NHAI has floated a ₹614 crore tender for the remaining 14 km of the Chennai–Bengaluru Expressway in Tamil Nadu, where 92 of 106 km is complete (DT Next, 30 October 2026). DT Next says a contractor will be chosen shortly and the work is expected to take about four months. The Tamil Nadu gap is in the Arakkonam–Kancheepuram stretch; no official opening date has been given for the full expressway.

Updated 8 November 2026. We read DT Next's 30 October and 3 September 2026 reports and the expressway's package list. The two reports give different costs and durations for the remaining work; we show both.

Status of the expressway by section

  • Total: 263 km, estimated cost ₹18,000 crore; about 230 km complete (DT Next, 30 October 2026).
  • Karnataka: the 71 km Hoskote–Bethamangala stretch is complete and open to traffic.
  • Andhra Pradesh and the AP–Tamil Nadu border sections: about 90% complete.
  • Tamil Nadu: 92 of 106 km complete; 14 km remaining.
  • Arakkonam–Kancheepuram (25 km): the first 11 km is complete, according to officials quoted by DT Next.
  • Travel time once complete: about 3 hours between Chennai and Bengaluru, down from 5 to 7 hours (DT Next, 30 October 2026).

The four Tamil Nadu packages

Package names and lengths from Wikipedia's expressway page (read 8 November 2026); together they make up the 106 km Tamil Nadu section. The expressway ends at Sriperumbudur, where it meets NH 48.

  • Gudipala–Walajapettai: 24.0 km
  • Walajapettai–Arakkonam: 24.5 km
  • Arakkonam–Kanchipuram: 25.5 km (Km 204.500 near Arakkonam to Km 230 in Kancheepuram district; 17.4 km in Ranipet district and 8.1 km in Kancheepuram district, per DT Next, 3 September 2026). This is where the remaining work lies.
  • Kanchipuram–Sriperumbudur: 32.1 km

Two reports, two numbers

  • DT Next, 3 September 2026: NHAI invited fresh EPC bids for the 25.5 km Arakkonam–Kancheepuram section, with a balance cost of ₹633.12 crore and an 18-month construction period plus five years' maintenance; 11.03 km (53%) had been completed when work stopped in May 2025.
  • DT Next, 30 October 2026: a ₹614 crore tender for the remaining 14 km, to be completed in about four months after the contractor is selected.
  • Our reading: both describe the unfinished part of the same package (25.5 km less about 11 km done is about 14 km). The 30 October figure is the later one. A four-month build for 14 km is far shorter than the 18 months in the September tender, so treat it with caution until NHAI publishes the award and schedule.
  • Wikipedia, citing ThePrint (13 June 2026), records that completion of the remaining sections had moved to early 2027.

What it means for the Sriperumbudur–Oragadam belt

The Chennai end at Sriperumbudur is on NH 48, close to the Oragadam industrial belt. A continuous expressway would give this area a direct high-speed road towards Ranipet, Vellore and Bengaluru. TNRERA-registered layouts in our catalogue in this belt:

  • Sriperumbudur: G Square Kings Haven (plots), TNRERA/1/LO/2645/2026 (G Square Kings Haven).
  • Oragadam: Hiranandani Tierra (plots), TN/01/Layout/0395/2024 (Hiranandani Tierra); Godrej Sunrise Estate (plots), TN/01/Layout/3492/2023 (Godrej Sunrise Estate).
  • We have not measured each layout's distance to an expressway entry point; interchange locations in Tamil Nadu are not listed in the sources we read.

What is not decided yet

  • The contractor and award date for the remaining 14 km.
  • An official opening date for the Tamil Nadu section or the full expressway.
  • The proposed 11th package from Sriperumbudur to Maduravoyal in Chennai, which Wikipedia describes as planned, not approved.

What to do now

  • 1. Drivers: the open sections can be used now; the Karnataka side, exits and toll are covered at Bangalore Chennai Expressway Opening Date: Hoskote Side.
  • 2. Plot buyers near Sriperumbudur or Oragadam: price the land on today's access (NH 48), not on a full expressway opening, until NHAI announces the award and schedule.
  • 3. Check DTCP or CMDA approval and the TNRERA number of any layout before paying an advance; compare listings at Plots, Chennai and Oragadam, Chennai.
  • 4. Watch for NHAI's award of the 14 km contract: the reported four-month clock starts from it.