Silverglades has three residential projects on the HRERA Gurugram register today: The Legacy Phase-I in Sector 63A on Golf Course Extension Road (RERA-GRG-1689-2024), Hightown in Sector 28 next to Sushant Lok 1 (RERA-GRG-337-2019) and The Melia in Sector 35, Sohna (RERA-GRG-350-2019, registered by DSS Buildtech and marketed on Silverglades’ own site). A fourth registration, Merchant Plaza in Sector 88, is commercial.

Updated 20 November 2026. We read every Silverglades row on the HRERA Gurugram registered-projects register (registration certificate, date and “registration valid up to” date), opened the HRERA project page for Hightown, and read Silverglades’ official pages for each project. Portal counts of “6+” or “10+” projects mix in commercial, out-of-state and pre-RERA work. This list keeps only Gurgaon homes that carry an HRERA number.

Silverglades projects in Gurgaon at a glance

Ordered by HRERA registration date, newest first. Format: Project — Promoter on HRERA — Location — HRERA no. (certificate, date) — Homes — Price — Status.

  • The Legacy Phase-I — Silverglades Homes LLP — Sector 63A, Golf Course Extension Road — RERA-GRG-1689-2024 (GGM/861/593/2024/88, 16 Aug 2024) — 3 BHK, 4 BHK and penthouses — builder price on request (portal sheet in our Legacy price post) — registration valid up to 31 May 2031
  • Hightown Residences — Silverglades Infrastructure Pvt Ltd — Sector 28 (village Sukhrali, opposite The Laburnum, Sushant Lok 1) — RERA-GRG-337-2019 (GGM/406/138/2020/22, 1 Sep 2020) — 260 homes, 3 and 4 BHK — price on request — HRERA status: extension certificate uploaded
  • The Melia (with Melia First Citizen) — DSS Buildtech Pvt Ltd — Sector 35, Sohna — RERA-GRG-350-2019 (288 of 2017, 10 Oct 2017) — 990 homes, 2, 3 and 4 BHK; 156 senior-living homes — price on request — ready to move per Silverglades; registration valid up to 26 April 2028
  • Merchant Plaza (commercial, not homes) — Silverglades Infrastructure Pvt Ltd — Sector 88 — RERA-GRG-507-2019 (340 of 2017, 27 Oct 2017) — shops/offices — HRERA register carries an OC/CC/PCC document

The Legacy, Sector 63A (Golf Course Extension Road)

The Legacy is Silverglades’ newest registered project. HRERA lists it as “The Legacy Phase-I”, promoted by Silverglades Homes LLP on land in village Behrampur, Sector 63A, with certificate GGM/861/593/2024/88 dated 16 August 2024 and registration valid up to 31 May 2031. Silverglades’ project page lists 3 BHK + family lounge + utility + powder room, 4 BHK + family lounge and 4 BHK + study layouts, plus penthouses.

We covered its price sheet, carpet areas and per-sq-ft maths in Silverglades The Legacy Sector 63A: Price, RERA, Sizes 2026, so we do not repeat them here. Our project page is Silverglades The Legacy, and the other registered launches in the same sector are in Sector 63A Gurgaon New Projects 2026: HRERA Numbers, Dates and on Sector 63a Gurgaon, Gurgaon.

Hightown Residences, Sector 28 (Golf Course Road side)

Hightown is a mixed-land-use project in the revenue estate of village Sukhrali, Sector 28. Silverglades’ page says it sits opposite The Laburnum in Sushant Lok 1 and offers 260 homes in 3 and 4 BHK layouts across three towers. The disclaimer on the same page gives the approvals: DTCP licence 110 of 2013, a Transit Oriented Development (TOD) benefit, and building plans approved on 25 August 2020 as mixed land use (70% residential, 30% commercial) for 4.85 acres, with 260 residential units, 46 EWS units and 189 shops or commercial units.

The marketing headline says the site “spans 5 acres”; the approved building plan says 4.85 acres. Use the approved figure in any agreement. On HRERA the project page shows the status “Extension Certificate Uploaded”, and Silverglades’ page still carries a construction-update section. Before you buy, open the latest quarterly progress report (QPR) from the register and ask for the current registration validity in writing. Our project page is Silverglades Hightown Residences; Golf Course Road context is on Golf Course Road, Gurgaon.

The Melia and Melia First Citizen, Sector 35 Sohna

The Melia appears on the HRERA register under the promoter DSS Buildtech Pvt Ltd, Sector 35, Gurugram, with registration 288 of 2017 dated 10 October 2017 and validity up to 26 April 2028. Silverglades’ page shows the same number with an extension suffix (288 of 2017/7(3)/2022/13) and lists the project as ready to move in.

Silverglades gives 17.50 acres and 990 units for The Melia, with 2 BHK + study (1,425 sq ft), 3 BHK + domestic help (1,845 sq ft) and 4 BHK plans. Melia First Citizen is a senior-living section of two towers and 156 homes; its floor plans show 1 BHK (1,021 sq ft), 2 BHK (1,300 sq ft) and 3 BHK (1,543 sq ft). The First Citizen page gives the wider site as 17.4 acres, a small difference from the 17.50 acres on the main page. Both pages say price on request. Sector 35 is covered in Sohna Sectors 35 and 36: Buyer's Guide 2026 — Independent Floors, Aravalli Foothills and Delivery Risk and on Sector 35 Sohna, Gurgaon.

How many projects does Silverglades have in Gurgaon?

It depends on what you count, which is why the ranking pages disagree (NoBroker says 6+, Square Yards 10+). Silverglades’ own site lists residential, commercial, township and golf-leisure work, including earlier Gurgaon communities, some developed with ITC Limited, that were finished before HRERA registration began in 2017 and so are not on the register, and projects outside Haryana.

Counting only HRERA Gurugram registrations under Silverglades company names, we found four: three housing projects (The Legacy Phase-I, Hightown, plus The Melia under DSS Buildtech) and one commercial project (Merchant Plaza). If you are comparing resale homes in the older communities, check the DTCP occupation certificate and the conveyance deed instead of a RERA number. Our guide Occupation and Completion Certificates in Haryana: What to Check Before You Take Possession explains how.

Silverglades upcoming projects: what is actually registered?

The newest Silverglades registration on the register we read on 20 November 2026 is The Legacy Phase-I (16 August 2024). Under Section 3 of the RERA Act, a promoter cannot advertise or book homes in a new project or phase until it is registered. So if you are offered a new tower, phase or “upcoming” project, ask which HRERA number covers it and check that the number, promoter and land match the register. If no number exists yet, do not pay a booking amount.

How to check a Silverglades project on HRERA

  • Open the HRERA Gurugram registered-projects list (haryanarera.gov.in → Registered Projects → Gurugram) and search the project name, or the promoter: Silverglades Homes LLP, Silverglades Infrastructure Pvt Ltd or DSS Buildtech Pvt Ltd.
  • Match the RERA-GRG number and the certificate number (GGM/…/…) with the one printed in the brochure or agreement.
  • Read the “registration valid up to” date. That is the legal completion date, even if the brochure shows an earlier target.
  • Open the QPR link for the latest quarterly progress report, and the OC/CC/PCC column for any occupation, completion or part-completion certificate.
  • Use How to Check if a Project is RERA Registered in Gurgaon (Haryana RERA Guide 2026) for screenshots of each step.