In Karnataka, every lift must be licensed before it is used, under the Karnataka Lifts, Escalators and Passenger Conveyors Act, 2012 (Karnataka Act 09 of 2013). Since the fee rules of 27 January 2025, a licence or its renewal for a lift in a residential building costs ₹2,500 per lift up to 6 floors, ₹3,500 for 7–15 floors, ₹4,500 for 16–25 floors and ₹6,000 above 25 floors. A late renewal adds ₹500 per lift for each month of delay, capped at ₹2,500. The licence is held by the building's owner, which for a Bangalore apartment means the builder until handover and the owners' association after it.

Updated 18 November 2026. We read the 2025 amendment rules as published by LegitQuest, Section 5 of the Act on Indian Kanoon, and the Karnataka Lifts, Escalators and Passenger Conveyors (Amendment) Bill, 2025 (LA Bill No. 65 of 2025), whose annexure reproduces Section 4 of the Act. The Act's page on India Code returned an error, so check the latest consolidated text before relying on any section.

What does the law require before a lift can run?

  • Erection permission: the owner needs permission to erect a lift under Section 3 of the Act.
  • Installation standard: lifts must follow the relevant BIS code of practice and the Central Electricity Authority's safety regulations (Section 4(1)); the 2025 Bill updates that reference to the CEA's 2023 regulations.
  • Completion notice and licence application: within one month of completing erection, the owner sends a written notice of completion and applies for a licence, with the inspection fee (Section 4(2)–(4)).
  • No power, no use without a licence: except for tests, electricity supply cannot be arranged for the lift, and neither the owner nor the erector may use it, until the licence is granted (Section 4(6)–(7)).
  • Who grants it: the Act said the Chief Inspector of Lifts; the 2025 Bill substitutes ‘authorised officer’ in Sections 4, 11, 16 and 17 to support ‘trust-based governance’.
  • Accidents: the owner (or a named agent) must report any accident that caused or could have caused injury to the authorised officer, the Commissioner of Police and the District Magistrate, and cannot resume operation without written permission (Section 11).

How long is a lift licence valid in Karnataka?

Section 5 of the Act, as published on Indian Kanoon, makes a licence valid for ten years from the date it is granted, provided no addition or alteration has been made to the lift, and says it must be renewed before it expires, for further periods of five years each, on the application, fee and conditions set by the Rules. The 2025 fee schedule separately lists a periodical inspection fee per lift under Rule 11(2), so a licensed lift is still inspected in between. If you see ‘annual renewal’ claims online, check the date and rule they cite.

Lift licence fees in Karnataka (2025 rules), residential lifts

Floors are counted including basement and ground floors. Non-residential lifts pay more.

  • Erection permission per lift: up to 6 floors ₹1,000 · 7–15 floors ₹2,000 · 16–25 floors ₹3,000 · above 25 floors ₹4,000
  • Licence grant (initial inspection) or renewal per lift: up to 6 floors ₹2,500 · 7–15 ₹3,500 · 16–25 ₹4,500 · above 25 ₹6,000
  • Late renewal: ₹500 per lift for each month or part of delay, capped at ₹2,500, on top of the renewal fee
  • Periodical inspection per lift: up to 6 floors ₹1,000 · 7–15 ₹2,500 · 16–25 ₹3,000 · above 25 ₹3,500 (LegitQuest notes the floor bands here are worded differently; check the gazette)
  • Escalator or travelator: erection permission ₹2,000; licence or renewal ₹4,000; periodical inspection ₹3,500
  • Transfer of licence ₹500 per unit; duplicate licence ₹1,000; additions or alterations ₹1,000; application fee ₹100 for erection, licence and alteration applications
  • Lift firms: registration for erection and maintenance ₹30,000 a year (maintenance only ₹20,000); three-year renewal ₹60,000 (₹30,000)

Worked example: a 20-floor tower with four lifts

  • Building: residential, 20 floors including basement and ground, so the 16–25 band applies.
  • Erection permission: 4 × ₹3,000 = ₹12,000, paid by the builder.
  • Licence: 4 × ₹4,500 = ₹18,000, plus ₹100 application fee, paid by the builder before possession.
  • Renewal at the end of the licence period: 4 × ₹4,500 = ₹18,000, paid by the association.
  • If the association files three months late: 4 × ₹500 × 3 = ₹6,000 extra. At five months or more it hits the ₹2,500-per-lift cap: ₹10,000.
  • Each periodical inspection: 4 × ₹3,000 = ₹12,000.

What should flat buyers and associations ask for at handover?