Namma Metro Phase 4 is a PROPOSED network of about 215 km in eight corridors, reported on 27 October 2026, reaching Tumakuru, Bidadi, Harohalli, Attibele, Hoskote and Devanahalli (OneIndia, 27 October 2026). It is not approved: a senior BMRCL official said the Phase 4 routes are 'not finalised or approved' (GoodReturns citing Moneycontrol, 27 October 2026). There is no sanctioned cost, no published alignment, no station list and no deadline for buyers or landowners to act on.

Updated 8 November 2026. We read both 27 October reports, traced each corridor back to its earliest official mention we could open (tenders, feasibility reports, a DPR handover), and matched K-RERA registered projects in our catalogue to the existing metro stations near each corridor. One corridor, KR Puram to Hoskote, already has its own post: KR Puram to Hoskote Metro Plan (Nov 2026): 11 Stops, Status.

The eight proposed Phase 4 corridors

Lengths and stages below are as reported on 27 October 2026 unless another date is given. 'Feasibility done' means a study exists. It does not mean the government has approved the line or found the money, and OneIndia says the same.

  • Madavara – Tumakuru (Green Line extension, Tumakuru Road via Nelamangala) — 59.9 km — feasibility study and DPR complete (OneIndia, 27 Oct 2026). The DPR was handed to the state on 23 May 2026: 59.6 km, 27 elevated stations, ₹20,649 crore, PPP model (IANS via The News Minute, 24 May 2026).
  • Kalena Agrahara – Jigani – Attibele – Sarjapur Road – Kadugodi Tree Park, with a branch to Anekal Cricket Stadium — about 69 km — feasibility study still being prepared (OneIndia, 27 Oct 2026). Described in 2024 as 52.41 km via Jigani, Anekal, Attibele, Sarjapur and Varthur (Public TV, 22 Jul 2024).
  • Silk Institute – Harohalli (Green Line, Kanakapura Road) — about 21.7 km — feasibility study complete (OneIndia, 27 Oct 2026). Listed as 24 km when the study was tendered (Public TV, 22 Jul 2024).
  • KR Pura – Hoskote (Purple Line side, Old Madras Road, possibly via Avalahalli and Budigere Cross) — length not stated — feasibility study complete (OneIndia, 27 Oct 2026). Details: KR Puram to Hoskote Metro Plan (Nov 2026): 11 Stops, Status.
  • Challaghatta – Bidadi (Purple Line, Mysuru Road beyond Kumbalgodu) — about 15.6 km — feasibility study complete (OneIndia, 27 Oct 2026). Listed as 15 km in 2024 (Public TV, 22 Jul 2024).
  • Doddajala – Devanahalli (from the airport Blue Line to Devanahalli town) — about 13.6 km — feasibility study complete (OneIndia, 27 Oct 2026). Earlier reported as 10 km (Metro Rail Today, 20 Oct 2025).
  • Bommasandra – Attibele (Yellow Line, Hosur Road) — length not stated — feasibility study complete (OneIndia, 27 Oct 2026). Listed as 11 km (Public TV, 22 Jul 2024; Metro Rail Today, 20 Oct 2025).
  • Kadabagere – Tavarekere (western end of the Phase 3 Magadi Road line) — 6.6 km — at DPR stage (OneIndia, 27 Oct 2026). Earlier reported as approved for addition under Phase 3A (NativePlanet, 25 Apr 2026).

When each corridor first appeared

Most of Phase 4 is not new. The corridors have been in tenders and statements since 2023. This timeline helps when a brochure says a line is 'coming soon'.

