On-time builders · Bengaluru · October 2026

Bengaluru builders who deliver on time

Every project registered with Karnataka RERA declares a completion date. We set each promise against the date of the official occupancy certificate. These 15 builders finished at least 75% of their projects on time, 187 projects delivered as promised.

#BuilderDelivered on timeProjects
1DS-MAX
96%
26 of 27 on time
2Rohan Builders
100%
12 of 12 on time
3Prestige Group
83%
34 of 41 on time
4Sobha
77%
47 of 61 on time
5Godrej Properties
91%
10 of 11 on time
6Vaishnavi Group
100%
6 of 6 on time
7Renaissance Holdings
100%
6 of 6 on time
8L&T Realty
100%
5 of 5 on time
9Pride Group
100%
5 of 5 on time
10Sumadhura
82%
9 of 11 on time
11Sattva (Salarpuria)
80%
8 of 10 on time
12Abhee
83%
5 of 6 on time
13Modern Spaaces
83%
5 of 6 on time
14Lakepoint Builders
83%
5 of 6 on time
15Bren Corporation
80%
4 of 5 on time

Ordered by on-time rate, weighted for how many projects it rests on. “Delivered on time” means the occupancy or completion certificate is dated on or before the promised date plus the COVID-19 extension.

How we measured

  • Promised: the completion date declared to K-RERA at registration, plus the COVID-19 extension granted to every project.
  • Delivered: the first occupancy or completion certificate on the project's K-RERA page.
  • On the list: at least 5 certified projects, with 75% or more of them delivered on time.

Source

  • Karnataka RERA , Bengaluru Urban and Rural. Read on 7 October 2026.
  • Free to quote with credit: “Property Point, from Karnataka RERA records, October 2026”.
  • Builders: to suggest a correction, write to sanjeevflyers@gmail.com with the registration number.

Good to know

Which builders in Bengaluru deliver on time?+

On Karnataka RERA records (checked October 2026), 15 builders finished at least 75% of their certified projects by the promised date, among them DS-MAX, Rohan Builders, Prestige Group, Sobha, Godrej Properties. Together they delivered 187 projects on time.

How is this list made?+

For each builder's Bengaluru projects on Karnataka RERA, we compare the completion date promised at registration (plus the COVID-19 extension the authority granted to every project) with the date of the official occupancy or completion certificate. Builders appear when at least 75% of their certified projects, and at least 5 of them, were finished by the promised date.

Why isn't my builder on the list?+

The list includes only builders with at least 5 certified completions and an on-time rate of 75% or more. Many good builders are newer or have fewer certified projects on record. Every project's own record is on the Karnataka RERA website.

Are COVID-19 delays counted?+

No. Karnataka RERA granted a COVID-19 extension to registered projects in 2020–21, and we add it to every promised date before comparing.