The biggest NH-48 change for Gurgaon is the Kherki Daula toll plaza: it is being replaced by a new plaza at Kukdola, near Pachgaon, about 12–13 km away. NHAI floated the tender for a gantry-based, multi-lane free-flow (MLFF) system there, with technical bids due to open on 23 October 2026 and completion expected within three months of award. Toll collection at Kherki Daula is to stop once Kukdola starts. Separately, four flyovers and nine foot over bridges on the Gurugram–Jaipur stretch are under way, and a 3 km Narsingpur flyover is at concept stage.
Updated 17 November 2026. We checked Construction World's 20 July and 6 October 2026 reports on the Kukdola plaza, the 26 August 2025 foundation-stone reports (All India Radio and IANS), the February 2026 Narsingpur and Rajiv Chowk proposals, the July 2026 NH-48 safety audit follow-up and PIB's 1 July 2026 Cabinet note. We found no official opening date for Kukdola as of today.
Is Kherki Daula toll plaza shifting, and where to?
- May 2025: the Union road transport ministry approved moving the plaza to Pachgaon.
- After local objections the site moved to Kukdola revenue estate near Sehrawan, about 13 km from the current plaza (Construction World, 20 July 2026). The new plaza is planned with 14 lanes and FASTag readers on gantries instead of toll booths.
- 20 July 2026: NHAI said construction of the plaza and administrative building would start the following month; HSIIDC, GMDA and nearby security agencies had given consent, and building was expected to take about six months.
- 6 October 2026: NHAI floated the MLFF tender. Technical bids were due to open on 23 October; the contractor must install two gantries in each direction about 350 m downstream of the plaza, with number-plate cameras and RFID readers, and finish within three months of award.
- Bijwasan (Dwarka Expressway) and Kukdola will operate as integrated fee plazas, with charges set by NHAI's annual fee notification.
What is the Kherki Daula toll rate now?
From 1 April 2026 a car pays ₹100 one way at Kherki Daula (up from ₹80) and ₹150 for a return journey; a 50-trip monthly pass costs ₹3,320 and the local resident pass ₹350. A community toll wiki still lists 2025 rates and a ₹105 figure, so confirm on your FASTag statement. These rates apply until the plaza moves.
Which flyovers and fixes are approved on NH-48?
- Four flyovers and nine FOBs: foundation stones laid on 26 August 2025 by Minister of State Harsh Malhotra, at Panchgaon Chowk, Rathiwas, near the Hero company and Sahlawas, plus nine foot over bridges on the Gurugram–Kotputli–Jaipur section, estimated at ₹282 crore (IANS; All India Radio confirms four flyovers and nine FOBs).
- Narsingpur flyover (proposal): NHAI proposed a 3 km flyover at Narsingpur, between the Hero Honda Chowk flyover and the Dwarka Expressway cloverleaf, where four lanes narrow to three. GMDA's CEO directed a DPR; NHAI called it conceptual (Construction World, 2 February 2026).
- Rajiv Chowk (proposal): two elevated grade separators, plus a left-turn ramp from NH-48 to NH-248A towards Sohna and a right-turn ramp back towards Delhi.
- Safety fixes: a May 2026 joint inspection of an 11 km stretch found about 40 deficient spots; NHAI said 33 were fixed in May–June 2026, with further work planned at Signature Towers, Jharsa, Sector 31 service roads and MDI Chowk (Construction World, 20 July 2026).
- Delhi side: the Cabinet approved a Shiv Murti–Vasant Kunj tunnel on 1 July 2026, and NHAI is proposing an AIIMS–Mahipalpur elevated corridor (PIB).
- Hero Honda Chowk–Umang Bhardwaj Chowk elevated road: see Hero Honda Chowk to Umang Bhardwaj Chowk Elevated Road.
Why is NH-48 in Gurugram so congested?
Volume and merging. PIB noted in March 2023 that NH-48 carries more than 3 lakh vehicles a day. NHAI's February 2026 review named the merge from four lanes to three near Narsingpur, poor service roads, unauthorised access points and heavy local traffic as the main causes. The Dwarka Expressway, opened end to end in August 2025, gives an alternative for Delhi-bound trips from western sectors; see Dwarka Expressway, Gurgaon.
What does this mean for Sectors 37C/37D, 9/10 and Manesar?
- Sectors 37C and 37D sit by the Kherki Daula end of the Dwarka Expressway and NH-48. Removing the plaza at Kherki Daula should ease the bottleneck at this junction once Kukdola runs. See Sector 37c Gurgaon, Gurgaon, Sector 37d Gurgaon, Gurgaon and Sector 37C Gurgaon: Buyer's Guide 2026 — Prices, Projects and Connectivity. A registered project here is Manasum Varishta at Signature Global Sarvam.
- Sectors 9 and 10 (old Gurgaon, west of NH-48): their NH-48 access is via Hero Honda Chowk and the Narsingpur stretch, where the flyover is proposed.
- Manesar and IMT Manesar: the Panchgaon Chowk flyover sits on the Manesar side; Kukdola lies further south near Sehrawan, so check where the gantries fall on your daily route once NHAI publishes the plaza location. See Manesar, Gurgaon and Imt Manesar.
Dated status list
- 17 March 2023 — NH-48 traffic over 3 lakh vehicles a day (PIB).
- May 2025 — plaza shift to Pachgaon approved.
- 26 August 2025 — foundation stones for four flyovers and nine FOBs.
- 2 February 2026 — Narsingpur flyover and Rajiv Chowk ramps proposed (concept).
- 1 July 2026 — Shiv Murti–Vasant Kunj tunnel approved; AIIMS–Mahipalpur corridor proposed.
- 20 July 2026 — Kukdola site finalised; 33 of 40 deficient spots fixed.
- 6 October 2026 — Kukdola MLFF tender floated; bids opened from 23 October.