The Greater Southern Peripheral Road (Greater SPR or GSPR) is a proposed new road south of Gurgaon’s existing SPR. HSVP is acquiring about 670 acres in 14 villages in two phases: Gurugram–Faridabad Road to Sohna Road, then Sohna Road to the Delhi–Jaipur highway (NH-48) near Manesar. The latest step: Haryana has moved to finalise about ₹986 crore in compensation for roughly 160 acres in six villages, at ₹4.92 crore to ₹8.25 crore an acre, with another 116 acres already transferred for TDRs (GoodReturns/PTI, 14 November 2026; Business Today, 17 November 2026). No construction start date has been announced.
Updated 18 November 2026. We checked the latest compensation reports, the HSVP phase plan and village list, the June 2026 land-cost report, Swarajya’s Budget 2026 report on the existing SPR’s elevated road, and the 2026-27 collector rates for the same villages.
What is the Greater SPR route?
Some pages describe the route as ‘IMT Manesar to Ambience Mall’ or ‘MG Road to Pachgaon’. Those are wider connectivity descriptions, not the alignment HSVP set out. Togetherbuying, citing the 2026-27 budget speech, gives about 21 km subject to final alignment; we could not open the speech to confirm it. No width or design has been published.
- Phase 1, about 276 acres: Gurugram–Faridabad Road to Sohna Road. Villages: Bahrampur (Behrampur), Ullawas, Kadarpur, Maidawas, Dhumaspur (written ‘Ghamaspur’ in one report) and Badshahpur.
- Phase 2, about 394 acres: Sohna Road to the Delhi–Jaipur highway. Villages: Aklimpur, Tikli, Sakatpur, Shikohpur, Naurangpur, Bar Gujjar, Manesar and Nainwal.
- Total: 276 + 394 = 670 acres in 14 villages (Daily Jagran, 17 December 2025). Togetherbuying says 671 acres in 14 villages were notified (11 August 2026).
How is the Greater SPR different from the existing SPR?
The existing SPR is already built and runs past Vatika Chowk on Sohna Road towards NH-48. Its next stage is an elevated road: Swarajya reported a ₹2,900 crore, 14 km plan in the Haryana Budget 2026, made of a 5.1 km stretch from Vatika Chowk to NH-48 (about ₹1,065 crore) and an 8.84 km stretch from Vatika Chowk to Ghata (about ₹1,846 crore) (3 March 2026). The Greater SPR is a separate, new road further south, through villages such as Badshahpur, Tikli and Naurangpur. For the SPR, see Southern Peripheral Road, Gurgaon, Southern Peripheral Road area guide and SPR Elevated Road After 18 Nov 2026: What Happens Next. For all ring roads, Southern Peripheral Road Map Gurgaon: NPR, SPR and CPR Explained.
Greater SPR timeline: what has happened so far?
- November 2025: Section 6 notification issued for Phase 1 land (Daily Jagran, 17 December 2025).
- December 2025: HSVP said Phase 1 acquisition would be done in four to five months and set February 2026 for the Phase 2 Section 6 notification (same report).
- March 2026: revival announced in the Haryana Budget 2026-27, per Togetherbuying (11 August 2026).
- June 2026: News24 reported the whole land exercise could cost nearly ₹6,000 crore, with ₹6–8 crore an acre and up to ₹11 crore in premium spots (30 June 2026).
- 14–17 November 2026: about ₹986 crore of compensation being finalised for about 160 acres in six villages; 116 acres already transferred through TDRs (GoodReturns/PTI; Business Today).
- Not yet announced: construction tender, contractor, start date or completion date.
How much compensation per acre, and how does it compare with collector rates?
The November 2026 per-acre rates, set against the 2026-27 collector rate for irrigated (chahi) farmland in the same village:
- Badshahpur: compensation ₹8.25 crore an acre; collector rate ₹7.00 crore (Tehsil Badshahpur).
- Maidawas: ₹6.17 crore; collector ₹6.60 crore (Tehsil Badshahpur).
- Behrampur: ₹5.26 crore; collector ₹3.96 crore (Tehsil Badshahpur).
- Dhumaspur: ₹5.19 crore; collector ₹2.75 crore (Tehsil Badshahpur).
- Ullawas: ₹4.96 crore; collector ₹9.07 crore for chahi land in the ‘Ullahwas’ row of Tehsil Wazirabad.
- Kadarpur: ₹4.92 crore; collector ₹7.25 crore for chahi land in the Kadarpur row of Tehsil Wazirabad.
The reports do not say how the per-acre figures were worked out, so the gap with collector rates in Maidawas, Ullawas and Kadarpur cannot be explained from them. Collector rows can also differ by zone inside a village. Landowners should rely on the award itself.
What does the Greater SPR mean for home buyers?
For homes along the existing road, see Southern Peripheral Road Spr and Manesar, Gurgaon.
- It is a land-acquisition-stage project. Value a home on today’s roads, not on a road with no start date.
- Sectors near Phase 1 villages (Badshahpur, Behrampur, Kadarpur, Maidawas) are on the Golf Course Extension and SPR side; see Badshahpur Gurgaon: Sectors, Pin Code, Tehsil and RERA Projects.
- Phase 2 villages (Naurangpur, Shikohpur, Manesar) sit under New Gurgaon Sectors 77–80; see New Gurgaon, Gurgaon and Shikohpur Gurgaon: Village Sectors, Pin Code and Land Guide.
- If you own land on the alignment, read the HSVP award, check the khasra in the notification and keep your jamabandi current.
- Check a project’s HRERA registration before booking. A RERA-registered example in a Phase 2 village: Godrej Aria.