A Bengaluru association should collect four things from the builder: documents, money, assets and a defect list. Section 16 of the Karnataka Apartment (Ownership and Management) Act, 2026 lists 15 kinds of documents, from land title and as-built drawings to lift, fire and environmental certificates, AMCs and tax receipts. It also covers every rupee collected as corpus, deposits and advance maintenance, with interest and an audited allottee-wise statement. The deadline is 60 days from the occupancy certificate (OC). Defects reported within five years of possession must still be fixed within 30 days under Section 14(3) of the RERA Act.
Updated 19 November 2026. We read the 2026 Act's Bill text (Sections 10, 16, 21, 22, 52, 53), Fox Mandal's note on the notified Act, Sections 11, 14, 17 and 19 of the RERA Act on the K-RERA site, and Section 5 of the Karnataka Lifts Act. One status point first: the 2026 Act was gazetted on 15 October 2026 but starts on a date the government notifies. We found no commencement notification by 18 November 2026, so its 60-day clock is not yet running. RERA applies today.
Which law governs the handover today?
Two laws matter. The RERA Act, 2016 is in force now. Section 17(2) makes the promoter hand over the necessary documents and plans, including common areas, to the association after the OC and possession, as per local laws. Where no local law applies, the deadline is 30 days after the completion certificate. Section 11(4)(d) makes the promoter run essential services until the association takes over maintenance.
The 2026 Act (Karnataka Act No. 45 of 2026, assent 9 October 2026, gazette 15 October 2026, per Fox Mandal) adds detail. Once it commences, the builder must hand over documents and funds within 60 days of the OC (Section 16(1)(b)-(c)). It must also sign a registered deed that transfers management of the common areas to the association (Section 10(2), (4)). That deed transfers management only. Ownership of land and common areas stays with flat owners in proportion to their undivided share (Section 10(3)). For the conveyance side, see Deemed Conveyance in Karnataka: What the 2026 Act Says.
One correction to a common claim. A 2022 ranking recap says RERA requires the association within one year of the sale deed. The Act says otherwise. Section 11(4)(e) says that where no local law applies, the association must be formed within three months of a majority of allottees booking. The 2026 Act also uses three months from majority allotment (Section 21(2)).
Part 1: which documents must the builder hand over?
Section 16(1)(b) of the 2026 Act lists these. Tick each one and note whether you got the original or a copy.
- Land title documents, and the lease deed or lease certificate if the land is leased.
- The declaration filed with the competent authority (due within 60 days of the OC under Section 13), showing each flat's undivided share. Check it against UDS in Apartment Bangalore: Your Land Share, 2026 Rules.
- Sanctioned plans, approvals, and the completion and occupancy certificates. RERA Section 11(4)(b) separately makes the builder give the OC/CC to the association.
- As-built drawings and structural drawings.
- Statutory compliance certificates: fire safety, lift safety and environmental approvals. Lift licences are valid for 10 years, then renewable every 5 years (Karnataka Lifts Act 2012, Section 5); see Lift Licence in Karnataka: Renewal and Fees for Bangalore Flats. For STP consent, see Sewage Treatment Plant in Apartments in Bangalore: Rules, Cost.
- Insurance policies for the project.
- Encumbrance certificates and related records.
- Electrical wiring diagrams, plumbing layouts and service drawings.
- Purchase, installation and commissioning papers for equipment.
- Operation manuals, service manuals and warranties for all equipment.
- Maintenance contracts, AMCs and vendor contacts for lifts, generators, fire systems, water treatment plants and other facilities.
- User manuals, access credentials and software papers for building-management and electronic security systems.
- Receipts for municipal taxes, fees and statutory dues up to the handover date.
- Any other document the rules prescribe. The association must acknowledge receipt and copy the acknowledgement to the competent authority.
Part 2: what money must move to the association?
- All funds collected for maintenance deposits, security deposits, corpus fund, advance maintenance or any other common-area charge, with the interest earned on them (2026 Act, Section 16(1)(c)).
