Before you accept a new flat in Gurgaon, do three things in order. First, confirm the occupation certificate (OC) covers your tower. Second, inspect the flat and common areas and write every defect into a snag list that the builder’s representative signs. Third, measure the carpet area against your agreement. Do not sign a blanket ‘no claims’ letter. Under Section 14(3) of the RERA Act you can report defects for 5 years from handover, and the builder must fix them free within 30 days.
Updated 17 November 2026. We checked the RERA Act (Sections 2(k), 11(4)(b), 14(3), 17, 19(10)), the Haryana model agreement for sale in the 2017 Rules, and HRERA Gurugram’s 12 August 2021 order on what makes a valid offer of possession. Document checks are covered in Gurgaon Project Paper Checks 2026: OC, CC, DTCP and RERA; this post is the physical inspection.
What should I check before the site visit?
- OC for your block: under clause 7.2(B) of the Haryana model agreement, the builder offers possession after the OC and must give you a copy on demand. Section 11(4)(b) makes getting the OC the promoter’s job.
- Schedules D and E of your agreement (fittings, fixtures and amenities). Clause 1.6 bars changes without your written consent, so carry the list and tick it off.
- The approved floor plan with dimensions, for the carpet-area check.
- The final demand letter. HRERA Gurugram caps advance maintenance at 12 months and bars holding charges; for the usual cost lines, see IFMS, EDC & Maintenance Charges in Gurgaon (2026): The Full Cost of a Flat.
- Tools: a socket tester, a torch, a 5 m tape or laser measure, a coin for tap-testing tiles, a spirit level, a bucket, and your phone for dated photos.
Room-by-room snag list: what to physically inspect
- Walls and ceilings: cracks, damp patches, bubbling paint, hollow-sounding plaster. Look closely at corners, around windows, and along the ceiling line.
- Seepage: run the shower for 10 minutes, then check the other side of every bathroom wall and the ceiling of the flat below if you can. Check below windows and along external walls.
- Plumbing: open all taps together to judge pressure, flush every WC, pour a bucket of water in each bathroom and balcony to check the floor slopes to the drain, and check under the sinks for leaks.
- Electrical: test every socket with the tester, switch every light and fan, trip and reset each MCB, and check that the distribution board is labelled. Confirm AC points and the sanctioned load match what was promised.
- Doors and windows: alignment, smooth closing, locks and keys, sealant around frames, cracked glass, and mesh if the specifications promise it.
- Floors and tiles: tap each tile with a coin (a hollow sound means poor bedding), check uneven joints, cracked tiles, grout gaps and skirting.
- Kitchen: platform level and fixing, sink drain, and the gas pipeline and exhaust points if they are in the specifications.
- Balconies and shafts: drain slope, railing fixing, and whether service-shaft doors close and are sealed.
- Smart locks, video door phones or other fittings named in the schedules: power them on and test them.
Which common areas and services should I check?
HRERA’s 2021 order says a habitable flat needs common facilities like lifts, stairs and lobbies to be working, or capable of working within 30 days. So inspect beyond your front door.
- Lifts: ride each lift serving your tower, and check the alarm and intercom inside.
- Fire safety: hydrant and hose points on your floor, sprinklers if provided, the fire alarm panel, and clear staircases and exits.
- Water and sewage: ask whether the sewage treatment plant (STP) is running and where the water supply comes from.
- Power backup: confirm the backup load for your flat matches the agreement.
- Parking: get the allotment letter with the slot number and check the slot exists on site. HRERA has held that open parking cannot be sold. See Car Parking Charges in Apartments Bangalore: Law and Checks for the RERA background.
How do I check the carpet area at possession?
Section 2(k) of the RERA Act defines carpet area as the net usable floor area inside the flat. It includes internal partition walls but excludes external walls, service shafts, exclusive balconies and exclusive open terraces. Measure each room wall to wall, add the area under internal walls, and compare with the carpet area in your agreement.
Clause 1.7 of the Haryana model agreement says the builder must confirm the final carpet area after the OC. If it is smaller, you get a refund of the excess within 90 days, with interest at the prescribed rate from the date you paid. If it is larger by up to 5%, the builder may bill the extra at your agreed rate per sq ft. Example: agreed carpet area 1,200 sq ft at ₹15,000 per sq ft. If the final figure is 1,180 sq ft, the refund due is 20 × ₹15,000 = ₹3,00,000 plus interest.
What should I not sign at handover?
Builders often attach an indemnity-cum-undertaking or ‘no claims’ declaration to the possession letter. HRERA Gurugram’s 2021 order held that such a document, signed to get the keys, does not stop a buyer from claiming delay interest. It is still better not to sign away rights. Write on the possession letter: ‘Possession accepted subject to snag list dated __ and without prejudice to my rights under the RERA Act.’
The same order separates minor defects from an unfinished flat. Gaps in windows, chipped plaster or paint, a few cracked tiles or stiff drawers are minor. HRERA says to accept such a flat under protest and the defects ‘can be rectified later at the cost of the developers’. A flat with plaster or flooring still to be done, or with lifts not working, is uninhabitable, and an offer of it ‘will not be considered a legally valid offer of possession’.
For the conveyance deed stage, see Signing a Conveyance Deed Under Protest: HRERA's 2026 Rulings.
How long is the builder liable for defects after possession?
Section 14(3): if you report a structural defect, or any defect in workmanship, quality or services, within 5 years of handover, the promoter must fix it without charge within 30 days. If it does not, you are entitled to compensation under the Act.
There is a conflict to know about. Clause 12 of the Haryana model agreement says ‘within ninety days’, while the Act says 30 days. Section 89 gives the Act overriding effect over anything inconsistent, so quote the 30-day period in your letters. The model agreement also says the builder is not liable for defects caused by your own structural or architectural changes, so record snags before your interior work starts.
- Report every defect in writing (email works) with dated photos, and keep the reply.
- Section 19(10) expects you to take possession within 2 months of the OC, so book the inspection early.
- Conveyance: the model agreement asks the builder to register the conveyance deed preferably within 3 months, and not later than 6 months, from possession. Budget stamp duty and registry with /calculators/gurgaon-total-cost.