For a house or builder floor on a plot in a DTCP-licensed colony in Gurgaon, the occupation certificate (OC) is issued by your architect under self-certification, within 8 working days of your application, under DGTCP's standard procedure of 16 November 2022. For a plot in an HSVP sector, HSVP certifies the OC; its service list gives 5 days for ‘OC certification (residential)’, and applications run on HSVP's OBPAS portal. Since 8 December 2025, the Haryana Building Code treats all residential plotted buildings up to 16.5 m high as ‘low risk’, which is why self-certification applies.
Updated 17 November 2026. We read the Haryana Building Code 2017 with amendments up to 13 August 2026, DGTCP's memo no. Misc-2484-D/2022/34493-94, TCP's policy index on independent-floor registration, HSVP's Right to Service list and the OBPAS portal page. For group-housing projects, use our separate OC/CC checks at Occupation and Completion Certificates in Haryana: What to Check Before You Take Possession.
Who issues the OC for your plot?
- Plot in a DTCP-licensed residential plotted colony (including DDJAY): the architect, under self-certification, in Form BRS-V. DGTCP made the architect the ‘competent authority’ for these OCs from 16 November 2022.
- Plot in an HSVP sector: HSVP's estate office, ‘OC certification (residential)’ in 5 days; ‘Occupancy Certificate’ is a service on HSVP's OBPAS portal, which has run all new applications since 1 October 2025.
- Buildings outside the low-risk class (for example over 16.5 m): an empanelled architect under third-party certification (Code 4.10), not self-certification.
- Group housing (apartments): not covered here; the developer applies for the project OC.
What does the architect check before issuing the OC?
DGTCP's 2022 procedure sets out these steps. Code 4.11 of the Building Code adds the forms.
- The owner applies in writing to the architect (Form BRS-III with completion drawings and a completion certificate in Form BRS-IV).
- The architect confirms in writing that he has no show-cause notice or blacklisting by any government agency.
- Papers: approved building plans, deviations marked on as-built drawings, photographs of front, side and rear setbacks and of internal finishing (with a CD), a structural stability certificate and the self-certification.
- A filled Annexure-R: plot area, permissible and achieved FAR floor by floor (basement, stilt/ground, first to fourth floor), setbacks, room sizes, toilets, staircase, cut-outs, railings, fittings and debris removal.
- A certificate from the HSVP Executive Engineer on services.
- Composition charges for compoundable deviations paid under the composition policy of 28 October 2022, with the online receipt (Annexure B).
- A No Dues Certificate from the competent authority (Code 4.11).
- If there is a non-compoundable violation or unfinished work, the architect must not issue the OC.
- Time limit: 8 working days from the owner's application. The architect then files the case with the District Town Planner within 3 working days.
How much must be built before you can get an OC?
For residential plots, Code 4.11(4) requires at least 25% of the total permissible ground coverage to be built, with one habitable room, a kitchen and a toilet from the approved plan completed. Code 4.11(5) says no OC is issued until construction debris is cleared from the site and surroundings. Until the OC is issued, nobody may occupy the building.
Can a self-certified OC be withdrawn?
Yes. The District Town Planner must check 10% of the OCs received from architects each month within 7 working days, and the Senior Town Planner may randomly check 5%. If a non-compoundable violation or an incomplete building is found, the DTP can issue a show-cause notice, blacklist the architect, withdraw the OC and recommend to the registration authority that no floor or building on that plot be registered. Code 4.11(3) also says violations found later cancel the OC until they are removed.
That is the buyer's risk in one line: a floor sold on a weak OC can become unregistrable. Ask for the OC early and check it.
Why does a floor-wise OC matter for separate registry?
Independent floors are sold and registered as separate units. TCP's policy index carries instructions on registering independent floors in licensed colonies (27 March 2009, 25 August 2009, 13 February 2013) and on registering a fourth floor as a separate dwelling unit (7 March 2019). HSVP lists ‘floor-wise registration (division of property, residential)’ as a 7-day service. The Building Code allows one dwelling unit per floor and a maximum of four per plot, as re-worded on 13 August 2026. A floor buyer should see the OC that covers the floor being bought, the approved plan showing it as a separate dwelling unit, and, for HSVP plots, the floor-wise registration.
For more checks on floors, read Is a Builder Floor Legal in Gurgaon? 2026 Checklist and the stilt-plus-four update at Stilt Plus 4 Latest News November 2026: HC Hearing Explained.
What does an OC cost, and how do you check one online?
We found no flat OC fee on the official pages we opened. The costs you will see are composition charges for compoundable deviations (as per the composition policy), labour cess and malba charges (HSVP's OBPAS fee calculator lists labour cess, malba, scrutiny, purchasable FAR and compounding), plus the architect's professional fee. Code 4.8 of the Building Code requires an online e-register of building-plan and occupation applications, permissions given or deemed and refusals, open to the public on the departmental website. Ask the seller for the OC number and date, and check it with the DTP office or HSVP estate office.
OC checklist for a Gurgaon house or floor buyer
- Identify the authority: HSVP sector or DTCP-licensed colony.
- OC copy (Form BRS-V for self-certified cases) with the date of the owner's application referred in it.
- Approved building plan matching the floors actually built.
- Composition receipt for any compoundable deviation.
- Services certificate from HSVP's Executive Engineer (licensed colonies).
- For HSVP plots: OC certification by the estate office and floor-wise registration.
- No pending show-cause notice against the plot or OC withdrawal on record.
- Stamp duty and registration: see Gurgaon stamp duty calculator; prices by sector at Gurgaon.