Eight HRERA-registered luxury phases in Gurgaon list a completion date between 31 December 2026 and 31 December 2027, all on Golf Course Extension Road: Birla Navya Anaika and Avik Phase 1, Adani x Brahma’s Samsara Avasa and Samsara Vilasa & Arya, Trump Towers Delhi NCR, Emaar Emerald Hills Phase 2, and Emaar Marbella Phases 2 and 7. Developers have not published current prices for these phases, so this list gives dates, sizes and RERA numbers rather than a price range.
Updated 20 November 2026. We read the HRERA Gurugram register on 20 November 2026 for each completion date and opened the registration forms (REP-I) for unit and plot counts. “Luxury” here means an objective format: branded towers, villa or villa-plot phases, or low-rise luxury residences, as described by HRERA or the developer. The list is ordered by HRERA completion date, then alphabetically. It is not a ranking.
Luxury projects with possession in 2026-27: summary table
Format: Project — Sector — RERA no. — Format — HRERA completion date — Our page.
- Birla Navya (Anaika) — 63A — RERA-GRG-1012-2022 — low-rise residences — 31 December 2026 — Birla Navya
- Emaar Marbella Phase 7 — 66 — RERA-GRG-2230-2026 — 12 villa plots — 31 December 2026 (see note) — Emaar Marbella
- Samsara Avasa — 63 — RERA-GRG-1150-2022 — low-rise floors — 31 December 2026 — no page
- Samsara Vilasa & Samsara Arya — HRERA address Plot 83, Sector 32 — RERA-GRG-985-2021 — low-rise floors — 31 December 2026 — Adani Samsara Vilasa
- Birla Navya (Avik Phase 1) — 63A — RERA-GRG-1233-2022 — low-rise residences — 30 April 2027 — Birla Navya
- Trump Towers Delhi NCR — 65 — RERA-GRG-1388-2023 — branded towers, 262 apartments — 28 June 2027 — Trump Towers Delhi NCR (Gurgaon)
- Emaar Emerald Hills Phase 2 — 62 & 65 — RERA-GRG-1342-2023 — 474 residential plots — 10 August 2027 — Emaar Emerald Hills
- Emaar Marbella Phase 2 — 65 & 66 — RERA-GRG-755-2020 — 136 villa plots — 31 December 2027 — Emaar Marbella
Trump Towers Delhi NCR, Sector 65
The first Trump-branded project in Gurgaon, built by Tribeca Developers with M3M. HRERA lists the promoter as Olive Realcon Pvt Ltd on 2.83 acres within a 56.05-acre licence.
- RERA no.: RERA-GRG-1388-2023 (registered 17 July 2023)
- HRERA completion date: 28 June 2027
- REP-I unit table: 262 apartments in two towers, carpet from 192.27 sq m (2,070 sq ft) to 352.75 sq m (3,797 sq ft) for most homes, with six larger units of 388.49, 621.84 and 1,277.26 sq m
- Our page: Trump Towers Delhi NCR (Gurgaon); how it differs from the second Trump project: Trump Residences Gurgaon vs Trump Towers: HRERA Facts (2026)
Birla Navya Anaika and Avik Phase 1, Sector 63A
Birla Navya is Birla Estates’ low-rise community on Golf Course Extension Road, registered in pockets under Avarna Projects LLP. Two pockets fall in this window; a third, Avik Phase 2 (RERA-GRG-1829-2024), lists 30 April 2030.
- Anaika: RERA-GRG-1012-2022 — completion 31 December 2026
- Avik Phase 1: RERA-GRG-1233-2022 — completion 30 April 2027
- Already showing an OC/CC/PCC link on the register: Drisha 1B, RERA-GRG-1011-2022
- Our page: Birla Navya; full sector list: Sector 63A Gurgaon Ready to Move Projects: Possession 2026-27
Samsara Avasa and Samsara Vilasa & Arya, Sector 63
Samsara is the Adani Realty and Brahma low-rise floors community (promoter on HRERA: Adani Brahma Synergy Pvt Ltd). On 20 November 2026 both registrations showed a “View OC/CC/PCC” link on the HRERA register, which usually means part of the project has a certificate. Open it to see which blocks are covered before you assume a unit is ready.
