Bengaluru has three outer road projects at very different stages as of November 2026. The 282.3-km Satellite Town Ring Road (STRR) has 80 km open; the BDA's Bengaluru Business Corridor (the old Peripheral Ring Road) has one ₹3,348 crore package awarded; and the 134-km road from Attibele to Nelamangala via the airport got ₹1,118 crore more on 5 November, taking its cost to ₹3,409 crore.

Updated 8 November 2026. Each figure below is from the dated report named next to it.

The three roads side by side

  • Satellite Town Ring Road (STRR) · agency NHAI · 282.3 km in all, about 30–60 km from the centre through satellite towns · 80 km open (Dobbspet–Hoskote) · 20.9 km Hoskote–Tamil Nadu border under construction, with a phased opening targeted for December 2026 · 144.25 km (Obalapura–Kunagal–S. Mudugadapalli) awaiting central approval in June 2026, cost ₹4,921.57 crore (Deccan Herald, 12 June 2026; Oneindia, 23 October 2026).
  • Bengaluru Business Corridor / PRR-1 · agency BDA · phase 1 of 68.36 km in four packages (Construction World, 31 July 2026); Deccan Herald (16 June 2026) describes a 74-km project · package 1, Madavara (near BIEC) to Ballari Road, about 21 km, ₹3,348 crore including 10 years' maintenance, letter of acceptance issued in June 2026 · packages 2 and 3 (Ballari Road–Old Madras Road–Sarjapur Road) expected to be tendered by November 2026 (News Karnataka, 10 October 2026).
  • The 134-km road · agency PWD · Attibele, Sarjapur, Dommasandra, Gunjur, Varthur, Whitefield, Kempegowda International Airport, Nelamangala · sanctioned 2017 at ₹2,290 crore, revised to ₹3,409 crore with ₹1,118 crore approved on 5 November 2026 · the SH-35 section was taken up in 2019 with a 2021 deadline and includes a Varthur Kodi flyover (The Hindu, 5 November 2026).

STRR: the outermost ring

  • Open: Dobbspet to Hoskote, 80 km (Deccan Herald, 12 June 2026).
  • Next to open: Hoskote to the Tamil Nadu border, 21 km. NHAI plans to open it in phases from December, diverting traffic around the railway overbridge at Lingadeeramallasandra; the second girder there is expected by March 2027 (Oneindia, 23 October 2026).
  • Pending: 144.25 km in two packages: Obalapura (Nelamangala taluk) to Kunagal, 79 km, ₹2,642.4 crore; Kunagal to S. Mudugadapalli (Hosur taluk), 65.25 km, ₹2,279.17 crore, including a 3.85-km flyover through the Bannerghatta forest. DH reported in June that even if cleared that year, it was unlikely to be completed before 2029.
  • Status posts: STRR Hoskote–Hosur Stretch: Opening by December 2026? and STRR Road Map and Status: Hoskote–Hosur by December 2026.

Business Corridor (PRR-1): the BDA ring

  • Packages (Construction World, 31 July 2026): 1) Tumakuru Road–Ballari Road, 21 km; 2) Ballari Road–Old Madras Road, 17 km; 3) to Sarjapur Road, 14.6 km; 4) to Hosur Road, 15.6 km, with an elevated section.
  • Package 1 contractor: Shankara Narayana Constructions, letter of acceptance for ₹3,348 crore (Deccan Herald, 16 June 2026).
  • Timeline: the contract allows three years; the government has asked for two (BDA chairman, Construction World, 31 July 2026).
  • Villages and compensation: Peripheral Ring Road Bangalore Villages List 2026 (All 61). Work start: Bengaluru Business Corridor Work Begins: Madavara-Ballari.
  • It is a chain of upgraded state roads, not a new greenfield ring. The 5 November money is meant to speed up the Gunjur–Varthur stretch (The Hindu).
  • Why it matters for homes: it ties Sarjapur Road, Varthur and Whitefield to the airport side and on to Nelamangala.
  • Varthur details: Varthur Kodi Flyover 2026: ₹1,118 Cr Top-Up, SH-35 Status.

Which ring helps which area

No research house has published a figure for how much these roads move nearby prices, so we do not estimate one. A road helps most when it is open, not when it is announced.