In west Bangalore, Mysore Road has the Purple Line to Challaghatta and Tumkur Road has the Green Line to Madavara, both already open. The next approved line is Phase 3. It includes the 12.5 km Hosahalli–Kadabagere line on Magadi Road and the 32.15 km Kempapura–JP Nagar 4th Phase line through Peenya, Nagarbhavi and Mysuru Road, approved in August 2024 with completion estimated for 2032. The Madavara–Tumakuru (59.9 km) and Challaghatta–Bidadi (15.6 km) metro extensions are only proposals.
Updated 17 November 2026. We checked the current metro lines, the Phase 3 station lists, BMRCL's proposed Phase 4 corridors, K-RIDE's west-side dates, the Business Corridor first package, the Bidadi–Harohalli township notifications, the July 2026 Mysuru expressway toll and the Cauvery Stage 6 towns. A changelog below records what moved.
Which metro lines already serve Mysore Road and Tumkur Road?
- Purple Line, Whitefield (Kadugodi) to Challaghatta: 43.49 km, 37 stations. Kengeri–Challaghatta opened on 9 October 2023 (Wikipedia). Station pages: /metro/bengaluru/rajarajeshwari-nagar.
- Green Line, Madavara to Silk Institute: 33.46 km, 32 stations. The Nagasandra–Madavara extension on Tumkur Road opened on 7 November 2024 (Wikipedia). Station page: /metro/bengaluru/peenya.
What is the status of the Magadi Road and Phase 3 metro?
- Hosahalli–Kadabagere (Magadi Road): 12.5 km, elevated, 9 stations (Kadabagere, Kamath Layout, Byadarahalli, Herohalli, Anjana Nagar, Sumanahalli Cross, Kamakshi Palya, KHB Colony, Hosahalli).
- Kempapura–JP Nagar 4th Phase: 32.15 km, elevated, 22 stations including Hebbal, BEL Circle, Peenya, Sumanahalli Cross, BDA Complex Nagarbhavi, Nagarbhavi Circle, Mysuru Road and Hosakerehalli.
- Approval and cost: approved by the Union Cabinet in August 2024. The ₹15,611 crore cost covers both lines. BMRCL has not finalised a deadline, and The Metro Rail Guy estimates 2032 (page updated February 2026).
- Recent step: the Orange Line land acquisition notice is covered at Namma Metro Phase 3 Land Acquisition: The 16 Oct 2026 Notice, and design changes at Namma Metro Phase 3: Orange and Grey Line Status and What Is Realistic for Buyers.
Which west Bangalore metro extensions are only proposals?
These are on BMRCL's proposed Phase 4 list. None is approved or funded, and BMRCL says the corridors are not finalised (Oneindia, 27 October 2026):
- Madavara–Tumakuru: 59.9 km, a Green Line extension via Nelamangala. Feasibility study and DPR completed.
- Challaghatta–Bidadi: 15.6 km along Mysuru Road beyond Kumbalgodu. Feasibility study completed. See Bidadi Metro 2026: Proposed 15.6 km Line From Challaghatta.
- Kadabagere–Tavarekere: 6.6 km, linking to the Phase 3 Magadi Road line. DPR stage reached.
When will suburban rail reach Kengeri and Chikkabanavara?
- Corridor-3, Kengeri to Bengaluru Cantonment: 16.9 km, K-RIDE target March 2030
- Corridor-2, Chikkabanavara to Yeshwanthpur: 7.4 km, target December 2028; Yeshwanthpur to Bennigenahalli 17.5 km, also December 2028
- Source: K-RIDE commissioning table in Knight Frank's India Real Estate H1 2026 report. For Yeshwanthpur-side works, see Mathikere Double-Decker Flyover: 1.11 km, Awarded Oct 2026.
What is happening on west Bangalore's roads and the Bidadi township?
- Bengaluru–Mysuru Expressway: since July 2026 a car pays ₹185 one way at Kaniminike and Sheshagirihalli, and there is a ₹360 local monthly pass for residents within 20 km (Asianet Newsable, 22 July 2026).
- Bengaluru Business Corridor Package 1: Tumakuru Road to Bellary Road, about 21 km, awarded, with land marking under way. The full corridor runs from Madavara near Nelamangala to Electronics City (Construction World, 31 July 2026).
- STRR west: the Dobbaspet–Hoskote arc has been open since 11 March 2024. The western packages from Obalapura to Kunigal were re-tendered in September 2024 (The Metro Rail Guy, page updated 7 September 2024). We could not open a later award notice.
- Greater Bengaluru Integrated Township, Bidadi–Harohalli: final notifications covered 499 acres in June 2026, over 4,941 acres on 15 July 2026 and 1,895 acres (Kanchugaranahalli and Byramangala) on 30 October 2026, over 7,335 acres in all. A four-member review committee headed by Justice Guhanathan Narendar was formed in August 2026. The project is run by the Greater Bengaluru Development Authority (The News Minute, 2 November 2026). See Bidadi Township Latest News: Villages, Land, Nearby Prices.
- PRR-2 near Kengeri: land matters are covered in PRR-2 Bengaluru: Kengeri Land Sale, HC Stay and What to Check.
Which west Bangalore towns are in Cauvery Stage 6?
Cauvery Stage 6, approved on 26 February 2026 at about ₹7,000 crore, lists Nelamangala, Madanayakanahalli, Chikkabanavara and Hunasemaranahalli among its eight local bodies. It also covers the Kempegowda and Shivarama Karanth layouts. Funding was still being sought, and no completion date was given (Oneindia, 27 February 2026).
What changed since our last west Bangalore update?
- 17 November 2026: first tracker version. Added the Phase 3 station lists, the three Phase 4 western proposals (marked unapproved), the K-RIDE Corridor-2 and Corridor-3 dates, the 30 October 2026 township notification and the July 2026 expressway toll.
- Compared with Mysore Road–Bidadi Investment Zone 2026–2030: The Drivers: no new approvals for any western metro extension.
- Next check: Phase 3 civil tenders on BMRCL's site, any decision on Phase 4, and the township review committee's report.
Area pages: Kengeri, Bangalore, Rajarajeshwari Nagar, Bangalore and Yeshwanthpur, Bangalore. A catalogue project on Tumkur Road is Brigade Lumina. For locality context, read Magadi Road, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks and Tumkur Road and Nagasandra, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks. A proposed line is not a funded line, so price a home on the metro station that is open today.