The Gurgaon–Sohna elevated road (NH-248A) is tolled at the Ghamroj plaza, also spelled Ghamdoj. From 1 April 2026 a car, jeep or van pays ₹130 for a single trip and ₹195 for a return trip. Buses and trucks pay ₹440, heavy machinery ₹690 and oversized vehicles ₹845 per crossing. There is no separate toll for getting on at Subhash Chowk; you pay once at Ghamroj.

Updated 17 November 2026. We checked the 1 April 2026 report on NHAI's annual revision, the March 2026 NHAI FASTag annual-pass notice, NHAI's 2022 decision on access points, the July 2022 opening report and the 2026 GMDA/NHAI plans for Rajiv Chowk and the SPR. NHAI's Toll Information System (tis.nhai.gov.in), which carries the plaza's fee notification, did not respond when we tried today, so confirm the rate there or in the Rajmargyatra app before relying on it.

What are the Ghamroj toll rates for 2026–27?

NHAI revises toll fees every year on 1 April in line with the Wholesale Price Index. The 2026–27 rates reported on 1 April 2026 for Ghamroj are:

  • Car / jeep / van: ₹130 single trip; ₹195 return trip.
  • Bus / truck: ₹440 per crossing.
  • Heavy construction machinery: ₹690 per crossing.
  • Oversized vehicles: ₹845 per crossing.
  • Older figures you will still see online: ₹115 and then ₹125 for a car single trip. These are from earlier years.

Is there a monthly, local or annual pass?

NHAI's FASTag Annual Pass for private, non-commercial vehicles rose from ₹3,000 to ₹3,075 for 2026–27, effective 1 April 2026, and covers over 1,000 fee plazas on National Highways and National Expressways. Check in the Rajmargyatra app that Ghamroj is listed before you buy it.

NHAI plazas also offer concessional monthly passes to residents living within 20 km. The 1 April 2026 report gives the local pass as ₹350 a month at Kherki Daula and Bijwasan but does not give a Ghamroj figure, so ask at the plaza office with your vehicle RC and address proof.

Where are the entry and exit points?

The road was designed as access-controlled, so there are few ramps. NHAI's position in June 2022 was:

  • Gurugram end: entry and exit at Subhash Chowk, about where Sohna Road meets the inner city. The road starts at Rajiv Chowk on NH-48 and runs south through Subhash Chowk.
  • Ghamroj toll plaza: an access point at the plaza itself.
  • Sohna end: entry and exit near K.R. Mangalam University, Sohna.
  • Added access: NHAI approved two more access points, near Subhash Chowk and at Jail Road near Bhondsi, so that traffic on the service lanes can join the elevated road.
  • Planned at Rajiv Chowk: NHAI has proposed a left-turn elevated ramp from NH-48 onto NH-248A for traffic heading to Sohna, and a right-turn ramp from NH-248A to NH-48 for traffic going towards Delhi (Construction World, 2 February 2026). This is a proposal, not built.

How long is the road and what did it cost?

Reports give 21.65–21.66 km, often rounded to 22 km, in two packages: Rajiv Chowk to Badshahpur (8.94 km) and Badshahpur to K.R. Mangalam University, Sohna (12.71 km). It is six lanes with local lanes alongside and opened to traffic in July 2022.

Costs conflict. The road ministry's July 2022 inauguration was reported at ₹2,009 crore for the six-lane Sohna highway; a status tracker gives an estimated ₹1,466 crore. The higher figure appears to be the total project cost and the lower an earlier estimate; we could not open an NHAI document that settles it.

Which Sohna Road sectors does it serve?

What changes are coming on this route?