All 13 projects with a live K-RERA registration in Nelamangala taluk are plotted layouts; there is no live apartment registration there, by Property Point's count of the K-RERA register on 7 November 2026. Two dated decisions now bear on the area: the Cabinet's ₹1,118 crore top-up on 5 November 2026 for the 134-km road that ends at Nelamangala, and Cauvery Stage 6, approved on 26 February 2026, which names Nelamangala among eight towns to get more water.

Updated 8 November 2026. Neither project has a published completion date in the reports we opened.

Upgrade 1: the 134-km road and its new money

  • What: a 134-km road linking Attibele, Sarjapur, Dommasandra, Gunjur, Varthur, Whitefield, Kempegowda International Airport and Nelamangala (The Hindu, 5 November 2026).
  • Money: ₹1,118 crore extra approved on 5 November 2026; revised cost ₹3,409 crore against ₹2,290 crore at sanction in 2017.
  • Focus: the Minister said the funds should speed up the Gunjur–Varthur stretch in the east. The report does not say what is pending at the Nelamangala end.
  • No new completion date was announced.

Upgrade 2: Cauvery Stage 6

  • Approved by the cabinet on 26 February 2026 at ₹6,939 crore to bring 500 MLD more (Deccan Herald, 27 February 2026).
  • Nelamangala and Madanayakanahalli are among the eight towns named (Oneindia, 27 February 2026).
  • BWSSB will supply water in bulk; the local body lays the pipes and gives house connections (Deccan Herald).
  • No commissioning date has been published. Full list and status: Cauvery Stage 6 Areas List 2026: The 8 Towns and Status.

Two other roads that touch Nelamangala

  • Satellite Town Ring Road (STRR): the 80-km Dobbspet–Hoskote section is operational. The next package, 79 km from Obalapura in Nelamangala taluk to Kunagal, was estimated at ₹2,642.4 crore and was awaiting central approval in June 2026 (Deccan Herald, 12 June 2026).
  • Bengaluru Business Corridor (PRR-1): package 1 runs from Madavara near the Bangalore International Exhibition Centre to Ballari Road; the BDA issued the letter of acceptance for the ₹3,348 crore contract in June 2026 (Deccan Herald, 16 June 2026).

Live K-RERA registrations in Nelamangala taluk

All plotted developments. Registered completion dates from K-RERA (snapshot of 7 November 2026). Newest first.

  • Jyothi Godhuli · PRM/KA/RERA/1250/307/PR/110926/008935 · approved 11 Sep 2026 · completion 31 Dec 2030
  • Apollo Address · PRM/KA/RERA/1250/307/PR/180826/008874 · 18 Aug 2026 · 31 Jul 2030
  • SJR Vivo City Phase 1 · PRM/KA/RERA/1250/307/PR/070326/008510 · 7 Mar 2026 · 30 Nov 2029
  • Chartered Gulmohar · PRM/KA/RERA/1250/307/PR/110226/008465 · 11 Feb 2026 · 30 Sep 2028
  • Ashwasurya Legacy · PRM/KA/RERA/1250/307/PR/061125/008231 · 6 Nov 2025 · 31 Dec 2029
  • Vistara 1 · PRM/KA/RERA/1250/307/PR/090925/008073 · 9 Sep 2025 · 31 Dec 2027
  • KNS Samooha Phase III · PRM/KA/RERA/1250/307/PR/290825/008039 · 29 Aug 2025 · 23 Aug 2029
  • KNS Samooha Phase II · PRM/KA/RERA/1250/307/PR/210825/008014 · 21 Aug 2025 · 22 Aug 2029
  • Artemis Address Phase 2 · PRM/KA/RERA/1250/307/PR/210525/007764 · 21 May 2025 · 31 Dec 2027
  • FRK Sapphire · PRM/KA/RERA/1250/307/PR/070525/007715 · 7 May 2025 · 31 Dec 2028
  • Artemis Arena · PRM/KA/RERA/1250/307/PR/070325/007560 · 7 Mar 2025 · 31 Dec 2026
  • KNS Samooha Phase I · PRM/KA/RERA/1250/307/PR/060325/007551 · 6 Mar 2025 · 22 Aug 2029
  • Arvind Lakeview · PRM/KA/RERA/1250/307/PR/280324/006755 · 28 Mar 2024 · 31 Dec 2027

What the register tells a buyer

  • Since 2017, 45 projects have been registered in Nelamangala taluk: 40 plotted and 5 apartment/group housing.
  • 14 of them were approved since January 2025, so most of the live supply is recent.
  • Compare Devanahalli taluk (126 live registrations) and Hosakote taluk (109): Nelamangala's registered pipeline is far smaller.

Checks before buying a plot near Nelamangala

  • K-RERA registration and the layout approval (BMRDA or the local planning authority), and that the plot number is in the approved plan.
  • Khata type: e-Swathu (gram panchayat) or town municipal khata, and whether the layout is inside the town limits that Stage 6 water will serve.
  • Water today: borewell or panchayat supply; ask for the layout's water plan in writing.
  • Road access: the actual route to Tumakuru Road (NH 48) and to the STRR, at peak hours.
  • Area guide: Nelamangala, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks. Plots across the city: Plots, Bangalore.