The ₹450 crore Outer Ring Road revamp covers 17 km from Silk Board Junction to KR Puram in two packages: Silk Board to Iblur (5.44 km, ₹143 crore) and Iblur to KR Puram (11.57 km, ₹307 crore), according to the government order reported by News Karnataka (1 January 2026). The Greater Bengaluru Authority planned the white-topping work for October 2026 to January 2027 (Swarajya, 16 August 2026), while companies on the corridor asked for it to wait until the Blue Line metro opens.
Updated 8 November 2026. We could not find a dated report confirming that carriageway work had started by this date, so check with the Greater Bengaluru Authority before planning around it. This page sets out what was approved, the timeline on record and what residents of Bellandur, Marathahalli and the corridor can expect.
What is in the ₹450 crore ORR project?
- Two packages: Package 1, Silk Board Junction to Iblur Junction, 5.44 km, ₹143 crore; Package 2, Iblur Junction to KR Puram, 11.57 km, ₹307 crore (News Karnataka, 1 January 2026).
- Funding: the state pays 50%; the Bengaluru East and Bengaluru South City Corporations share the rest equally.
- Works: a bus priority lane marked with signage, bollards at points and digital enforcement rather than continuous barriers; rebuilt footpaths; cycle lanes; white-topping at major junctions; vertical gratings against flooding; overhead gantries and signage; utility ducts; and upgrades to connecting roads.
- Footpaths: the Minister ordered end-to-end footpaths at least 3 metres wide on the ORR and up to 1.8 metres on side roads, with taxi and bus pick-up points and bus bays (Business Today, 18 August 2026).
When does the work start, and why is it disputed?
- Minister Krishna Byre Gowda directed officials to begin ORR white-topping in October 2026 and to work with companies on 50% work-from-home arrangements during construction, with internal roads used for diversions (Business Today, 18 August 2026).
- Plan on record: October 2026 to January 2027 (Swarajya, 16 August 2026).
- The Outer Ring Road Companies Association, which represents more than 500 companies, asked the GBA to hold major carriageway work until the Blue Line is running, and rejected work-from-home as a substitute for traffic planning. It asked for a white-topping versus black-topping comparison, a traffic simulation and a construction plan coordinated with the traffic police and the metro schedule (Business Today, 18 August 2026).
- The association said it supports drains, utilities, footpaths and flood work along the corridor in the meantime.
How does it fit with the Blue Line?
The Blue Line's Phase 2A runs above the same stretch, Silk Board to KR Puram, with stations at HSR Layout, Agara, Ibbaluru, Bellandur, Kadubeesanahalli, Marathahalli and beyond. Business Today (18 August 2026) put its expected opening at around June 2027; our metro status file (20 October 2026) also records March 2027 and May 2027 targets from other reports, and Swarajya (16 August 2026), citing The Times of India, reported that commercial operation within 2026 was not feasible. The full line to the airport is expected by March 2028. See Blue Line Metro Bangalore Opening Date: Silk Board–KR Puram 2026.
If the road work runs from late 2026 into 2027, residents could see road and metro work on the corridor at the same time, which is the overlap the companies' association raised.
What residents along the ORR should expect
Browse more homes along the corridor at Outer Ring Road Orr and Bellandur, Bangalore.
- Diversions onto internal roads during carriageway work, per the Minister's plan; side roads in Bellandur, Kadubeesanahalli and Marathahalli are the likely alternates.
- Longer school-run and office commutes during construction; check your society's exit routes once the diversion plan is published.
- After completion: wider footpaths, bus bays and a bus priority lane, which matter most for residents who walk to an office or a future Blue Line station.
- Registered homes close to the corridor in our catalogue include Godrej Reflections, Harlur Road (PRM/KA/RERA/1251/446/PR/180329/002843, ready, 1.2 km from the Ibbaluru station site) — Godrej Reflections; and, in the Bellandur area, Sobha Insignia (PRM/KA/RERA/1251/446/PR/030922/005212, ready) — Sobha Insignia, and Purva Meraki in HSR Layout (PRM/KA/RERA/1251/310/PR/071022/005307, RERA completion date 31 Oct 2027).