Yes, the Dwarka Expressway is complete and open end to end. The Prime Minister opened the 19 km Haryana section on 11 March 2024 and the 10.1 km Delhi section on 17 August 2025, so all four packages of the roughly 29 km road between Shiv Murti (NH-48, near IGI Airport) and Kherki Daula in Gurugram are now in use. What is still being built is around it: service roads, new interchanges and a tunnel link towards South Delhi.
Updated 17 November 2026. We checked the PIB releases for both inaugurations, the July 2022 and March 2023 PIB descriptions of the project, the 1 July 2026 Cabinet approval for the Vasant Kunj tunnel, the Ministry's August 2023 response to the CAG audit (via All India Radio), and dated 2026 reports on service roads, interchanges and tolling.
Which sections are open, and when did each open?
The road was built in four packages. PIB gives the lengths and opening dates below. The Haryana and Delhi figures add up to about 29 km, which matches the 29 km total the Ministry gave in July 2022.
- Package I (Delhi): Shiv Murti intersection to the Road Under Bridge at Dwarka Sector 21, 5.9 km — opened 17 August 2025.
- Package II (Delhi): Dwarka Sector 21 RUB to the Delhi–Haryana border, 4.2 km — opened 17 August 2025; it links directly to Urban Extension Road-II.
- Package III (Haryana): Delhi–Haryana border to the Basai Rail-over-Bridge, 10.2 km — opened 11 March 2024.
- Package IV (Haryana): Basai ROB to Kherki Daula, 8.7 km — opened 11 March 2024.
Is Dwarka Expressway in Delhi or Gurgaon, and is it under NHAI?
Both. About 19 km is in Haryana (Gurugram district) and 10.1 km is in Delhi. In Haryana it is also called the Northern Peripheral Road (NPR), the name used in the Gurgaon master plan; the Ministry's 2022 release uses both names. For the Southern Peripheral Road that runs parallel to the south, see Southern Peripheral Road, Gurgaon.
It is a National Highway built and run by NHAI under the Ministry of Road Transport and Highways. PIB's March 2023 release says NHAI was building it to bypass NH-48 between Shiv Murti and Kherki Daula, and the July 2026 Cabinet note numbers it NH-248BB. Local service roads alongside it in Gurugram are being built by GMDA.
Is it 8 lanes, 14 lanes or 16 lanes?
Official descriptions differ, and this is where most confusion comes from. They describe the same road counted in different ways:
- 11 July 2022 (PIB, MoRTH): ‘a 16-lane access-controlled highway with provision of minimum 3-lane service road on both sides’.
- 17 March 2023 (PIB, MoRTH): ‘fully access controlled grade separated 14 lane Expressway’ with an 8-lane elevated structure and an 8-lane tunnel of about 4 km.
- 10 and 11 March 2024 (PIB, PMO): ‘the 8 lane Dwarka Expressway’, described as India's first elevated road built on a single pier.
- Our reading: the main expressway is 8 lanes (largely elevated in Haryana); the 14- and 16-lane counts add the service roads on both sides. The 3.6 km, 8-lane urban road tunnel and four-level interchanges were described in the 2022 release.
What did it cost, and what is the cost per km?
PIB puts the Haryana section at about ₹4,100 crore and the Delhi section at about ₹5,360 crore. Together that is about ₹9,460 crore for about 29 km, or roughly ₹326 crore per km on our arithmetic. In 2022 the Ministry had given a total of ₹9,000 crore for 29 km.
The section figures differ a lot per km: about ₹216 crore per km in Haryana (₹4,100 crore ÷ 19 km) and about ₹531 crore per km in Delhi (₹5,360 crore ÷ 10.1 km). The Delhi part includes the tunnel and the multi-level interchange at Shiv Murti, which explains much of the gap.
The ‘₹250 crore per km’ figure in many articles comes from the CAG's 2023 audit of Bharatmala Phase-I, which compared it with a CCEA-approved ₹18.2 crore per km. The Ministry responded on 14 August 2023 that ₹18.2 crore was a normative average used to frame the whole Bharatmala programme, that costs vary with design, terrain and location, and that the average for special projects with long bridges, viaducts and tunnels is ₹152 crore per km. The two figures measure different things, so they should not be read as a like-for-like overrun.
What is still pending or being added in 2026?
- GMDA service roads: 27 km of two-lane, 7.5 m service roads on both sides, cost ₹99 crore, were 70% complete on 5 June 2026 with a September 2026 target (Swarajya, quoting GMDA). We found no completion notice as of 17 November 2026.
- Global City / Vision City interchange: a four-lane underground trumpet interchange near the Pataudi Road junction, estimated at ₹923 crore and funded by HSIIDC, about 30 months to build once work starts (Swarajya, 7 March 2026, citing The Times of India and an NHAI official).
- Tunnel to Vasant Kunj: the Cabinet approved a 6-lane, 8.1 km NH-148AE link from the Shiv Murti interchange to Nelson Mandela Marg on 1 July 2026, at ₹6,969.67 crore on Hybrid Annuity Mode, with 3.14 km of tunnel (PIB). An AIIMS–Mahipalpur elevated corridor is ‘proposed’. More in Dwarka Expressway New Links 2026: Tunnel, Katra, AIIMS Road.
- Tolling: NHAI's tender for multi-lane free-flow tolling at the new Kukdola plaza (replacing Kherki Daula) says Bijwasan on the Dwarka Expressway and Kukdola will run as integrated fee plazas (Construction World, 6 October 2026). For passes and local rates see Dwarka Expressway Toll Pass 2026: Annual Pass, Rules.
Dated changelog
- 11 July 2022 — Ministry describes the 29 km, ₹9,000 crore project (19 km Haryana, 10 km Delhi).
- 17 March 2023 — NH-48 diversion between Mahipalpur and Rajokari for construction; NH-48 carries more than 3 lakh vehicles a day (PIB).
- 14 August 2023 — Ministry responds to CAG cost-per-km observation.
- 11 March 2024 — Haryana section (19 km) inaugurated.
- 17 August 2025 — Delhi section (10.1 km) inaugurated; road open end to end.
- 7 March 2026 — Global City trumpet interchange reported as cleared.
- 5 June 2026 — GMDA service roads 70% complete.
- 1 July 2026 — Cabinet approves Shiv Murti–Vasant Kunj tunnel.
- 6 October 2026 — Kukdola MLFF toll tender floated; Bijwasan to be integrated.
What it means for Gurgaon home buyers
The corridor itself is no longer a ‘future’ item. Sectors 99 to 115, 36A, 37C/37D and 88–89 now front a working expressway; what still varies sector by sector is local access through service roads and sector roads. Check the nearest exit and service road on the ground before buying. Sector pages such as Sector 106 Gurgaon, Gurgaon and Sector 113 Gurgaon, Gurgaon, the hub at Dwarka Expressway, Gurgaon and rates at Dwarka Expressway help compare. Registered projects on the corridor include Godrej Meridien and Tata La Vida; see Dwarka Expressway for more.