To get a new DHBVN electricity connection in Gurgaon, apply on econnection.dhbvn.org.in using “Apply for New Connection”, choose “New connection”, upload proof of ownership, ID, a photo and the wiring test report, and pay the charges within 7 days or the application is cancelled. Under DHBVN's published schedule, a 5 kW single-phase home pays roughly ₹7,400–7,550 in one-time charges (deposit, meter and service line), before any network work. DHBVN's Right to Service notification says the connection should be released within 30 days of a complete application and payment when the existing network can carry it.

Updated 18 November 2026. We opened DHBVN's e-connection portal and its live application form, the “Charges for New Connections”, “Documents required”, “Timelines” and “Connected load calculation” PDFs, DHBVN's Right to Service (RTS) notification, and Sales Circular D-06/2026, which carries the HERC tariff for FY 2026-27. The fee examples below are our arithmetic on those official figures.

Who applies for an individual DHBVN connection?

You apply directly to DHBVN if you own a house, a plot, a shop or a separately registered builder floor. Each floor of a builder floor can have its own meter in the floor owner's name, because the floor owner holds a registered deed for that floor (see Builder Floor Registry in Gurgaon: Floor-Wise Registration 2026).

Flats in most group-housing societies are different. The society or developer takes one bulk “single-point” connection and bills residents through sub-meters, so a flat owner does not apply to DHBVN at all. That case is covered in Single Point Connection Gurgaon: DHBVN Society Power Rules 2026. For a newly built house, keep the occupation certificate ready too; see Occupation Certificate DTCP Haryana: House & Floor OC in Gurgaon.

How do you apply for a DHBVN new connection online?

The form at econnection.dhbvn.org.in (OnlineApplyNewCon page) asks for these details, in this order:

  • Applicant type “Consumer”, Application For “New connection” (the same form also handles Reconnection, Extension of Load, Reduction of Load and Change of Name), and category “Domestic (DS)” for a home.
  • Your Family ID (Parivar Pehchan Patra) or Aadhaar, then choose the member and validate the OTP.
  • Circle and sub-division (there is a link if you don't know your sub-division), and type of supply: permanent or temporary.
  • Full supply address, mobile and email, plus optional Property ID and PPP ID fields.
  • Connected load in kW, purpose of supply, and smart meter type: the form offers PREPAID or POSTPAID.
  • Uploads: your photo (under 50 KB), proof of ownership and proof of identity (each under 500 KB), and the test report of the internal wiring.
  • Submit, download the application and check every column. Then pay the charges within 7 days. The form says that if you choose offline payment, you pay at the sub-division, which then contacts you.

Which documents does DHBVN accept?

DHBVN's “Documents required” PDF lists two kinds of proof:

  • Proof of ownership or legal occupation (any one): sale deed, allotment letter, lease deed or rent deed in the applicant's name; or a property tax receipt or tax demand notice, with a rent deed or other proof of tenancy if you are a tenant.
  • Proof of identity (any one): voter ID, passport, driving licence, ration card, PAN card, Aadhaar, or a photo ID issued by a government agency.
  • For a company, trust or institution: an authorised signatory plus a board resolution or authority letter.
  • A wiring test report: the declaration on the form says the internal wiring has been done and tested by a licensed electrical contractor and that the test certificate is available.

If you have no ownership papers, for example in a slum or unauthorised colony, DHBVN Sales Circular D-40/2023 provides an affidavit and indemnity bond. That affidavit states that the connection gives no ownership or legal-occupancy right and that the meter is there only for billing. A buyer should never treat an electricity bill as proof of title.

What are the DHBVN new connection charges?

These are the domestic charges from DHBVN's “Charges for New Connections” PDF on the e-connection portal. They exclude augmentation (network) work, which is charged separately if your area needs it.

  • Application processing fee (non-refundable): ₹50 for a load up to 2 kW; ₹25 per kW above 2 kW (maximum ₹20,000).
  • Advance Consumption Deposit (ACD), refundable: ₹750 per kW or part of a kW for domestic supply.
  • Meter security: ₹600 for a single-phase meter; ₹1,430 for a three-phase whole-current meter.
  • Meter box (MCB): ₹250 single-phase; ₹350 three-phase.
  • Meter testing: ₹90 single-phase; ₹330 three-phase. Meter installation: ₹100 single-phase; ₹200 three-phase.
  • Fixed service connection charge (up to 150 m of line): ₹200 per kW single-phase up to 2 kW; ₹500 per kW single-phase above 2 kW and up to 5 kW; ₹1,000 per kW three-phase above 5 kW.
  • Extra line beyond 150 m: ₹175 per metre for loads up to 50 kW.

One inconsistency in DHBVN's own PDF: the processing-fee table says ₹25 per kW above 2 kW, but the worked example under it charges ₹50 × 5 = ₹250 for 4.5 kW. Your demand notice decides. That is why we give the totals below as a range.

  • 5 kW single-phase home: ACD ₹3,750 + meter security ₹600 + MCB ₹250 + testing ₹90 + installation ₹100 + service connection ₹2,500 = ₹7,290, plus a processing fee of ₹125 (table) or ₹250 (example). Total about ₹7,415–7,540.
  • 8 kW three-phase home: ACD ₹6,000 + meter security ₹1,430 + MCB ₹350 + testing ₹330 + installation ₹200 + service connection ₹8,000 = ₹16,310, plus a processing fee of ₹200 or ₹400. Total about ₹16,510–16,710.

How much load should you apply for?

DHBVN's connected-load PDF sets the domestic counting rules: 11 W per light point and 60 W per fan point (each counted at 50%, rounded up); full rating for up to two ACs and two geysers, or 70% of total rating if you have more; 200 W per 5 A socket and 1,000 W per 15 A socket (one-third counted). Load also sets your tariff band. Under the FY 2026-27 schedule, homes up to 5 kW pay ₹2.95 per unit for the first 150 units, while homes above 5 kW pay ₹6.50 per unit from the first unit plus a ₹75 per kW monthly fixed charge. Don't over-declare.

How long does DHBVN take to release a connection?

DHBVN's “Timelines” PDF lists these limits for LT (ordinary home) connections:

  • Acknowledge the complete application, or point out what is missing: within 2 days.
  • Inspect the premises: within 7 days of a complete application.
  • Issue the demand notice: 7 days. The notice stays valid for 2 months for LT connections.
  • Test your installation: 5 days. Issue the service connection order: 5 days.
  • Complete the work: 10 days. Release the connection after the work is done: 3 days.
  • DHBVN's RTS notification caps the total at 30 days where supply is feasible from the existing network, and 71 days for LT connections that need network expansion.

How do you check DHBVN new connection status?

On the e-connection portal, use “Real time status of application DHBVN” (PublicView page) or the applicant tracking login with your application number. DHBVN's website also has a “New Connection Status” page. For help, call 1912 or 1800-180-4334, message WhatsApp 8813999708, or email dhcomplaints@dhbvn.org.in, which the portal lists for new-connection problems.

If the RTS deadline passes, escalate. DHBVN's RTS notification names the SDO (Operation) as the designated officer, with first and second appeals to the XEN and SE (Operation). You can apply through the Antyodaya Saral portal or the e-connection portal. A bill or supply dispute that stays unresolved can go to the Consumer Grievance Redressal Forum.