- An audited statement of accounts, project-wise and allottee-wise (Section 16(1)(c)). Match it against each owner's receipts. A shortfall shows up here.
- Proof that outgoings the builder collected, such as property tax and water and power charges, were paid up to possession. Under RERA Section 11(4)(g) the builder stays liable for unpaid outgoings even after transfer.
- The maintenance account for the period the builder ran the complex, including dues on unsold flats. The builder is a member for unsold flats and pays their maintenance (2026 Act, Section 21(8)).
- A bank account in the association's name with a scheduled bank, to receive all of the above (Section 28(1)). Separate accounts for different funds are allowed (Section 28(2)).
- GST and TDS records for amounts the builder collected or deducted while running maintenance. Ask for them so the association's own filings start clean. Maintenance GST basics: Maintenance Charges in Bangalore Apartments 2026: GST, Corpus.
Part 3: which assets and systems should be checked and listed?
Section 21(11)(a) and (d) hand the association possession and control of the common areas and the running of all service installations. Before you sign, walk each system with the vendor or an independent engineer. Record its make, age, warranty end date and AMC status.
- Lifts: licence copy, last inspection, AMC, rescue drill log.
- DG sets, transformers and electrical panels: load tests, earthing reports, fuel log.
- STP and WTP: consent copy, outlet test reports, membrane and media age.
- Pumps, sumps and overhead tanks: capacity, cleaning record.
- Fire systems: hydrants, sprinklers, alarm panel test, fire NOC copy.
- CCTV, access control, intercom: admin passwords and recorder retention.
- Clubhouse, gym and pool equipment with warranties.
- Inventory: keys (labelled by door), spares, furniture and tools, signed by both sides.
Part 4: how should defects be recorded?
- Do a joint snag audit of common areas with the builder's engineer. Photograph and number every item. Owners' own flat checks: Flat Possession Checklist: Bangalore Snag List and Documents.
- Send the list in writing and keep the acknowledgement. RERA Section 14(3) says defects in structure, workmanship, quality or services raised within five years of possession must be fixed within 30 days at no charge. If they are not, allottees are entitled to compensation.
- Handover does not end that duty. Section 21(13) of the 2026 Act keeps the builder liable for RERA obligations, including defect repair, after management passes to the association.
- Track the five-year date for each block. It runs from possession, so phases may end on different dates.
What is the timeline, and who signs?
- Majority of flats allotted: builder must facilitate the association within three months (2026 Act, Section 21(2); RERA Section 11(4)(e) where no local law applies).
- OC issued: declaration to the competent authority within 60 days (Section 13). Documents and funds to the association within 60 days (Section 16).
- Association registered: registered management-transfer deed (Section 10(2), (4)). Possession of common areas, records, funds and installations (Section 21(10)-(11)).
- Who signs: the builder's authorised signatory and the association's authorised office-bearers, under a general body or executive committee resolution. Keep the resolution with the handover file.
- Projects sold before the Act starts: the association applies for registration within three months of commencement. Existing associations update their details and bye-laws within six months (Section 22(1), (7)).
- Buying under construction? These are the steps your association will follow at handover in catalogue projects such as Prestige Glenbrook and Brigade Laguna.
What if the builder withholds items?
- Write first. List the missing items, cite RERA Sections 11(4), 17 and 19(5) (allottees' right to documents and plans), and set a date. Keep the acknowledgement.
- Today: file a complaint with K-RERA. Steps and fee: How to File a Complaint in Karnataka RERA: 2026 Guide.
- After the 2026 Act commences: the association's secretary or an authorised person can complain to the competent authority. Failing to file the declaration, facilitate the association or execute deeds carries a penalty of up to ₹1 lakh, plus up to ₹1,000 a day while the default continues (Section 52(1)). Other disputes go to the competent authority under Section 53, with two levels of appeal.
- If your complex has no association yet, start with Apartment Owners Association Registration Bangalore 2026. For the law itself, see Karnataka Apartment Act 2026 Notified: What Flat Owners Must Do.