- Samsara Avasa: RERA-GRG-1150-2022 — Block L, Sector 63 — completion 31 December 2026
- Samsara Vilasa & Samsara Arya: RERA-GRG-985-2021 — completion 31 December 2026
- Later phases: Samsara Ivana RERA-GRG-1787-2024 (30 June 2029) and Ivana 2.0 RERA-GRG-2024-2025 (30 September 2030) — Adani Samsara Ivana 2.0
Emaar Emerald Hills Phase 2, Sectors 62 and 65
A plotted phase of Emaar’s Emerald Hills community. Buyers get a residential plot and build their own home, so “possession” here means handover of a developed plot with roads, services and parks complete.
- RERA no.: RERA-GRG-1342-2023 (registered 8 May 2023)
- HRERA completion date: 10 August 2027
- REP-I: 474 plots on about 50.6 acres; the largest groups are 188 plots of 50.40 sq m, 62 of 151.20 sq m, 30 of 151.97 sq m and 22 of 219.60 sq m
- Our page: Emaar Emerald Hills
Emaar Marbella Phases 2 and 7, Sectors 65 and 66
Marbella is Emaar’s villa community on Golf Course Extension Road. Both phases in this window are registered as plotted phases: HRERA lists plots and no apartments.
- Marbella Phase 2: RERA-GRG-755-2020 — 136 plots on 12.61 acres (sizes 50.16–595.91 sq m, including 22 plots of about 292–296 sq m) — HRERA completion 31 December 2027
- Marbella Phase 7: RERA-GRG-2230-2026 (registered 5 August 2026) — 12 plots of 298.99–418.03 sq m on 2.59 acres
- Note on Phase 7: the HRERA register shows 31 December 2026, while the REP-I form shows a likely completion of 31 December 2031. Ask Emaar which date is in your agreement.
- Marbella Terraces (RERA-GRG-2228-2026, 31 December 2031) is a separate, later plotted phase: its REP-I lists 247 plots and no apartments — Marbella Terraces
- Our page: Emaar Marbella
Luxury projects often quoted for 2027 that HRERA dates later
Several ranking pages put these projects in 2027. On 20 November 2026 the HRERA register showed the following completion dates. Ordered by date.
- Godrej Aristocrat, Sector 49 — RERA-GRG-1480-2023 — 31 December 2030 — Godrej Aristocrat; Godrej Aristocrat, Sector 49: Review 2026 - Price, Pros, Cons and Who It Suits
- M3M Altitude, Sector 65 — RERA-GRG-1607-2024 — 31 July 2031 — M3M Altitude; M3M Altitude Sector 65 Gurugram: Price, RERA, Possession 2026
- The Dahlias (DLF), Sector 54 — RERA-GRG-1690-2024 — 31 December 2031 — DLF The Dahlias
- Trump Residences Gurgaon, Sector 69 — RERA-GRG-1850-2025 — 30 September 2032 — Trump Residences Gurgaon
What does “possession 2027” mean on HRERA?
The completion date on the HRERA register is the date the promoter declared for finishing the registered phase. Possession for an apartment follows the occupation certificate (OC); for a plotted phase it follows the completion certificate for development works. The builder-buyer agreement may give its own possession date and grace period, so read both.
- Search the RERA-GRG number on the HRERA Gurugram register and note the completion date.
- Open “View OC/CC/PCC”. If a certificate is uploaded, check which towers, blocks or plots it names.
- Open the quarterly progress report to see the latest construction and spending figures filed.
- Ask the developer for the offer-of-possession timeline and the final demand, then cost it with /calculators/gurgaon-total-cost.
- For homes already complete, see Ready-to-Move Luxury Homes in Bangalore, Gurgaon and Chennai (2026): No GST, No Waiting; for the whole corridor, Golf Course Extension Road Possession 2027: HRERA List and Golf Course Extension Road, Gurgaon.