The MRTS (Chennai Beach to St Thomas Mount) has not yet passed to Chennai Metro Rail. The Railway Board approved the draft agreement by a circular dated 12 August 2026; under it, Southern Railway hands over station assets and routine operations within 90 days of the MoU being signed, and core train operations over a 24-month transition. As of 8 November 2026 we found no report that the final MoU has been signed, so the 90-day clock has no confirmed start date.

Updated 8 November 2026. We read the August 2026 reports on the Railway Board decision in DT Next, Swarajya and Metro Rail News, the December 2025 report on the state's stake purchase, and the station list. Commuters and home buyers along the Velachery–Mount line affect 21 stations; the asset transfer covers 19 of them.

What the Railway Board approved, and when

Swarajya reported on 19 August 2026 that a Railway Board circular dated 12 August 2026, addressed to the General Manager of Southern Railway, cleared the transfer. It says the draft MoU was signed in May 2026 by Southern Railway and the Tamil Nadu government. Metro Rail News (19 August 2026) gives the same sequence. The proposal itself dates to a letter of 27 January 2011 from the then Chief Secretary (DT Next, 19 August 2026).

DT Next's report of 19 August 2026 sets out the terms. These are terms of the draft as approved, not of a signed final agreement:

  • Within 90 days of signing: assets and general operation and maintenance move to the state side. The state must deploy staff for ticketing, security and other general functions in that period.
  • For 24 months from the MoU date: Southern Railway keeps running core train operations, including crews and the EMU rakes, without charge to the state. Ticket checking stays with the Railways, and fare and non-fare revenue in this period goes to Southern Railway.
  • Before the 24 months end: the state pays for land, assets and infrastructure, in full or in instalments.
  • EMUs stay with Southern Railway until Tamil Nadu buys new rolling stock or the transition ends, whichever is later.
  • Chennai Beach: suburban trains keep using MRTS platforms 9 and 10 through to St Thomas Mount during the transition, and the Railways share those platforms afterwards too.
  • Chennai Fort: the state builds a crossing station with electronic interlocking. Southern Railway will consider a state proposal to double the single-line Beach–Fort stretch.
  • Oversight: a committee of Southern Railway and state officials, with the CUMTA convenor as coordinating officer.

All 21 MRTS stations

Station order from Wikipedia's MRTS page (read 8 November 2026). Swarajya and Metro Rail News (19 August 2026) say the transfer covers land and infrastructure at 19 of the 21 stations, but neither names the two left out, so we do not guess.

  • 1. Chennai Beach (shared platforms 9 and 10, per the draft terms)
  • 2. Chennai Fort
  • 3. Chennai Park Town
  • 4. Chintadripet
  • 5. Chepauk
  • 6. Thiruvallikeni
  • 7. Light House (the Yellow Line metro's planned terminus is also called Light House)
  • 8. Mundagakanniamman Koil
  • 9. Thirumayilai (Thirumayilai metro station is planned on the Yellow and Purple Lines)
  • 10. Mandaveli
  • 11. Greenways Road
  • 12. Kotturpuram
  • 13. Kasturba Nagar
  • 14. Indira Nagar
  • 15. Thiruvanmiyur
  • 16. Taramani
  • 17. Perungudi
  • 18. Velachery
  • 19. Puzhuthivakkam (Velachery–St Thomas Mount extension, commercial service from 14 March 2026, per Wikipedia)
  • 20. Adambakkam (listed by Wikipedia with opening still to be decided)
  • 21. St Thomas Mount (interchange with the Green Line metro; Red Line planned)

What is not decided yet

  • The signing date of the final MoU. Without it, there is no date for the 90-day asset handover or the 24-month train-operations handover.
  • The price. Swarajya (9 December 2025) reported that the state, which already holds 67% of the MRTS joint venture, was expected to pay ₹600 to ₹700 crore for the Railways' share. We found no later confirmed figure.
  • Which two stations are outside the asset transfer.
  • The upgrade plan. The same December 2025 report quoted officials planning a 'Metro model system' on the line by December 2027 and talks with the World Bank for a loan of about ₹4,000 crore for coaches and station refurbishment. That was a plan, not a sanctioned project.

Homes in localities served by MRTS stations

Listed for orientation only: TNRERA-registered projects in our catalogue in localities the MRTS serves. We have not measured walking distance to each station, so check it on a site visit.

What to do now

  • 1. Commuters: nothing changes yet. Tickets, timetables and season passes stay with Southern Railway until the MoU is signed, and ticketing stays with the Railways through the transition under the draft terms.
  • 2. Buyers weighing a flat near Velachery, Perungudi or Taramani: treat any 'metro-standard MRTS' upgrade as a plan. The only dated commitment is a 24-month transition that has not started.
  • 3. Watch for one event: the signing of the final MoU. Count 90 days from that date for the station handover and 24 months for train operations.
  • 4. Compare the MRTS with the metro lines due near the same localities: the Purple Line along OMR and Taramani (Purple Line Metro Chennai: Stations, Completion (Nov 2026)) and the full Phase 2 schedule (Chennai Metro Phase 2 Completion Date by Corridor (Nov 2026)).
  • 5. For locality prices and projects, start at Velachery, Chennai or Perungudi, Chennai.