Bengaluru East City Corporation is preparing a satellite bus stand for KR Puram on about five acres near the main road between KR Puram and Bhattarahalli, and a joint survey of the land is scheduled for 16 November 2026 (Asianet Suvarna News, 6 November 2026; Eesanje, 7 November 2026). ITI Limited's land in the area is being considered, and KSRTC has shown interest in about five acres. The survey will mark government and private land, the area available, the road alignment and any encroachments.

Updated 8 November 2026. We read both Kannada reports of the coordination meeting chaired by Additional Commissioner (Development) Lokhande Snehal Sudhakar, and the State Budget announcement of a KR Puram satellite bus station. No cost or design has been announced.

Key dates and facts

  • Coordination meeting: Friday, 6 November 2026, chaired by the East corporation's Additional Commissioner (Development).
  • Land sought: about 5 acres, government or private, near the KR Puram–Bhattarahalli main road.
  • ITI Limited land is under consideration; KSRTC is interested in about 5 acres.
  • Joint survey: 16 November 2026, with ITI Limited representatives, the Assistant Director of Land Records (ADLR) and the Karnataka Housing Board.
  • Before the survey: a road alignment to be prepared on the CDP road map, and encroachments and trees along it cleared.
  • Encroached road: an 80-metre stretch near ITI that is shown on the map but missing on the ground is to be cleared for public use; work was ordered from 7 November.
  • Land options: compensation at market value under the rules, land exchange, or acquisition under the land acquisition law.
  • Departments at the meeting: Chief Engineer Vishwanath J., KHB, PWD, the land records office, ITI Limited and corporation officials.

Background

A new satellite bus station for KR Puram, to be built under public-private partnership, was announced by the Chief Minister in the March 2025 State Budget (Deccan Herald, reporting the budget). Officials quoted by Eesanje said the need had also been discussed at the Chief Minister's level. The new site work comes a day before the minister ordered a master plan for the nearby Tin Factory junction: Tin Factory Junction Master Plan Ordered (7 Nov 2026).

What is not decided

  • The exact site. Five acres have been 'identified' near the main road, but the survey decides what is available.
  • Whether ITI Limited will sell, exchange or lease land, and at what value.
  • Who will build and run the stand (KSRTC, BMTC or a private partner), its cost and its completion date.

Registered homes near Bhattarahalli

Projects in our catalogue with a pin within about 2.5 km of Bhattarahalli (OpenStreetMap point), with K-RERA numbers and RERA completion dates:

  • Brigade Lakecrest, Old Madras Road — PRM/KA/RERA/1251/446/PR/240625/007866 — about 0.4 km — RERA completion date 31 March 2030 — Brigade Lakecrest.