In Bengaluru areas with underground drainage, an in-house sewage treatment plant (STP) is now mandatory only for apartment projects with more than 120 units that generate more than 80 kilolitres of sewage a day (KLD). In areas without underground drainage, every project above 20 units still needs one. That is the effect of the 12 March 2024 amendment by Karnataka's Department of Forest, Ecology and Environment, as reported at the time; it applies to new projects, and existing STPs continue. Where an STP is needed, it requires KSPCB consent to establish (CFE) and consent to operate (CFO), with fees set by plant capacity.

Updated 18 November 2026. We read KSPCB's current consent-fee page and its consent menus, and OneIndia's 27 March 2024 report of the amendment. We could not open the notification itself or two other reports (403 and 404), so confirm the threshold for your project with KSPCB or BWSSB before relying on it.

Which apartments in Bangalore must have an STP?

  • Sewered areas (with underground drainage): in-situ STP required for projects with more than 120 units and more than 80 KLD of sewage (amendment of 12 March 2024, as reported by OneIndia).
  • Unsewered areas: in-situ STP required for all projects with more than 20 units (same report).
  • Before 2024: a 2016 government order had required in-situ STPs for group housing above 20 units in Bengaluru; for sewered areas, the threshold was more than 50 units or 35 KLD (OneIndia's summary).
  • Not retrospective: the 2024 amendment applies to new projects, and complexes that already have smaller STPs can keep operating them (OneIndia).
  • Conflict: some installer guides still quote 20 or 50 units, or a built-up-area test. Those reflect the older rules. The project's own CFE/CFO, issued by KSPCB, is the document that settles it for a given building.

KSPCB grants consent in two stages: consent to establish (CFE), taken by the developer before building the STP, and consent to operate (CFO), needed before the plant runs. Applications go through KSPCB's XGN online consent system. Fees for residential apartments, layouts and townships are fixed by STP capacity and the type of local body, not by project cost.

  • Up to 10 KLD (Green): CFE ₹5,000 · CFO ₹2,000
  • Above 10 to 50 KLD (Orange): CFE ₹25,000 · CFO ₹10,000
  • Above 50 to 100 KLD (Orange): CFE ₹50,000 · CFO ₹20,000
  • Above 100 to 300 KLD (Red): CFE ₹1,25,000 · CFO ₹50,000
  • Above 300 to 500 KLD (Red): CFE ₹2,00,000 · CFO ₹80,000
  • Above 500 to 1,000 KLD (Red): CFE ₹3,75,000 · CFO ₹1,50,000
  • 1 to 25 MLD (Red): CFE ₹6,25,000 · CFO ₹2,50,000
  • Several STPs in one project are added together to find the band. City municipal councils and taluk or gram panchayat areas pay less (KSPCB fee page).
  • Older articles quote a ‘₹250 a year’ CFO fee for apartments. KSPCB's current fee page does not list it.
  • Assume the developer's design puts total sewage at 200 KLD across two STPs of 100 KLD each. Combined capacity is 200 KLD, so the Red band ‘above 100 to 300 KLD’ applies.
  • Within a city corporation: CFE ₹1,25,000, paid by the developer before building the plant.
  • CFO ₹50,000 per fee year. KSPCB's page says CFO validity and the number of fee years vary by category, so the total depends on the validity granted.
  • After handover, renewing the CFO is usually the association's job. Budget it in maintenance (see Maintenance Charges in Bangalore Apartments 2026: GST, Corpus).

What should you check before booking a flat?

  • Whether the project needs an in-situ STP at all, and why: sewered or unsewered area, unit count and design sewage load.
  • The KSPCB CFE: ask for it, or look in the project's K-RERA documents. Its capacity should match the number of flats.
  • Where the STP sits on the sanctioned plan (basement or open), and access for desludging and maintenance.
  • Treated-water reuse: dual piping for flushing, and landscape use. Read Water Problem in Bangalore Apartments: 12 Checks to Run for the wider water checks.
  • Browse RERA-registered projects at /projects, for example Brigade Eternia, and put the STP questions to the sales team in writing.

What should the association collect at handover?