Five HRERA-registered residential phases in Sector 63A, Gurgaon list a completion date between 31 December 2026 and 30 April 2027: Birla Navya Anaika, Anant Raj’s Ashok Estate, two Signature Global City 63A floor registrations at Kadarpur, and Birla Navya Avik Phase 1. A sixth, Adani x Brahma’s Samsara Avasa next door in Sector 63, lists 31 December 2026. Two older Sector 63A projects already show completion papers on the register, so they are the truly ready-to-move options.

Updated 20 November 2026. We read every Sector 63A row of the HRERA Gurugram register of registered projects on 20 November 2026 and noted each registration number, promoter name, completion date and whether an OC/CC/PCC (occupation, completion or part-completion certificate) link is shown. Registrations no longer active are left out. Resale prices are not given because we could not verify them from an official source.

Sector 63A projects nearing possession: summary table

Ordered by HRERA completion date. Format: Project — Promoter on HRERA — RERA no. — Type — HRERA completion date.

  • Birla Navya (Anaika) — Avarna Projects LLP (Birla Estates) — RERA-GRG-1012-2022 — low-rise homes — 31 December 2026
  • Ashok Estate — Anant Raj Ltd — RERA-GRG-1085-2022 — residential — 31 December 2026
  • Samsara Avasa (Sector 63, Block L) — Adani Brahma Synergy Pvt Ltd — RERA-GRG-1150-2022 — low-rise floors — 31 December 2026
  • Signature Global City 63A — Signatureglobal (India) Ltd — RERA-GRG-1023-2022 — independent floors (DDJAY) — 24 February 2027
  • Signature Global City 63A (1) — Signatureglobal (India) Ltd — RERA-GRG-1063-2022 — independent floors (DDJAY) — 26 February 2027
  • Birla Navya (Avik Phase 1) — Avarna Projects LLP (Birla Estates) — RERA-GRG-1233-2022 — low-rise homes — 30 April 2027
  • Already complete on the register: Signatureglobal Prime (RERA-GRG-321-2019, marked completed, OC/CC/PCC link shown) and Birla Navya Drisha 1B (RERA-GRG-1011-2022, OC/CC/PCC link shown).

Birla Navya Anaika, Sector 63A

Anaika is one of the low-rise pockets of Birla Navya, the Birla Estates community on Golf Course Extension Road. HRERA lists it under Avarna Projects LLP with registration GGM/596/328/2022/71 dated 27 July 2022.

Birla Navya Avik Phase 1, Sector 63A

Avik Phase 1 sits on land in villages Kadarpur, Maidawas and Ullahwas, per the HRERA address. A separate Avik Phase 2 (RERA-GRG-1829-2024) lists 30 April 2030, so check which phase a resale unit belongs to before you compare dates.

  • RERA no.: RERA-GRG-1233-2022 (registered 23 January 2023)
  • HRERA completion date: 30 April 2027
  • Later phase: Avik Phase 2, RERA-GRG-1829-2024, completion 30 April 2030
  • Our page: Birla Navya

Ashok Estate (Anant Raj), Sector 63A

Ashok Estate is the phase most portal lists miss. HRERA registered it to Anant Raj Ltd on 18 July 2022. Anant Raj also has newer Sector 63A registrations with later dates, which helps you avoid mixing them up when reading listings.

  • RERA no.: RERA-GRG-1085-2022
  • HRERA completion date: 31 December 2026
  • Other Anant Raj Sector 63A registrations: Anant Raj Estate plots RERA-GRG-2043-2025 (31 December 2030), The Estate Residences RERA-GRG-1423-2023 (31 March 2030), The Estate One RERA-GRG-2197-2026 (21 July 2033)
  • Related pages: Anant Raj Estate, Anant Raj The Estate Residences, Anant Raj The Estate One

Signature Global City 63A (Kadarpur), Sector 63A

Signature Global City 63A is a Deen Dayal Jan Awas Yojana (DDJAY) independent-floor colony at village Kadarpur. It has two live registrations with dates two days apart. Each floor’s builder-buyer agreement names its registration, so match the number before you rely on a date.

