Sarjapur Road is not one widening project but four pieces of work. The 4.7 km main road from Iblur Junction to Carmelaram was widened to 45 metres and asphalted in 2022; the service road is still waiting on land acquired under Transfer of Development Rights (TDR), and the Greater Bengaluru Authority (GBA) began re-asphalting about 5 km between Iblur and the Carmelaram rail overbridge in December 2025. At the Koramangala end, white-topping was given an end-March 2026 deadline. A new Lower Agaram link on defence land and the 134 km Anekal–Sarjapur–Varthur–airport road are separate projects.
Updated 18 November 2026. We dated each report, split the work into stretches, converted the 134 km road’s figures into crore, and added what plot and flat owners along the road should check. We could not open an official GBA status page for these works, so the dates below come from dated news reports.
What is the status of each Sarjapur Road stretch?
- Iblur Junction – Carmelaram (RJ Tech Park), 4.7 km: main carriageway widened to 45 m and asphalted in 2022. The service road is held up by properties still to be acquired under TDR; on 3 June 2025 the BBMP chief commissioner told officials to settle compensation and also develop the Iblur, Haralur Road and Kasavanahalli Road junctions (Deccan Herald, 4 June 2025).
- Iblur – Carmelaram railway overbridge, about 5 km: GBA began asphalting (Deccan Herald, 8 December 2025).
- Automart Junction – Agara Junction (Koramangala end): closed for white-topping from late September 2025 for up to two months (Deccan Herald, 29 September 2025). On 20 February 2026 the GBA chief set end-March 2026 for finishing white-topping on Sarjapur Road and Koramangala Road (Asianet Newsable, 21 February 2026). We found no dated report confirming completion.
- Lower Agaram – Ejipura – Iblur new link: see the next section.
- Anekal – Sarjapur – Varthur – airport – Nelamangala, 134 km (KRDCL): fresh state funding in November 2026; see below.
What is the Lower Agaram–Sarjapur Road on defence land?
This is a new link meant to take traffic from the city centre to Sarjapur Road without going round the defence area.
- Late September 2024: Deputy Chief Minister D K Shivakumar announced that the Defence Ministry had agreed to transfer 12.34 acres, with in-principle consent for another 10.77 acres. A BBMP official said Lower Agaram–Ejipura would be widened and a new road built from Ejipura to Agara (Deccan Herald, 3 October 2024).
- 24 February 2025: the realigned plan was reported as 6.9 km from Lower Agaram through the Ejipura signal to Iblur, 24 m wide, with ₹55 crore earmarked and completion promised in about 15 months. The defence land comes under an ‘equal value infrastructure’ arrangement (Citizen Matters).
- 22 December 2025: the Deputy Chief Minister inspected a 5.5 km road being built in a storm-water drain buffer zone between Koramangala and Sarjapur. He said it could cut the MG Road–Bellandur distance by nearly 10 km, should be ready within three months and will be open only to two-wheelers and cars. Defence land still lay in the way, and the state had written to the Defence Minister (Deccan Herald, 23 December 2025).
What is the 134 km Anekal–Sarjapur–Varthur road?
It is the outer corridor, run by the Karnataka Road Development Corporation (KRDCL). It links Attibele, Sarjapur, Dommasandra, Gunjur, Varthur, Whitefield, Kempegowda airport and Nelamangala. Construction World (10 November 2026) reports that the state Cabinet allocated ₹1,119 crore more. That includes ₹267 crore for land acquisition and ₹348 crore for price adjustment. The project’s total cost is revised to ₹3,409 crore, against ₹2,291 crore when sanctioned in 2017. Works include a 1.92 km elevated stretch at Varthur and railway flyovers at Gollahalli, Basavanahalli, Rajanukunte, Narayanapura, Kadugodi and Varthur Junction. No completion date was given.
For the Sarjapur–Attibele end, this corridor is the live project; we found no separate 2026 widening notice for the Sarjapur–Attibele state highway. Homes along the corridor are covered in Anekal–Sarjapur–Airport–Nelamangala Road: ₹3,409 Cr, Homes and the ring-road comparison in Bangalore Ring Roads Compared: STRR vs PRR vs 134-km Road.
I own land on Sarjapur Road. What does widening mean for me?
If part of your plot falls in the road-widening line, the civic body usually takes it in exchange for TDR, not cash, and the 2025 inspection shows TDR handovers are what decide the service-road timeline. How TDR is issued and sold is explained in TDR for Road Widening in Bangalore 2026: How It Works. Setback and FAR relief after you give up land is covered in Road Widening in Bengaluru 2026: 2x FAR and 25% Setback Relief.
- Check whether your survey number touches the widening line on the approved plan before you build or sell.
- Keep your khata, sale deed and any surrender agreement together; TDR certificates are issued against the surrendered area.
- Ask the planning office for the current road width notified for your stretch rather than relying on what is built today.
What should flat buyers on Sarjapur Road check?
Wider roads help, but the corridor’s bigger long-term change is the proposed Phase 3A metro; Deccan Herald’s December 2025 report notes the planned elevated line along this road. Our status note is Sarjapur Road Metro (Phase 3A, Red Line): What Is Actually Sanctioned in 2026. For a project you are considering, check that its RERA-approved layout shows the building set back from the notified road width, and that the entry and frontage are not in a widening zone.