The Bommasandra–Attibele metro is a PROPOSED extension of the Yellow Line along Hosur Road from Delta Electronics Bommasandra to Attibele, listed in Phase 4 with a completed feasibility study (OneIndia, 27 October 2026). Earlier reports put it at 11 km (Public TV, 22 July 2024; Metro Rail Today, 20 October 2025). BMRCL says Phase 4 routes are not finalised or approved (GoodReturns citing Moneycontrol, 27 October 2026). There is no DPR, cost, station list or date.
Updated 8 November 2026. We checked why the plan stops at Attibele rather than Hosur, what the Yellow Line offers today, and which K-RERA projects in our catalogue sit near its southern end. One year of the Yellow Line: Yellow Line One Year On: What Changed for Electronic City and Bommasandra Homes.
The record so far
- Feb 2024 — Bommasandra–Attibele (11 km) included in BMRCL's ₹1.59 crore feasibility tender (Public TV, 22 Jul 2024).
- 11 Aug 2025 — Yellow Line (RV Road–Delta Electronics Bommasandra, 19.15 km, 16 stations) opened to the public (our station file, citing Wikipedia).
- 20 Oct 2025 — BMRCL declared a direct Bengaluru–Hosur metro 'technically not feasible' and evaluated the 11 km Attibele extension on its own system (Metro Rail Today, 20 Oct 2025, citing Deccan Herald).
- 27 Oct 2026 — Bommasandra–Attibele listed in the proposed Phase 4, feasibility study complete (OneIndia, 27 Oct 2026).
Why the line stops at Attibele, not Hosur
Attibele is the last major suburb before the Tamil Nadu border. A feasibility study done for the Tamil Nadu side proposed a 25 kV AC overhead power system for Hosur–Bommasandra, while Namma Metro runs on 750 V DC third rail. A senior BMRCL official said the Hosur line 'just cannot be integrated into our system', and the assessment was sent to the Karnataka government (Metro Rail Today, 20 October 2025, citing Deccan Herald). Extending to Attibele keeps the same DC system, so trains could run through from the Yellow Line.
What is NOT decided
- No state approval of the feasibility report has been reported, and no DPR has been ordered.
- No stations have been named between Bommasandra and Attibele (Chandapura and Hebbagodi-side stops are not confirmed).
- The 27 October 2026 report gives no length; 11 km is the earlier figure.
- Whether Tamil Nadu pursues a separate link from Hosur to Attibele is outside BMRCL's plan as reported.
K-RERA projects near the Yellow Line's southern end
Straight-line distance from our map pin to the nearest open Yellow Line station.
- Purva Silversky — Purva Silversky, Hebbagodi, K-RERA PRM/KA/RERA/1251/310/PR/151225/008338, 356 units, RERA completion 30 Jul 2030. About 0.8 km from Huskur Road station.
- Brigade Valencia — Brigade Valencia, Bommasandra, K-RERA PRM/KA/RERA/1251/308/PR/120123/005613, 662 units, RERA completion 31 Dec 2027. About 2.4 km from Delta Electronics Bommasandra.
- Shriram Songs Of The Earth — Shriram Songs of the Earth, Chandapura, K-RERA PRM/KA/RERA/1251/310/PR/120625/007819. Our pin is the Chandapura locality centre, about 4.0 km from Delta Electronics Bommasandra.
- Sobha Townpark — Sobha Townpark, towards Attibele, K-RERA PRM/KA/RERA/1251/308/PR/230125/007418 to 007421, RERA completion dates 31 Dec 2030 to 30 Jun 2033. About 7.4 km from Delta Electronics Bommasandra.
What to do now
- 1. Use Delta Electronics Bommasandra as the end of the line for any commute plan south of Electronic City.
- 2. Do not price Chandapura or Attibele homes on a metro station; none exists or is approved there.
- 3. Check K-RERA registration and completion date on rera.karnataka.gov.in; area pages: Attibele, Bangalore and Chandapura, Bangalore.
- 4. Landowners on Hosur Road between Bommasandra and Attibele: no metro alignment or land notice exists.
- 5. Watch for state approval of the feasibility study and a DPR order. Budget-home context: Budget Homes Beyond Electronic City: Chandapura, Attibele and Phase 2 in 2026.