JP Nagar 4th Phase metro station, renamed NS Palya-JP Nagar 4th Phase, is open on the Pink Line since 14 November 2026. It is also the planned starting point of the Orange Line (Phase 3) to Kempapura, which was approved in August 2024 but has not started construction: land notices are being issued, and on 11 November 2026 the state said it aims to finish tendering and begin work within six months. The Phase 3 deadline is reported as 2032.

Updated 17 November 2026. We checked the Pink Line opening and renaming reports (12–14 November 2026), the Phase 3 approval as reported, the October 2026 land notice reports, The Hans India’s April 2026 status report, the minister’s 11 November comments, Wikipedia’s station record and our project pages. Each line’s status is given separately below.

Where is NS Palya-JP Nagar 4th Phase station?

The station is on the Outer Ring Road at JP Nagar 4th Phase, Bengaluru 560078, where the Pink Line runs along Bannerghatta Road (Wikipedia). It is elevated with two platform levels and four tracks: two in use for the Pink Line and two reserved for the Orange Line. NS Palya is the revenue village name; the Centre approved the new name on 12 November 2026.

Pink Line status at JP Nagar 4th Phase

  • Open since 6 am on 14 November 2026 on the 7.5 km Kalena Agrahara–SG Palya stretch (PTI via The Federal).
  • Neighbours: Jayadeva Hospital (1 stop north, Yellow Line interchange) and Bilekahalli-IIMB (1 stop south).
  • Trains every 8 minutes at peak and about 10 minutes off-peak; first train 6 am Tuesday to Saturday, 7 am Sunday, 4:55 am Monday from Kalena Agrahara (Oneindia; IANS).
  • The underground continuation from SG Palya to MG Road and Nagawara has a BMRCL target of May 2027 (Urban Acres, 10 November 2026).

Orange Line status at JP Nagar 4th Phase

  • Approval: Union Cabinet, 16 August 2024. JP Nagar 4th Phase to Kempapura, 32.15 km with 22 stations, plus Hosahalli to Kadabagere, 12.5 km with 9 stations; ₹15,611 crore (The Metro Rail Guy).
  • Land: the third preliminary land acquisition notification for Package 1, dated 16 October 2026, covers 13,409.05 sq m between JP Nagar 4th Phase and Mysuru Road station. Metro Rail News counts 11 gazette entries; Urban Acres says 170 properties. One likely reason is that a gazette entry can cover several properties, but we could not check the gazette itself.
  • Localities in that notice (Urban Acres): Bilekahalli, Sarakki Agrahara, Sarakki, Jaraganahalli, Kadirenahalli, Kareesandra, Katriguppe, Ittamadu, Hosakerehalli and Pantharapalya. Linked stations: JP Nagar, Dwarakanagar, Hosakerehalli, Kadirenahalli and Kamakya.
  • Tenders: The Hans India (22 April 2026) reported about ₹4,187 crore of civil tenders floated for double-decker sections, with the Centre’s final approval of the double-decker plan still pending. Urban Acres (20 October 2026) says the double-decker length was cut to about 11 km from 37 km.
  • Latest aim: on 11 November 2026 the minister said the government aims to complete tendering and begin work within six months (PTI via The Week).
  • Deadline: 2032 (The Hans India, 22 April 2026). Wikipedia’s 2029 date for the Orange platforms is older.

Where will the Orange Line take you from JP Nagar 4th Phase?

The Orange Line follows the western Outer Ring Road to Hebbal and Kempapura. Interchanges listed on the route include JP Nagar (Green Line), Mysuru Road (Purple Line), Peenya (Green Line), Hebbal and Kempapura (Blue Line) (Wikipedia; Phase 3 integration points as reported by The Metro Rail Guy). The first Orange stop after this station is JP Nagar 5th Phase. Station list: Namma Metro Phase 3 Stations List: All 31 Stations (2026). Land notice detail: Namma Metro Phase 3 Land Acquisition: The 16 Oct 2026 Notice

RERA-registered homes in JP Nagar within reach

Straight-line distances are from our project pages, checked on 17 November 2026. We have left out pre-launch projects that do not yet have a K-RERA number.

  • Total Environment Learning To Fly, Ring Road near Jayadeva Hospital, JP Nagar: completed; about 1 km from Jaya Prakash Nagar (Green Line), a future Orange Line interchange. K-RERA PRM/KA/RERA/1251/310/PR/171014/000270. Total Environment Learning To Fly
  • Purva Coronation Square, Puttenahalli Road, JP Nagar 7th Phase: completed, first occupancy certificate 4 January 2020; about 1 km from Yelachenahalli (Green Line). K-RERA PRM/KA/RERA/1251/310/PR/170916/000235; 3 and 4 BHK. Purva Coronation Square
  • Godrej Vanantara, Bannerghatta Road: about 800 m from Bilekahalli-IIMB, one Pink Line stop south. K-RERA PRM/KA/RERA/1251/310/PR/130526/008653; new launch, RERA completion 31 May 2031. Godrej Vanantara
  • Rates and area: Jp Nagar and Jp Nagar, Bangalore

What should JP Nagar buyers do with the Orange Line?

  • Value the Pink Line now; it is open. Treat the Orange Line as a 2030s benefit.
  • If you own land near the ORR between JP Nagar and Mysuru Road, match your survey number against the notified schedule before you sell or lease.
  • Background on the double-decker change: Orange Line Metro: Double-Decker Dropped, 4 Flyovers Instead