On the HRERA Gurugram register, one DLF residential registration is due in 2026–27: Independent Floors at DLF Gardencity Enclave, Sector 93 (RERA-GRG-1060-2022), with a completion date of 19 August 2027. The next DLF dates are two more Sector 93 registrations on 30 October 2028, while DLF's high-rise launches (The Arbour, Privana South, Privana West, The Dahlias) are registered for March 2030 to December 2031.

Updated 20 November 2026. We read every DLF-group row on the HRERA register (DLF Ltd, DLF Home Developers, DLF Utilities and other DLF companies), noted the completion date and whether an occupation certificate (OC) record is uploaded, and opened the HRERA forms for the main projects. DLF's own pages were used for its stated targets.

DLF projects in Gurgaon by HRERA date: summary

Format: project — sector — HRERA no. — HRERA completion or status — OC record.

  • Independent Floors at DLF Gardencity Enclave — 93 — RERA-GRG-1060-2022 — 19 Aug 2027 — none yet
  • DLF Gardencity Enclave (plotted colony) — 93 — RERA-GRG-1008-2022 — 30 Oct 2028 — OC/CC/PCC record uploaded
  • Independent Floors at DLF Gardencity Enclave Phase 2 — 93 — RERA-GRG-1223-2022 — 30 Oct 2028 — none yet
  • The Arbour (registered as The Sixty Three) — 63 — RERA-GRG-1138-2022 — 31 Mar 2030 — none yet
  • DLF Privana South — 76/77 — RERA-GRG-1406-2023 — 30 Jun 2031 — none yet
  • DLF Privana West — 76/77 — RERA-GRG-1540-2024 — 31 Dec 2031 (DLF target: December 2028) — none yet
  • The Dahlias — 54 (DLF 5) — RERA-GRG-1690-2024 — 31 Dec 2031 — none yet
  • Already with OC/CC/PCC records: The Grove (DLF 5, RERA-GRG-941-2021), Independent Floors at DLF Alameda, Sector 73 (RERA-GRG-898-2021), DLF Gardencity (RERA-GRG-834-2021) and its Sector 91/92 floors, and DLF City Phase I–IV floor registrations

Independent Floors at DLF Gardencity Enclave, Sector 93

RERA-GRG-1060-2022, certificate GGM/603/335/2022/78 dated 17 August 2022, DLF Ltd as collaborator under licence 94 of 2021. The HRERA form covers 97 plots of 132.6 to 150 sq m on 3.57 acres, with floors of 73.95 to 83.61 sq m carpet listed, and construction from 29 September 2022. HRERA completion: 19 August 2027. This is DLF's only residential registration in Gurgaon due in 2026–27. Our page: Independent Floors At DLF Gardencity Enclave

DLF Gardencity Enclave, Sector 93

RERA-GRG-1008-2022, certificate GGM/550/282/2022/25 dated 11 April 2022, the plotted colony itself: 367 plots, 339 of them 150 sq m, on 26.92 acres under licence 94 of 2021. HRERA completion: 30 October 2028. The register row already shows an OC/CC/PCC record for the colony. Our page: DLF Garden City Enclave

Independent Floors at DLF Gardencity Enclave Phase 2, Sector 93

RERA-GRG-1223-2022, certificate GGM/657/389/2023/01 dated 2 January 2023, DLF Ltd. HRERA completion: 30 October 2028. Sector guide: Sector 93 Gurgaon, Gurgaon

The Arbour, Sector 63

Registered on HRERA as ‘The Sixty Three’, RERA-GRG-1138-2022 (GGM/671/403/2023/15, 23 January 2023), promoter DLF Home Developers; a document uploaded on 16 February 2023 records the change of name to The Arbour. The form lists 1,137 apartments of 209.51 sq m carpet (about 2,255 sq ft) in towers A to E on 25.09 acres, with construction from 1 September 2022. HRERA completion: 31 March 2030. Our page: DLF The Arbour

DLF Privana South, Sectors 76/77

RERA-GRG-1406-2023 (GGM/772/504/2023/116, 18 December 2023). The form lists seven towers with 1,099 apartments of 198.48 sq m and 14 of 330.88 sq m carpet on 25.15 acres, part of a 116.3-acre licence (219 of 2023). HRERA completion: 30 June 2031. Aggregator pages show dates from March 2026 to December 2028; the registered date is June 2031. Our page: DLF Privana South

DLF Privana West, Sectors 76/77

RERA-GRG-1540-2024 (RC/REP/HARERA/GGM/819/551/2024/46). DLF's page describes five G+38 towers of 4 BHK homes on 12.57 acres, says the project is sold out and gives possession as ‘December 2028’. The HRERA completion date is 31 December 2031, so DLF's target is three years inside the registered outer date. Our page: DLF Privana West

The Dahlias, Sector 54

RERA-GRG-1690-2024 (GGM/872/604/2024/99, 4 October 2024), DLF Ltd, R16, DLF 5. HRERA completion: 31 December 2031. Our page: DLF The Dahlias

Which DLF projects in Gurgaon are ready to move?

If you need a DLF home sooner than 2027, the HRERA register shows OC/CC/PCC records on these DLF registrations. Ask the seller for the certificate covering the exact tower or floor.

Which DLF projects come after 2031?

  • Privana Enclave (plots), Sectors 76/77 — RERA-GRG-2236-2026 — HRERA completion 30 April 2033 — DLF Privana Enclave
  • The Aureva (senior living), Sector 63 — RERA-GRG-2265-2026 — 31 October 2033 — DLF The Aureva
  • DLF Privana North, Sectors 76/77 — RERA-GRG-1781-2024 — 30 September 2034 — DLF Privana North
  • DLF's builder page with all projects: Gurgaon; delivery history: Track Record

What do ready DLF homes in New Gurgaon cost?

Square Yards' New Gurgaon ready-to-move list (approx, portal, opened 20 November 2026) shows these starting prices for DLF projects that have an HRERA number:

  • DLF Ultima Phase II, Sector 81 (RERA-GRG-201-2019): 3 BHK of 1,912–2,132 sq ft and 4 BHK of 2,549–2,824 sq ft from about ₹3.23 crore, ₹16,900 per sq ft — DLF The Ultima
  • DLF Garden City Independent Floors, Sector 92 (Gardencity floor registrations listed above): 4 BHK of 2,864–3,480 sq ft from about ₹6.30 crore, ₹22,000 per sq ft
  • DLF Garden City Plots, Sector 91 (DLF Gardencity, RERA-GRG-834-2021): plots of 2,700–6,386 sq ft from about ₹6.85 crore, ₹25,368 per sq ft
  • Square Yards also tags ‘DLF Privana, Sector 76’ ready to move from about ₹4.34 crore; on HRERA, Privana South and Privana West are registered to 2031, so check which Privana registration a listing refers to.

Why do DLF's target dates differ from HRERA dates?

Under Section 4(2)(l)(C) of the RERA Act, a promoter registers the period within which it undertakes to complete the project; many builders register a cautious outer date and market an earlier target. DLF's Privana West page shows December 2028 against a registered 31 December 2031. Your agreement for sale fixes your own date, and Section 18 of the Act works from that agreement. The registered date is the one you can check independently.

How do I check a DLF project's possession status on HRERA?