In Haryana, permission to change land use (CLU) in a controlled area is granted by the Director General, Town and Country Planning (DTCP), under the Punjab Scheduled Roads and Controlled Areas Act, 1963. You apply online at ofa.tcpharyana.gov.in (e-CLU) with a scrutiny fee of ₹10 per sq m of the site's gross area. TCP's Right to Service list sets 60 days for a CLU in a conforming zone of the final development plan. On grant, you pay conversion charges from the schedule notified on 16 April 2025. In the Gurgaon-Manesar Urban Complex these are ₹105–₹210 per sq m for residential use and ₹1,050–₹1,470 per sq m for ordinary commercial use up to 150% FAR, depending on the road the site fronts.

Updated 18 November 2026. We opened the TCP Haryana website (CLU form page, CLU cases list, the CLU workflow and checklist, the RTS services list), the e-CLU handbook, and the Haryana Government Gazette of 16 April 2025 that replaced Schedule IV (conversion charges) of the 1965 Rules. The Urban Local Bodies department's CLU page returned ‘Page Not Found’ on 18 November 2026.

Who grants CLU in Gurgaon: DTCP, ULB or GMDA?

  • Inside a notified controlled area (the jamabandi.nic.in menu links TCP's controlled-area and urban-area lists): the DTCP. TCP's RTS list names the Director General, Town & Country Planning as designated officer for ‘change of land use permission’, at 60 days.
  • Outside a controlled area but inside a notified urban area: TCP issues an NOC, at 30 days, with the Senior Town Planner as designated officer.
  • Outside both: TCP NOC at 10 days, through the District Town Planner.
  • Inside municipal limits: check with the municipal body as well. The ULB department runs a separate CLU page, which was offline when we checked.
  • For who does what among GMDA, MCG, HSVP, DTCP and HRERA, see GMDA Full Form and Gurgaon Authorities: MCG, HSVP, DTCP, HRERA.

How do you apply for CLU online in Haryana?

TCP's e-CLU handbook (version 2.0) and workflow PDF describe this sequence:

  • Register as a new user on ofa.tcpharyana.gov.in. The password is emailed to you.
  • File a new CLU application in six steps: basic and payment details; applicant and contact person; address; site parameters; ownership and land details; final submission. Pay the scrutiny fee online by net banking, debit card or credit card.
  • Attach the checklist documents: Form CLU-I, a survey plan at 1 inch to 40 feet showing access, your title deed, jamabandi, mutation and aks shajra from the halka patwari, the project cost and report, means of finance, and use-specific papers. Use-specific papers include NHAI or PWD (B&R) access permission for sites on national highways or scheduled roads, MSME registration and a pollution NOC for industry, a DC's genuineness certificate for institutions, and an oil company LOI for fuel stations.
  • The field DTP inspects the site and the circle office reports to headquarters. If the site meets the policy and falls in a conforming zone of the final development plan, DTCP issues a Letter of Intent (LOI). Cases needing relaxation go to the government.
  • Within 30 days of the LOI, pay the fees and charges and submit the agreement (Form CLU-II) and undertakings. DTCP then grants the CLU (Form CLU-III is the grant or refusal).
  • Track progress and reports in your e-CLU dashboard. The system also sends SMS and email updates at key events.

How long does CLU take?

TCP's RTS list gives 60 days for CLU in controlled areas. Its published internal workflow is tighter: 37 days from application to LOI or rejection (basic scrutiny, field report, circle report, headquarters examination, DTCP approval), then 22 days from LOI compliance to final grant. Clock time starts only when the application is complete, so missing revenue papers are the usual cause of delay.

What are the CLU conversion charges in Gurgaon?

Schedule IV was replaced by the Haryana Government Gazette (Extraordinary) No. 70-2025 of 16 April 2025. Rates are in ₹ per sq m and vary by potential zone and frontage (national highway, scheduled road or sector road, or other road). The ‘hyper potential’ zone is the controlled area forming part of the Gurgaon-Manesar Urban Complex development plan:

  • Residential: ₹210 (NH) / ₹158 (scheduled or sector road) / ₹105 (other road).
  • Commercial projects such as motels, five-star hotels and resorts with banquet halls (150% FAR): ₹4,700 / ₹4,500 / ₹4,300.
  • Other commercial up to 150% FAR: ₹1,470 / ₹1,260 / ₹1,050. Above 150% FAR: ₹1,715 / ₹1,470 / ₹1,225.
  • Institutional: ₹158 / ₹126 / ₹105. Industrial: ₹100. Recreational: ₹200.
  • Warehousing: ₹100 for agricultural produce, ₹150 for non-agricultural.
  • Other Gurugram district controlled areas (Pataudi, Farrukhnagar, Sohna development plan areas) fall in the ‘high potential’ zone. There residential is ₹158 / ₹125 / ₹105 and other commercial up to 150% FAR is ₹1,260 / ₹1,050 / ₹840.
  • Notes in the gazette: where a site spans two categories, the higher rate applies. Registered renewable-energy projects pay no conversion charges or scrutiny fees.

Worked example: a 1,000 sq m commercial site on a sector road in the Gurgaon-Manesar controlled area, built to 150% FAR, pays a ₹10,000 scrutiny fee (1,000 × ₹10) and ₹12,60,000 in conversion charges (1,000 × ₹1,260). That is ₹12.7 lakh before any other fees the LOI lists. The same plot for a school on an internal road would pay 1,000 × ₹105 = ₹1,05,000 in conversion charges.

How do you check a CLU before buying a plot, shop or farmhouse?