Eight DDJAY independent-floor colonies and phases in Gurgaon carry HRERA completion dates between 30 December 2026 and 30 November 2027, from Signature Global, M3M and Smartworld in Sectors 37D, 63A, 79, 79B, 89 and 93. DLF's Independent Floors at Gardencity Enclave, Sector 93, a licensed colony outside DDJAY, is due 19 August 2027.
Updated 20 November 2026. We read each registration's completion date and occupation certificate (OC) link on the HRERA Gurugram register, opened the HRERA forms for plot and floor counts, and re-read the Deen Dayal Jan Awas Yojana (DDJAY) 2016 notification. Prices are not shown because no builder price could be verified today.
DDJAY floors in Gurgaon due by 2027: summary
Ordered by HRERA completion date. Format: project — sector — HRERA no. — HRERA completion — OC record on register.
- 8.71-acre DDJAY plotted colony (Loon Land Development) — 79 — RERA-GRG-1241-2022 — 30 Dec 2026 — none yet
- Signature Global City 37D Extn. — 37D — RERA-GRG-1784-2024 and 1803-2024 — 31 Jan 2027 — none yet
- Signature Global City 63A — 63A (Kadarpur) — RERA-GRG-1023-2022 and 1063-2022 — 24 and 26 Feb 2027 — none yet
- M3M Soulitude 2 — 89 — RERA-GRG-1309-2023 — 3 Apr 2027 — OC/CC/PCC record uploaded
- Smartworld Gems 2 — 89 — RERA-GRG-1308-2023 — 3 Apr 2027 — none yet
- Sector 89 DDJAY plotted colony (Adhikaansh Realtors and Aawam Residency) — 89 — RERA-GRG-1307-2023 and 920-2021 — 3 Apr and 30 Oct 2027 — record uploaded for 920-2021
- Signature Global City 79B — 79B (Naurangpur) — RERA-GRG-1200-2022 — 27 Apr 2027 — none yet
- Signature Global City 93 — 93 (Wazirpur) — RERA-GRG-1281-2023 and 1283-2023 — 28 Apr and 30 Nov 2027 — none yet
- Separate box, licensed colony: Independent Floors at DLF Gardencity Enclave — 93 — RERA-GRG-1060-2022 — 19 Aug 2027 — none yet
What is a DDJAY colony, and why are there two kinds of registration?
DDJAY is Haryana's Affordable Plotted Housing Policy of 2016. A colony has a net planned area of 5 to 15 acres, plots of up to 150 sq m, a density of 240–400 persons per acre and an FAR of 2.0 on each plot. At least 7.5% must be organised open space and 10% of the licensed area goes free to the government for community facilities. The policy allows stilt parking and ‘registration of independent floors in plots’, which is why builders sell floors here.
The colony itself must be completed within seven years (5+2) of the licence. Some builders register the plotted colony on HRERA and the floors built on it as separate projects, each with its own completion date. In Sector 89, for example, the plotted colony is RERA-GRG-1307-2023 and 920-2021, while M3M Soulitude 2 and Smartworld Gems 2 are separate floor registrations.