  • 11 Aug 2023 — the state is 'actively considering' metro links to Doddaballapur, Nelamangala, Devanahalli and Hoskote (The News Minute, 11 Aug 2023).
  • Feb 2024 — BMRCL tenders a ₹1.59 crore feasibility study covering Challaghatta–Bidadi, Silk Institute–Harohalli, Bommasandra–Attibele and the Kalena Agrahara–Kadugodi Tree Park line. A Hyderabad-based firm was chosen (Public TV, 22 Jul 2024).
  • 25 Sep 2025 — government order directing BMRCL to prepare a fresh DPR for Madavara–Tumakuru; on 29 Sep 2025 Home Minister G Parameshwara confirmed the feasibility study was accepted (Swarajya, 30 Sep 2025).
  • 20 Oct 2025 — BMRCL calls a direct Bengaluru–Hosur metro 'technically not feasible' and evaluates an 11 km Bommasandra–Attibele extension instead (Metro Rail Today, 20 Oct 2025, citing Deccan Herald).
  • 25 Apr 2026 — state approval reported for adding Kadabagere–Tavarekere under Phase 3A (NativePlanet, 25 Apr 2026).
  • 23 May 2026 — the Madavara–Tumakuru DPR is handed to Home Minister G Parameshwara at Vidhana Soudha; it will go to the Cabinet (IANS via The News Minute, 24 May 2026).
  • 27 Oct 2026 — the eight corridors are reported together as Phase 4, about 215 km; BMRCL says not finalised (OneIndia; GoodReturns, 27 Oct 2026).

What is NOT decided

  • No corridor in Phase 4 has state Cabinet approval with a cost, as far as we could find on 8 November 2026. The Tumakuru DPR was to go to the Cabinet (24 May 2026) and we found no decision since.
  • No alignment or station list has been published by BMRCL for any Phase 4 corridor. Any station name in an advertisement is a guess or a report, not an official stop.
  • No land acquisition notice has been issued for Phase 4. For comparison, Phase 3 was approved by the Union Cabinet in August 2024, and its Orange Line land notice came in October 2026: Namma Metro Phase 3 Land Acquisition: The 16 Oct 2026 Notice.
  • Lengths differ by source (Tumakuru 59.9 or 59.6 km; Harohalli 21.7 or 24 km; Devanahalli 13.6 or 10 km; Jigani loop 69 or 52.41 km). We show both because neither figure is final.

What exists today near each corridor

Plan around these, not around Phase 4. Distances are straight lines from our map pin to the station (our station file, October 2026).

  • Tumakuru Road: Green Line open to Madavara since 7 November 2024. Sattva Green Groves (plots, K-RERA PRM/KA/RERA/1250/307/PR/040524/006863), near Nelamangala toll, is about 11.7 km from Madavara.
  • Bannerghatta Road (Jigani loop's start): the Pink Line's elevated stretch from Kalena Agrahara is due to open on 13 or 15 November 2026 (OneIndia; The Hans India, both 2 Nov 2026). Sobha Magnus (K-RERA PRM/KA/RERA/1251/310/PR/131025/008160, RERA completion 31 May 2030) is about 0.8 km from Kalena Agrahara station.
  • Mysuru Road: Purple Line open to Challaghatta. Provident Equinox, Kumbalgodu (K-RERA PRM/KA/RERA/1251/310/PR/180724/006944, RERA completion 31 Mar 2028) is about 2.0 km from Challaghatta.
  • Kanakapura Road: Green Line open to Silk Institute. Purva Park Hill (K-RERA PRM/KA/RERA/1251/310/PR/220601/004946) is about 0.3 km from Thalaghattapura station.
  • Airport Road: the Blue Line's Doddajala station is under construction. Sattva City (K-RERA PRM/KA/RERA/1251/472/PR/270226/008494, RERA completion 28 Feb 2032) is about 0.5 km from it.
  • Hosur Road: Yellow Line open to Delta Electronics Bommasandra since 11 August 2025. Brigade Valencia (K-RERA PRM/KA/RERA/1251/308/PR/120123/005613, RERA completion 31 Dec 2027) is about 2.4 km from that station.

What to do now

  • 1. Treat every Phase 4 corridor as a proposal. If a seller quotes a Phase 4 station, ask for the BMRCL or government document that names it. None has been published.
  • 2. Price a home on today's access: the nearest open or under-construction station and the road. Use /metro/bengaluru to check station status.
  • 3. Check the project on the K-RERA portal (rera.karnataka.gov.in): registration number, RERA completion date and approvals. Our project pages carry the number.
  • 4. If you own land along a corridor, keep your RTC, mutation and survey sketch current. There is no notice to respond to yet; when one comes, it will name survey numbers and give an objection window.
  • 5. Watch for three triggers: a state Cabinet decision with a cost (Tumakuru is first in line), a published alignment, and a land notice. We will update this page when any of them happens.