salarpuria-Sattva East Crest on Old Madras Road (PRM/KA/RERA/1251/446/PR/170920/000406, filed 3 February 2024) and the Salarpuria Sattva Serene Life plots at Shettigere (PRM/KA/RERA/1250/303/PR/181215/002219, filed 29 January 2024; Salarpuria Sattva Serene Life). Sattva's own site also labels these as ‘ready to move in’, with starting prices:
- Sattva Bliss, Budigere Cross — PRM/KA/RERA/1251/446/PR/120123/005620 — 2, 3 BHK from ₹90.87 lakh (K-RERA completion date 22 August 2027; ask for the OC for your tower); Sattva Bliss
- Salarpuria Sattva Anugraha, Vijayanagar — PRM/KA/RERA/1251/309/PR/171014/000407 — 2, 2.5, 3 BHK from ₹1.14 Cr; Salarpuria Sattva Anugraha
- Salarpuria Sattva Misty Charm, off Kanakapura Road — PRM/KA/RERA/1251/310/PR/180507/001635 — 1, 2, 3 BHK from ₹1.08 Cr; Salarpuria Sattva Misty Charm
- Salarpuria Sattva Park Cubix, Devanahalli town — PRM/KA/RERA/1250/303/PR/171023/001749 — 1, 2, 3 BHK from ₹1.02 Cr
- Sattva Green Groves plots, near Nelamangala toll — PRM/KA/RERA/1250/307/PR/040524/006863; Sattva Green Groves
Sattva projects the builder lists as under construction
Two more Sattva registrations are listed by the builder as under construction: Sattva Aeropolis near the airport (PRM/KA/RERA/1250/303/PR/110522/004869; 1, 2 and 3 BHK from ₹68.53 lakh) and Sattva La Vita villas off Hennur Main Road (PRM/KA/RERA/1251/446/PR/041223/006446; 4 BHK villas from ₹5.70 crore). Check their K-RERA pages for the latest quarterly progress. Pages: Sattva Aeropolis and Sattva La Vita.
How to verify a Sattva project on K-RERA
- Search the RERA number on rera.karnataka.gov.in. Sattva's site says all its projects are RERA-registered but does not print the numbers, so ask for the number in writing and match it to the list above.
- Check the promoter: most new projects are Sattva Resi Pvt Ltd; Bhumi and Ekatra are Shirasa Construction; Aeropolis is Trinayani Realtors.
- Note the completion date for your phase; Songbird and Aeropolis have separate registrations.
- Read quarterly progress (/blog/karnataka-rera-quarterly-progress-report-check-construction-2026) and, for ready homes, the OC (Occupancy Certificate Download Online in Bangalore: Check an OC).
- Pipeline and upcoming launches: Sattva Upcoming Projects in Bangalore 2027: Full List; all listed projects: Bangalore.