  • RERA-GRG-1023-2022 (registered 31 March 2022): completion 24 February 2027
  • RERA-GRG-1063-2022 (registered 27 June 2022): completion 26 February 2027
  • Format: independent floors on DDJAY plots
  • Our page: Signature Global City 63A

Samsara Avasa, Sector 63 (next door)

Portal pages often put Samsara under Sector 63A. HRERA lists Samsara Avasa at Block L, Sector 63, village Ullahawas. The register already shows an OC/CC/PCC link for this registration, which usually means part of the project has received a certificate; open it to see which towers or floors it covers.

  • RERA no.: RERA-GRG-1150-2022 (Adani Brahma Synergy Pvt Ltd)
  • HRERA completion date: 31 December 2026
  • Sister registration: Samsara Vilasa and Samsara Arya, RERA-GRG-985-2021, completion 31 December 2026 (HRERA address Plot 83, Sector 32)
  • Our pages: Adani Samsara Vilasa and Adani Samsara Ivana 2.0 (Ivana 2.0, RERA-GRG-2024-2025, completion 30 September 2030)

Which Sector 63A projects are actually ready to move?

“Ready to move” on a portal is a sales label. The legal test in Haryana is an occupation certificate (OC) for your tower or floor, followed by the builder’s offer of possession. On 20 November 2026 two Sector 63A residential registrations showed completion papers on the HRERA register: Signatureglobal Prime (RERA-GRG-321-2019), which is marked completed, and Birla Navya Drisha 1B (RERA-GRG-1011-2022), which shows an OC/CC/PCC link. Samsara Avasa in Sector 63 also shows that link.

The five phases in the table above are “nearing possession”: construction is under way and the completion date on HRERA is the promoter’s own declared deadline. A unit in these phases becomes ready to move only once its OC is granted. If you need to move in by a fixed date, ask for the OC copy, not a brochure date.

How do I check the OC and possession status on HRERA?

  • Open the HRERA Gurugram register of registered projects (haryanarera.gov.in, “Registered Projects”, Gurugram) and search the project name or RERA-GRG number.
  • Read the completion date column. This is the date the promoter declared; an extension, if any, shows up through the “View Corrigendum” link.
  • Look for the “View OC/CC/PCC” link. If it is present, open the certificate and note which towers, floors or plots it covers. A part-completion certificate may not include your unit.
  • Open “View” under quarterly progress reports (QPR) to see the latest construction and spending figures the promoter has filed.
  • For the Haryana procedure behind an occupation certificate, see the DTCP page “Procedure for CLU/Building Plan/Occupation Certificate”. The DTCP homepage has no public OC search, so the HRERA link and the builder’s copy are your practical checks.
  • Ask the builder for the offer-of-possession letter, the final statement of dues and the conveyance-deed timeline.

Buying a nearing-possession unit on resale: what to check

Most homes in these phases are sold, so a 2026-27 purchase is usually a resale of an allotment. The builder must endorse the transfer in its records before possession, and the buyer takes on the original builder-buyer agreement and its RERA date.

  • Match the RERA number on the allotment letter with the HRERA register entry above.
  • Get the builder’s no-dues letter and the transfer (endorsement) charges in writing before you pay a token.
  • Check the DDJAY floor number and plot number in Signature Global City 63A; each floor is a separate unit.
  • Check the loan sanction letter covers an under-construction resale, and that the bank has approved the project.
  • Budget stamp duty and registration for the final conveyance deed; our calculator at /calculators/gurgaon-total-cost shows the full cost.

Later Sector 63A phases (possession 2030 and beyond)

If your timeline is longer, these Sector 63A registrations list later completion dates on the HRERA register. Ordered by date.