North Bangalore's biggest projects in November 2026 are the airport metro (Blue Line Phase 2B), which is 61.5% built with targets ranging from June 2027 to March 2028, and suburban rail Corridor-1 to Devanahalli and the airport, targeted for March 2030. Alongside them are the 68 km Bengaluru Business Corridor, where package 1 from Tumakuru Road to Bellary Road has been awarded, and KWIN City, where KIADB has been told to start allotting plots in February–March 2027. The STRR Dobbaspet–Hoskote arc has been open since March 2024.

Updated 17 November 2026. We checked the latest dated report for each project, put the conflicting metro targets side by side, and added the K-RIDE corridor dates and the Cauvery Stage 6 town list. A changelog below records what moved since our last north Bengaluru round-up.

When will the airport metro open?

  • Blue Line, KR Puram–Hebbal–airport: 38.44 km, 61.5% built (The Indian Express, via Transclew, 23 October 2026).
  • Hebbal–airport target: end-2027 (The Indian Express). Start of operations: October–November 2027, according to the state minister (The Hindu, via Transclew). Business Today (10 August 2026): December 2027. Knight Frank (July 2026): June 2027 for Phase 2B.
  • Hebbal–KR Puram target: early 2028; full corridor March 2028 (New Indian Express table, via Transclew).
  • Proposed Doddajala–Devanahalli link: about 13.6 km. Its feasibility study is complete, but like all Phase 4 corridors it is not approved or funded (Oneindia, 27 October 2026).
  • Next milestone to watch: trial runs on the airport section. Asianet Newsable reported November 2027 for the start of trials (via Transclew), which conflicts with the minister's operations target.

Station-level detail is at Airport Metro Line Bangalore: 29 Stations, Oct 2026 Status, and the Phase 4 list is at Namma Metro Phase 4 Route Map: 8 Proposed Corridors (2026).

What is the status of suburban rail in the north?

K-RIDE's commissioning targets, as published in Knight Frank's H1 2026 report:

  • Corridor-1 (Sampige): Bengaluru city–Yelahanka 17.7 km and Yelahanka–Devanahalli plus airport 29.5 km, target March 2030
  • Corridor-2 (Mallige): Chikkabanavara–Yeshwanthpur 7.4 km and Yeshwanthpur–Bennigenahalli 17.5 km, target December 2028
  • Corridor-4 (Kanaka): Bennigenahalli–Rajanukunte 24.6 km and Heelalige–Bennigenahalli 22.5 km, target March 2029
  • Overall: about 148 km across four corridors in the first phase, with long-term plans for about 306 km (Knight Frank, citing K-RIDE)

Corridor-2 runs through Hebbal, Nagawara and Banaswadi, and Corridor-4 reaches Yelahanka and Rajanukunte, so both matter to north Bengaluru buyers. More at K-RIDE Suburban Rail and the Mallige Line: Status in 2026 and the Areas It Would Serve and Bangalore Suburban Rail Stations: All 4 Lines, 2026 Status.

Which road projects are under way in north Bangalore?

  • STRR Dobbaspet–Hoskote (NH-648), 80 km: inaugurated on 11 March 2024. Package 1 (Dobbaspet–Doddaballapur Bypass, 42 km) and Package 2 (Doddaballapur Bypass–Hoskote, 38 km). Toll at Nallaru began in November 2023 for Package 2 and in June 2024 for Package 1 (The Metro Rail Guy). See STRR Road Map and Status: Hoskote–Hosur by December 2026.
  • Bengaluru Business Corridor (former PRR), 68.36 km in four packages: Package 1, Tumakuru Road to Bellary Road (about 21 km), has been awarded, and land marking is under way. Package 2, Bellary Road to Old Madras Road, is 17 km. The tender for the 20 km first package was ₹3,348 crore. The contract allows three years, and the government has asked for two (Construction World, 31 July 2026). See Peripheral Ring Road Bangalore Villages List 2026 (All 61).
  • Hebbal–Silk Board tunnel road, 16.75 km twin tunnel: Adani Enterprises was the lowest bidder for both packages. The contract had not been awarded by 1 October 2026, and the state was still seeking Defence land, including about 2 acres near Hebbal for a ramp (Construction World). See Bangalore Tunnel Road Project Status 2026: Route, Toll, Date.
  • Hebbal short tunnel (BDA): 1,128 trees are proposed for felling, and more than 1,500 objections were received. The National Green Tribunal has barred felling until its next hearing on 15 December 2026 (The News Minute, 21 October 2026).
  • Airport road toll at Sadahalli: ₹120 for a car, unchanged from 1 April 2026 (newskarnataka.com).

What is happening with KWIN City and the Aerospace Park?

  • KWIN City: at a 16 October 2026 review, Industries Minister M.B. Patil told KIADB to start allotting plots to investors from February–March 2027 and to report progress every 15 days. The investment target is ₹50,000 crore (newkerala, citing ANI). See KWIN City Bengaluru 2026: Location, Status, Plots by March.
  • KIADB Aerospace Park near Devanahalli: Knight Frank names Boeing, Shell, SAP and Collins Aerospace as occupiers, and notes the commissioning of Collins Aerospace's 26-acre facility for over 2,200 employees (H1 2026 report). See Flats Near Aerospace Park Bangalore 2026: Prices, Commute.
  • Housing demand: in Knight Frank's figures, North Bengaluru launches rose 10% and sales 11% year on year in H1 2026, the fastest growth of any Bengaluru zone.

Will Devanahalli and Yelahanka get more Cauvery water?

Cauvery Stage 6 was approved on 26 February 2026 at about ₹7,000 crore. It will supply eight local bodies: Madanayakanahalli, Chikkabanavara, Hunasemaranahalli, Nelamangala, Hoskote, Devanahalli, Bashettihalli and Vijayapura, plus the Kempegowda and Shivarama Karanth layouts. The government plans to seek funding from the World Bank, JICA and others, and no completion date has been given (Oneindia, 27 February 2026). Until Stage 6 is built, ask any Devanahalli or Vijayapura project how it gets its water. More at Cauvery Stage 6 Areas List 2026: The 8 Towns and Status.

What changed since our last north Bangalore update?

  • 17 November 2026: first tracker version. Added the airport-metro progress figure (61.5%) and the October 2026 targets; K-RIDE corridor dates from Knight Frank H1 2026; KWIN allotment timing (16 October 2026); the NGT hearing date for the Hebbal short tunnel (15 December 2026).
  • Compared with North Bangalore Investment 2026–2030: 8 Dated Drivers (7 November 2026): no new official opening dates; the tunnel road contract was still not awarded on the latest report we could open.
  • Next check: after the NGT hearing on 15 December 2026 and any BMRCL trial-run notice for the airport line.