Loon Land 8.71-acre DDJAY colony, Sector 79
RERA-GRG-1241-2022, ‘8.7111 acres DDJAY residential plotted colony’, promoter Loon Land Development Ltd, which is also the HRERA promoter of M3M Antalya Hills Phase 1 in the same sector. HRERA completion: 30 December 2026. Antalya Hills page: M3M Antalya Hills
Signature Global City 37D Extn., Sector 37D
Two registrations dated 28 March 2025 on village Gadauli Kalan land: RERA-GRG-1784-2024 (GGM/931/663/2025/34) and RERA-GRG-1803-2024 (GGM/930/662/2025/33), both with HRERA completion on 31 January 2027. Signature Global has other City 37D registrations due in January–February 2027 (RERA-GRG-1824-2024, 1022-2022 and 1061-2022); match your floor to its number. Sector page: Sector 37d Gurgaon, Gurgaon
Signature Global City 63A, Sector 63A
RERA-GRG-1023-2022 (GGM/546/278/2022/21, 31 March 2022) covers 72 plots of 106.65 to 149.74 sq m on 5.01 acres under licence 110 of 2021, with HRERA completion on 24 February 2027. A second registration, RERA-GRG-1063-2022, runs to 26 February 2027. Our page: Signature Global City 63A
M3M Soulitude 2, Sector 89
RERA-GRG-1309-2023, certificate GGM/859/591/2024/86 dated 12 August 2024, promoter Aawam Residency. The HRERA form lists 658 floor units on 6.64 acres, part of a 57.4-acre licensed area, with construction from 3 April 2024. HRERA completion: 3 April 2027. The register row shows an OC/CC/PCC record. Our page: M3M Soulitude
Smartworld Gems 2, Sector 89
RERA-GRG-1308-2023, certificate GGM/858/590/2024/85 dated 12 August 2024, promoter Adhikaansh Realtors. HRERA completion: 3 April 2027. Our page: Smartworld Gems
Sector 89 DDJAY plotted colony
The colony under Soulitude and Gems is registered jointly by Adhikaansh Realtors and Aawam Residency as RERA-GRG-1307-2023 (completion 3 April 2027) and RERA-GRG-920-2021 (30 October 2027, with an OC/CC/PCC record on the register). Colony works such as roads and services are tracked under these numbers. Sector page: Sector 89 Gurgaon, Gurgaon
Signature Global City 79B, Sector 79B
RERA-GRG-1200-2022, certificate GGM/656/388/2022/131 dated 23 December 2022, promoter JMK Holdings, village Naurangpur. HRERA completion: 27 April 2027. Our page: Signature Global City 79B
Signature Global City 93, Sector 93
Two registrations dated 30 January 2023 by Signature Builders Pvt Ltd on village Wazirpur land. RERA-GRG-1281-2023 covers 251 plots, most of about 150 sq m, on 17.32 acres, with HRERA completion on 28 April 2027. RERA-GRG-1283-2023 runs to 30 November 2027. Portals show anything from June 2026 to December 2027 for ‘City 93’; the date depends on which registration your floor sits in. Our page: Signature Global City 93
Independent Floors at DLF Gardencity Enclave, Sector 93 (licensed colony)
RERA-GRG-1060-2022, certificate GGM/603/335/2022/78 dated 17 August 2022, DLF Ltd. This is a licensed plotted colony (licence 94 of 2021 over 26.92 acres), not DDJAY. The HRERA form lists 97 plots of 132.6 to 150 sq m on 3.57 acres for the floors. HRERA completion: 19 August 2027. Our page: Independent Floors At DLF Gardencity Enclave
How do possession and registry work for a DDJAY floor?
- Colony completion: the builder finishes internal roads, water, sewer and power under the colony licence. Half of the saleable plot area stays frozen by the department until internal development works are done.
- Building plan and OC: each plot's floors are built under an approved building plan, and an occupation certificate is issued for the building. On HRERA, a ‘View OC/CC/PCC’ link appears on the row when one is uploaded.
- Offer of possession: after the OC, the builder sends a final demand; Section 19(10) of the RERA Act asks you to take possession within two months.
- Floor-wise registry: the DDJAY policy allows independent floors to be registered separately. The steps and stamp duty are explained in Builder Floor Registry in Gurgaon: Floor-Wise Registration 2026
- Parking: stilt parking is allowed under the policy; check which stilt bay is allotted to your floor in the agreement.
How do I check a DDJAY floor project on HRERA?
- Search the RERA-GRG number on the HRERA Gurugram register and read ‘Registration up to’.
- Open the form: a plotted registration lists plots and sizes; a floors registration lists floor units. Ask which one your sale agreement cites.
- Note the licence number and date on the form; DDJAY colonies must be completed within seven years of licence.
- Read the quarterly progress report for the colony and for your building.
- More on DDJAY: DDJAY Plots in Gurgaon 2026: Sectors, Prices, Rules and floors near the Expressway: Independent Floors Near Dwarka Expressway 2026: HRERA List